Davis-Bacon wage rates · New Jersey
Somerset County building construction wage rates
Federal prevailing wage rates for building construction in Somerset County, New Jersey, from the wage determination SAM.gov lists for this county. Rates are shown exactly as published.
- Wage determination
- NJ20260042
- Modification
- 2
- Published
- August 13, 2026
- Classifications
- 48
- Other types here
- Residential, Heavy, Highway
These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See New Jersey prevailing wage for how the two fit together.
WD NJ20260042, Mod 2
Make a WH-347 with these ratesSome rows apply only to an area or zone named in the classification. The area text is printed exactly as published; check it against your project's location before you use a row.
| Classification | Rate ID | Base | Fringe | Total / hour |
|---|---|---|---|---|
ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE APPLICATION OF...ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (SOMERSET COUNTY (BOROUGHS OF BERNARDSVILLE AND BOUND BROOK; TOWNSHIP OF BRIDGEWATER; BOROUGH OF FAR HILLS; TOWNSHIP OF GREEN BROOK; BOROUGHS OF NORTH PLAINFIELD, PEAPACK-GLADSTONE, RARITAN, SOMERVILLE, SOUTH BOUND BROOK AND WATCHUNG; TOWNSHIP OF WARREN) | ASBE0032-007 09/19/2024 | $51.74 | $46.20 | $97.94 |
ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE APPLICATION OF...ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (SOMERSET COUNTY (TOWNSHIPS OF BRANCHBURG, FRANKLIN, HILLSBOROUGH AND MONTGOMERY)) | ASBE0089-007 07/01/2024 | $55.80 | $40.80 | $96.60 |
| BRICKLAYER (WORK ON HIGH STACKS: 22% PER HOUR ADDITIONAL.) | BRNJ0002-013 05/01/2021 | $45.20 | $33.26 | $78.46 |
| CARPENTER: INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND BLOWN INSULATION | CARP0006-011 05/01/2025 | $57.42 | $34.17 | $91.59 |
| CARPENTER: SCAFFOLD BUILDER (THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER.) | CARP0006-009 05/01/2025 | $57.42 | $34.17 | $91.59 |
| CEMENT MASON | BRNJ0004-001 05/01/2025 | $49.60 | $37.96 | $87.56 |
| DRYWALL FINISHER/TAPER | PAIN0711-018 05/01/2025 | $44.87 | $30.15 | $75.02 |
ELECTRICIAN: CABLE SPLICER (INCLUDING LOW VOLTAGE WIRING) (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTER...ELECTRICIAN: CABLE SPLICER (INCLUDING LOW VOLTAGE WIRING) (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN RD.; THEN, WEST ALONG HARLINGEN RD. AND THE DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP LINE) (WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL.) (WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATE.) | ELEC0102-022 06/02/2025 | $69.72 | $44.27 | $113.99 |
ELECTRICIAN: CABLE SPLICER (INCLUDING LOW VOLTAGE WIRING) (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE...ELECTRICIAN: CABLE SPLICER (INCLUDING LOW VOLTAGE WIRING) (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE)) (WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR OVER CONVEYORS OR MOVING EQUIPMENT OR MACHINERY: 10% PER HOUR ADDITIONAL.) | ELEC0456-007 05/30/2022 | $65.35 | $46.56 | $111.91 |
ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO...ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN RD.; THEN, WEST ALONG HARLINGEN RD. AND THE DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP LINE) (WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL.) (WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATE.) | ELEC0102-022 06/02/2025 | $65.43 | $42.86 | $108.29 |
ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANC...ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE)) (WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR OVER CONVEYORS OR MOVING EQUIPMENT OR MACHINERY: 10% PER HOUR ADDITIONAL.) | ELEC0456-007 05/30/2022 | $55.85 | $39.79 | $95.64 |
ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY (WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER COUNTY LINE TO HARLI...ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY (WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN RD.; THEN, WEST ALONG HARLINGEN RD. AND THE DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP LINE))) | ELEC0269-019 07/07/2025 | $61.84 | $40.32 | $102.16 |
| ELEVATOR MECHANIC: ALL OTHER WORK Footnote NOTE below | ELEV0001-003 03/17/2013 | $57.01 | $27.61 | $84.62 |
ELEVATOR MECHANIC: WORK ON THE ADDITION, REPLACEMENT, REFURBISHING OR RELOCATION OF CONTROL, DRIVE, GENERATING EQUIPMENT, HOISTWAY OR PIT EQUIPMENT, INCLUDING WORK INVOLVING A STRUCTURAL RISE IN THE E...ELEVATOR MECHANIC: WORK ON THE ADDITION, REPLACEMENT, REFURBISHING OR RELOCATION OF CONTROL, DRIVE, GENERATING EQUIPMENT, HOISTWAY OR PIT EQUIPMENT, INCLUDING WORK INVOLVING A STRUCTURAL RISE IN THE ELEVATOR SHAFTS IN AN EXISTING BUILDING AND OTHER ELEVATOR WORK IN THE MACHINE ROOM, HOISTWAY OR PIT; ALSO, CHANGES IN DESIGN AND APPEARANCE OF BASIC ESCALATOR EQUIPMENT | ELEV0001-003 03/17/2013 | $45.14 | $27.46 | $72.60 |
GLAZIER (WORK WELDING OR USING A CUTTING TORCH: $1.00 PER HOUR ADDITIONAL.) (WORK ON A SWING STAGE SCAFFOLD; ON A PIPE SCAFFOLD PROVIDING THE WORKING HEIGHT OF THE PLATFORM IS 30 FT. OR ABOVE; AND ON ...GLAZIER (WORK WELDING OR USING A CUTTING TORCH: $1.00 PER HOUR ADDITIONAL.) (WORK ON A SWING STAGE SCAFFOLD; ON A PIPE SCAFFOLD PROVIDING THE WORKING HEIGHT OF THE PLATFORM IS 30 FT. OR ABOVE; AND ON MOTORIZED LIFTS PROVIDED THAT THE HEIGHT OF THE LIFT PLATFORM IS ABOVE THE SECOND FLOOR OR ABOVE THIRTY FEET: $1.00 PER HOUR ADDITIONAL.) | PAIN0711-021 05/01/2025 | $52.68 | $31.29 | $83.97 |
| IRONWORKER: REINFORCING (SOMERSET COUNTY (NORTHERN HALF OF COUNTY)) | IRON0011-010 07/01/2025 | $49.94 | $50.32 | $100.26 |
| IRONWORKER: REINFORCING (SOMERSET COUNTY (SOUTHERN HALF OF COUNTY)) | IRON0399-018 07/01/2024 | $53.24 | $38.40 | $91.64 |
| IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (SOMERSET COUNTY (NORTHERN HALF OF COUNTY)) | IRON0011-010 07/01/2025 | $52.24 | $50.32 | $102.56 |
| IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (SOMERSET COUNTY (SOUTHERN HALF OF COUNTY)) | IRON0399-018 07/01/2024 | $54.24 | $38.40 | $92.64 |
LABORER: ASBESTOS REMOVAL (THE REMOVAL, ABATEMENT, ENCLOSURE AND DECONTAMINATION OF PERSONAL PROTECTIVE EQUIPMENT, CHEMICAL PROTECTIVE CLOTHING AND MACHINERY RELATING TO ASBESTOS AND/OR TOXIC AND HAZA...LABORER: ASBESTOS REMOVAL (THE REMOVAL, ABATEMENT, ENCLOSURE AND DECONTAMINATION OF PERSONAL PROTECTIVE EQUIPMENT, CHEMICAL PROTECTIVE CLOTHING AND MACHINERY RELATING TO ASBESTOS AND/OR TOXIC AND HAZARDOUS WASTE OR MATERIALS WHICH SHALL INCLUDE BUT NOT NECESSARILY BE LIMITED TO: THE ERECTION, MOVING, SERVICING AND DISMANTLING OF ALL ENCLOSURES, SCAFFOLDING AND BARRICADES; THE OPERATION OF ALL TOOLS AND EQUIPMENT NORMALLY USED IN THE REMOVAL OR ABATEMENT OF ASBESTOS AND TOXIC OR HAZARDOUS WASTE OR MATERIALS; THE LABELING, BAGGING, CARTONING, CRATING, OR OTHER PACKAGING OF MATERIALS FOR DISPOSAL; THE CLEAN-UP OF THE WORKSITE; AND ALL OTHER WORK INCIDENTAL TO THE REMOVAL, ABATEMENT, ENCAPSULATION, ENCLOSURE, AND DECONTAMINATION OF ASBESTOS AND TOXIC OR HAZARDOUS WASTE OR MATERIALS; AND, IN ADDITION, ALL WORK TASKS INVOLVED IN THE MAINTENANCE AND OPERATION OF ENERGY RESOURCE RECOVERY PLANTS (CO-GENERATION PLANTS)) | LABO0008-001 05/01/2011 | $28.37 | $21.62 | $49.99 |
| LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, POWER TOOL OPERATOR AND SCREEDMAN | LABO0077-005 05/01/2022 | $35.75 | $30.22 | $65.97 |
| LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE | LABO0077-002 05/01/2022 | $36.50 | $30.22 | $66.72 |
MILLWRIGHT (WORK OF ERECTION AND DISMANTLING OF ELEVATORS AND TOWERS, SUCH AS CONCRETE CONVEYORS AND TEMPORARY MATERIAL ELEVATORS, SCAFFOLDING OR OTHER STRUCTURES TO BE USED AS SCAFFOLDING INSIDE OR O...MILLWRIGHT (WORK OF ERECTION AND DISMANTLING OF ELEVATORS AND TOWERS, SUCH AS CONCRETE CONVEYORS AND TEMPORARY MATERIAL ELEVATORS, SCAFFOLDING OR OTHER STRUCTURES TO BE USED AS SCAFFOLDING INSIDE OR OUTSIDE OF BUILDINGS: THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER.) | CARP0715-007 05/01/2025 | $58.84 | $35.06 | $93.90 |
| PAINTER: BRUSH AND ROLLER | PAIN0711-020 05/01/2025 | $45.55 | $29.86 | $75.41 |
| PAINTER: PAPERHANGER | PAIN0711-020 05/01/2025 | $45.55 | $29.86 | $75.41 |
| PAINTER: SPRAY | PAIN0711-020 05/01/2025 | $45.55 | $29.86 | $75.41 |
| PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | PLUM0475-012 05/01/2025 | $56.34 | $50.80 | $107.14 |
| PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | PLUM0009-020 07/01/2025 | $59.57 | $46.45 | $106.02 |
| PLASTERER | PLAS0008-008 05/01/2021 | $38.37 | $31.64 | $70.01 |
| PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | PLUM0024-011 05/01/2025 | $62.09 | $45.05 | $107.14 |
| PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | PLUM0009-020 07/01/2025 | $59.57 | $46.45 | $106.02 |
| PLUMBER/PIPEFITTER: SERVICE AND REPAIR (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL)) | PLUM0009-020 07/01/2025 | $46.23 | $29.23 | $75.46 |
POWER EQUIPMENT OPERATOR: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY...POWER EQUIPMENT OPERATOR: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); TRENCHER (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.) | ENGI0825-020 07/01/2025 | $61.72 | $37.50 | $99.22 |
POWER EQUIPMENT OPERATOR: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER...POWER EQUIPMENT OPERATOR: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.) | ENGI0825-020 07/01/2025 | $60.13 | $37.50 | $97.63 |
POWER EQUIPMENT OPERATOR: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC;...POWER EQUIPMENT OPERATOR: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.) | ENGI0825-020 07/01/2025 | $58.22 | $37.50 | $95.72 |
POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC (HAZARDOUS WASTE REMOVAL WORK: ...POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.) | ENGI0825-020 07/01/2025 | $56.59 | $37.50 | $94.09 |
POWER EQUIPMENT OPERATOR: GROUP 5 OILER (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND ...POWER EQUIPMENT OPERATOR: GROUP 5 OILER (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.) | ENGI0825-020 07/01/2025 | $52.88 | $37.50 | $90.38 |
ROOFER: ALL OTHER WORK (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY L...ROOFER: ALL OTHER WORK (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR ADDITIONAL.) | ROOF0030-029 05/01/2025 | $46.03 | $34.27 | $80.30 |
| ROOFER: ALL TYPES (SOMERSET COUNTY (NORTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE ALONG ROUTE #206 NORTH TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE)) | ROOF0004-004 06/01/2024 | $44.52 | $32.25 | $76.77 |
ROOFER: SHINGLES (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) (...ROOFER: SHINGLES (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL.) (WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR ADDITIONAL.) | ROOF0030-029 05/01/2025 | $35.95 | $21.85 | $57.80 |
ROOFER: SLATE AND TILE (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY L...ROOFER: SLATE AND TILE (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE) (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL.) ( WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR ADDITIONAL.) | ROOF0030-029 05/01/2025 | $38.95 | $21.85 | $60.80 |
| SHEET METAL WORKER: INCLUDING HVAC DUCT INSTALLATION | SHEE0025-005 06/01/2024 | $51.30 | $51.55 | $102.85 |
| SPRINKLER FITTER: FIRE SPRINKLERS (SOMERSET COUNTY (REMAINDER OF COUNTY)) | SFNJ0696-004 01/01/2025 | $67.97 | $39.35 | $107.32 |
| SPRINKLER FITTER: FIRE SPRINKLERS (SOMERSET COUNTY (TOWNSHIPS OF BRANCHBURG AND MONTGOMERY; BOROUGH OF ROCKY HILL)) | SFNJ0669-008 07/01/2025 | $49.97 | $41.35 | $91.32 |
| TILE FINISHER (WORK GROUTING ALL EPOXY: $10.00 ADDITIONAL PER DAY.) | BRNJ0007-001 06/02/2025 | $50.05 | $33.90 | $83.95 |
| TILE SETTER | BRNJ0007-001 06/02/2025 | $64.90 | $37.28 | $102.18 |
TRUCK DRIVER: DUMP TRUCK (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL P...TRUCK DRIVER: DUMP TRUCK (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE WHERE THE WORKER IS NOT WORKING IN A ZONE REQUIRING LEVEL A, B OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.) | TEAM0469-005 05/01/2025 | $48.63 | $42.66 | $91.29 |
TRUCK DRIVER: OFF THE ROAD TRUCK (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PE...TRUCK DRIVER: OFF THE ROAD TRUCK (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE WHERE THE WORKER IS NOT WORKING IN A ZONE REQUIRING LEVEL A, B OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL | TEAM0469-005 05/01/2025 | $48.78 | $42.66 | $91.44 |
Footnotes in NJ20260042 (5)
- ASBE0089-007 NOTE: PAID HOLIDAYS: THE LAST DAY PRIOR TO THE CHRISTMAS AND NEW YEAR'S DAY OBSERVED HOLIDAY: 4 HRS. PAY
- ELEV0001-003 NOTE: PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY.) (PAID VACATION: A WORKER WHO HAS WORKED LESS THAN 5 YEARS: 4% OF HIS OR HER HOURLY RATE FOR ALL HOURS WORKED. A WORKER WHO HAS WORKED 5 TO 10 YEARS: 6% OF HIS OR HER HOURLY RATE FOR ALL HOURS WORKED. A WORKER WHO HAS WORKED 15 OR MORE YEARS: 8% OF HIS OR HER HOURLY RATE FOR ALL HOURS WORKED.)
- ENGI0825-020 NOTE: PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY
- ROOF0030-029 NOTE: PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR HOURS PAY.)
- TEAM0469-005 NOTE: PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY.) (VACATION PAY CREDIT: WORKERS WORKING OR RECEIVING PAY FOR 80 DAYS WITHIN A YEAR RECEIVE ONE WEEK PAID VACATION (48 HOURS); 125 DAYS RECEIVE TWO WEEKS PAID VACATION (96 HOURS); 145 DAYS RECEIVE 15 DAYS PAID VACATION (120 HOURS); 15 YEARS SENIORITY AND 145 DAYS RECEIVE 4 WEEKS PAID VACATION (160 HOURS)).
Questions about these rates
What is the Davis-Bacon rate for plumbers on building work in Somerset County?
What is the Davis-Bacon rate for carpenters on building work in Somerset County?
What is the Davis-Bacon rate for laborers on building work in Somerset County?
Which wage determination applies to my project?
What counts as building construction?
What if my worker's trade is not on the list?
Using these rates on a WH-347
Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.
Make this week's WH-347 with NJ20260042
Other counties: all New Jersey counties · WD lookup
Your first certified payroll is free.
Upload last week's payroll, get a checked WH-347 back today.
No card. Same full report, no watermark.