Davis-Bacon wage rates · New Jersey
Mercer County building construction wage rates
Federal prevailing wage rates for building construction in Mercer County, New Jersey, from the wage determination SAM.gov lists for this county. Rates are shown exactly as published.
- Wage determination
- NJ20260035
- Modification
- 2
- Published
- May 18, 2026
- Classifications
- 43
- Other types here
- Residential, Heavy, Highway
These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See New Jersey prevailing wage for how the two fit together.
WD NJ20260035, Mod 2
Make a WH-347 with these rates| Classification | Rate ID | Base | Fringe | Total / hour |
|---|---|---|---|---|
ASBESTOS REMOVAL LABORER The removal, abatement, enclosure and decontamination of personal protective equipment, chemical protective clothing and machinery relating to asbestos and/or toxic and hazard...ASBESTOS REMOVAL LABORER The removal, abatement, enclosure and decontamination of personal protective equipment, chemical protective clothing and machinery relating to asbestos and/or toxic and hazardous waste or materials which shall include but not necessarily be limited to: the erection, moving, servicing and dismantling of all enclosures, scaffolding and barricades; the operation of all tools and equipment normally used in the removal or abatement of asbestos and toxic or hazardous waste or materials; the labeling, bagging, cartoning, crating, or other packaging of materials for disposal; the clean-up of the worksite; and all other work incidental to the removal, abatement, encapsulation, enclosure, and decontamination of asbestos and toxic or hazardous waste or materials; and, in addition, all work tasks involved in the maintenance and operation of energy resource recovery plants (co-generation plants) | LABO0008-001 05/01/2011 | $28.37 | $21.62 | $49.99 |
ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of...ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead | ASBE0089-004 07/01/2025 | $55.80 | $40.80 | $96.60 |
| BRICKLAYER Work on high stacks: 22% per hour additional | BRNJ0002-013 05/01/2021 | $45.20 | $33.26 | $78.46 |
| CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING AND FORMWORK) | CARP0006-011 05/01/2025 | $57.42 | $34.17 | $91.59 |
| CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter | CARP0006-009 05/01/2025 | $57.42 | $34.17 | $91.59 |
| CEMENT MASON/CONCRETE FINISHER | PLAS0592-036 05/01/2025 | $53.21 | $33.42 | $86.63 |
| DRYWALL FINISHER/TAPER | PAIN0711-018 05/01/2025 | $44.87 | $30.15 | $75.02 |
| ELECTRICIAN (INCLUDES LOW VOLTAGE WIRING) | ELEC0269-016 01/05/2026 | $63.82 | $41.99 | $105.81 |
| ELECTRICIAN: CABLE SPLICER | ELEC0269-016 01/05/2026 | $68.02 | $44.04 | $112.06 |
| ELEVATOR MECHANIC Footnote A, B below | ELEV0005-004 01/01/2025 | $71.85 | $38.44 | $110.29 |
GLAZIER WORK WELDING OR USING A CUTTING TORCH: $1.00 PER HOUR ADDITIONAL. WORK ON A SWING STAGE SCAFFOLD; ON A PIPE SCAFFOLD PROVIDING THE WORKING HEIGHT OF THE PLATFORM IS 30 FT. OR ABOVE; AND ON MOT...GLAZIER WORK WELDING OR USING A CUTTING TORCH: $1.00 PER HOUR ADDITIONAL. WORK ON A SWING STAGE SCAFFOLD; ON A PIPE SCAFFOLD PROVIDING THE WORKING HEIGHT OF THE PLATFORM IS 30 FT. OR ABOVE; AND ON MOTORIZED LIFTS PROVIDED THAT THE HEIGHT OF THE LIFT PLATFORM IS ABOVE THE SECOND FLOOR OR ABOVE THIRTY FEET: $1.00 PER HOUR ADDITIONAL | PAIN0711-017 05/01/2025 | $52.68 | $31.29 | $83.97 |
| IRONWORKER: REINFORCING | IRON0399-016 07/01/2025 | $53.24 | $40.40 | $93.64 |
| IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER | IRON0399-016 07/01/2025 | $54.24 | $40.40 | $94.64 |
| LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, PIPELAYER, POWER TOOL OPERATOR AND SCREEDMAN | LABO0222-009 07/01/2012 | $29.35 | $23.07 | $52.42 |
| LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE | LABO0222-006 07/01/2012 | $29.85 | $23.07 | $52.92 |
| PAINTER (BRUSH & ROLLER) | PAIN0711-020 05/01/2025 | $45.55 | $29.86 | $75.41 |
| PAINTER (PAPERHANGER) | PAIN0711-020 05/01/2025 | $45.55 | $29.86 | $75.41 |
| PAINTER (SPRAY) | PAIN0711-020 05/01/2025 | $45.55 | $29.86 | $75.41 |
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (MERCER COUNTY (south of a line drawn from the point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then...PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (MERCER COUNTY (south of a line drawn from the point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then, south along Rt. 602 (also known as Hopewell - Wertsville Rd.) to the Borough of Hopewell, includes the Borough of Hopewell; then, east along the Reading Railroad to the Mercer/Somerset County line (Province Line Rd.)) | PLUM0009-016 07/01/2025 | $59.57 | $46.45 | $106.02 |
PIPEFITTER, INCLUDING HVAC PIPE INSTALLATION (MERCER COUNTY (north of a line drawn from point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then, s...PIPEFITTER, INCLUDING HVAC PIPE INSTALLATION (MERCER COUNTY (north of a line drawn from point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then, south along Rt. 602 (also known as Hopewell - Wertsville Rd.) to the Borough of Hopewell, includes the Borough of Hopewell; then, east along the Reading Railroad to the Mercer/Somerset County line (Province Line Rd.) | PLUM0475-010 05/01/2025 | $56.34 | $50.80 | $107.14 |
PIPEFITTER: SERVICE AND REPAIR (MERCER COUNTY (south of a line drawn from the point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then, south along...PIPEFITTER: SERVICE AND REPAIR (MERCER COUNTY (south of a line drawn from the point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then, south along Rt. 602 (also known as Hopewell - Wertsville Rd.) to the Borough of Hopewell, includes the Borough of Hopewell; then, east along the Reading Railroad to the Mercer/Somerset County line (Province Line Rd.)) | PLUM0009-016 07/01/2025 | $46.23 | $29.23 | $75.46 |
| PLASTERER | PLAS0008-007 05/01/2021 | $38.37 | $31.64 | $70.01 |
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (MERCER COUNTY (NORTH OF A LINE DRAWN FROM THE POINT AT WHICH RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) MEETS THE HUNTERDON/MERCER COUNTY LINE; THEN, S...PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (MERCER COUNTY (NORTH OF A LINE DRAWN FROM THE POINT AT WHICH RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) MEETS THE HUNTERDON/MERCER COUNTY LINE; THEN, SOUTH ALONG RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) TO THE BOROUGH OF HOPEWELL, INCLUDES THE BOROUGH OF HOPEWELL; THEN, EAST ALONG THE READING RAILROAD TO THE MERCER/SOMERSET COUNTY LINE (PROVINCE LINE RD.)) | PLUM0024-009 05/01/2025 | $62.09 | $45.05 | $107.14 |
PLUMBER, EXCLUDING HVAC PIPE INSTALLATION (MERCER COUNTY (south of a line drawn from the point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then, ...PLUMBER, EXCLUDING HVAC PIPE INSTALLATION (MERCER COUNTY (south of a line drawn from the point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then, south along Rt. 602 (also known as Hopewell - Wertsville Rd.) to the Borough of Hopewell, includes the Borough of Hopewell; then, east along the Reading Railroad to the Mercer/Somerset County line (Province Line Rd.)) | PLUM0009-016 07/01/2025 | $59.57 | $46.45 | $106.02 |
PLUMBER: SERVICE AND REPAIR (MERCER COUNTY (south of a line drawn from the point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then, south along Rt...PLUMBER: SERVICE AND REPAIR (MERCER COUNTY (south of a line drawn from the point at which Rt. 602 (also known as Hopewell - Wertsville Rd.) meets the Hunterdon/Mercer County line; then, south along Rt. 602 (also known as Hopewell - Wertsville Rd.) to the Borough of Hopewell, includes the Borough of Hopewell; then, east along the Reading Railroad to the Mercer/Somerset County line (Province Line Rd.)) | PLUM0009-016 07/01/2025 | $46.23 | $29.23 | $75.46 |
POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTAR...POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); TRENCHER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL | ENGI0825-020 07/01/2025 | $61.72 | $37.50 | $99.22 |
POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPE...POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL | ENGI0825-020 07/01/2025 | $60.13 | $37.50 | $97.63 |
POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC...POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR; HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL | ENGI0825-020 07/01/2025 | $58.22 | $37.50 | $95.72 |
POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDOUS WASTE REMOVAL WORK: ...POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL | ENGI0825-020 07/01/2025 | $56.59 | $37.50 | $94.09 |
POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND ...POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL | ENGI0825-020 07/01/2025 | $52.88 | $37.50 | $90.38 |
ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensin...ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour | ROOF0030-027 05/01/2025 | $46.03 | $34.27 | $80.30 |
ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine ...ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour | ROOF0030-027 05/01/2025 | $35.95 | $21.85 | $57.80 |
ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensin...ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour | ROOF0030-027 05/01/2025 | $38.95 | $21.85 | $60.80 |
| SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION) | SHEE0027-009 06/01/2024 | $59.08 | $47.06 | $106.14 |
| SPRINKLER FITTER: FIRE (Within 15 miles beyond the city limits of Philadelphia.) | SFNJ0692-002 05/01/2021 | $60.83 | $30.34 | $91.17 |
| SPRINKLER FITTER: FIRE SPRINKLERS (MERCER COUNTY (DOES NOT INCLUDE THE TOWN OF TRENTON)) | SFNJ0669-003 04/01/2025 | $59.19 | $36.51 | $95.70 |
| TILE FINISHER (MERCER COUNTY (NORTH OF ROUTE 33)) WORK GROUTING ALL EPOXY: $10.00 ADDITIONAL PER DAY | BRNJ0007-015 06/02/2025 | $50.05 | $33.90 | $83.95 |
| TILE FINISHER (MERCER COUNTY (SOUTH OF ROUTE 33)) WORK GROUTING ALL EPOXY: $10.00 ADDITIONAL PER DAY | BRNJ0007-018 06/02/2025 | $50.05 | $33.90 | $83.95 |
| TILE SETTER (MERCER COUNTY (NORTH OF ROUTE 33)) | BRNJ0007-015 06/02/2025 | $64.90 | $37.28 | $102.18 |
| TILE SETTER (MERCER COUNTY (SOUTH OF ROUTE 33)) | BRNJ0007-018 06/02/2025 | $64.90 | $37.28 | $102.18 |
TRUCK DRIVER: DUMP HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protecti...TRUCK DRIVER: DUMP HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level A, B or C personal protection: $1.00 per hour | TEAM0469-004 05/01/2025 | $48.63 | $42.66 | $91.29 |
TRUCK DRIVER: OFF THE ROAD HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal ...TRUCK DRIVER: OFF THE ROAD HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level A, B or C personal protection: $1.00 per hour | TEAM0469-004 05/01/2025 | $48.78 | $42.66 | $91.44 |
Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of bu...Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter. | CARP0715-007 05/01/2025 | $58.84 | $35.06 | $93.90 |
Footnotes in NJ20260035 (6)
- ASBE0089-004 NOTE: PAID HOLIDAYS: The last day prior to the Christmas and New Year's Day observed holiday: 4 hrs. pay
- ELEV0005-004 A: PAID VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% for 6 months to 5 years of
- ELEV0005-004 B: Eight Paid Holidays (provided employee has worked 5 consecutive days before and the working day after the holiday): New Years's Day; Memorial Day; Independence Day; Labor Day; Veteran's Day; Thanksgiving Day and the Friday after Thanksgiving Day, and Christmas Day
- ENGI0825-020 NOTE: PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY
- ROOF0030-027 NOTE: PAID HOLIDAY: The last working day before Christmas, to be paid at the rate of four hours pay
- TEAM0469-004 NOTE: PAID HOLIDAYS: New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas VACATION PAY CREDIT: Workers working or receiving pay for 80 days within a year receive one week paid vacation (48 hours); 125 days receive two weeks paid vacation (96 hours); 145 days receive 15 days paid vacation (120 hours); 15 years seniority and 145 days receive 4 weeks paid vacation (160 hours)
Questions about these rates
What is the Davis-Bacon rate for electricians on building work in Mercer County?
What is the Davis-Bacon rate for plumbers on building work in Mercer County?
What is the Davis-Bacon rate for carpenters on building work in Mercer County?
Which wage determination applies to my project?
What counts as building construction?
What if my worker's trade is not on the list?
Using these rates on a WH-347
Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.
Make this week's WH-347 with NJ20260035
Other counties: all New Jersey counties · WD lookup
Your first certified payroll is free.
Upload last week's payroll, get a checked WH-347 back today.
No card. Same full report, no watermark.