Davis-Bacon wage rates · New York

Herkimer County heavy construction wage rates

Federal prevailing wage rates for heavy construction in Herkimer County, New York, from the wage determinations SAM.gov lists for this county. Rates are shown exactly as published.

Data from SAM.gov, fetched October 7, 20262 wage determinations
Wage determination
NY20260031
Modification
2
Published
May 18, 2026
Classifications
82
Other types here
Building, Residential, Highway

2 wage determinations cover heavy work in Herkimer County. They differ by scope (for example landscaping, dredging or part of the county). Use the WD number written in your contract; the scope text under each one says what it covers.

These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See New York prevailing wage for how the two fit together.

1 of 2: WD NY20260031, Mod 2

Make a WH-347 with these rates
Published May 18, 2026 82 classifications Covers 1 county Types: Building, Heavy, Highway Source: SAM.gov

Scope as published: Building Construction Projects · Heavy Construction Projects · Highway Construction Projects

Some rows apply only to an area or zone named in the classification. The area text is printed exactly as published; check it against your project's location before you use a row.

Davis-Bacon rates in NY20260031 Mod 2, published 05/18/2026. Total is base plus the hourly fringe printed in the WD; footnote benefits (paid holidays, vacation) are extra and listed below the table.
ClassificationRate IDBaseFringeTotal / hour
ASBESTOS/INSULATOR WORKER (INCLUDES APPLICATION OF ALL MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS. ALSO THE APPLICATION OF FIRESTOPPING MATERIAL TO OPE...ASBESTOS/INSULATOR WORKER (INCLUDES APPLICATION OF ALL MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS. ALSO THE APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS, CURTAIN WALLS AND ALL LEAD ABATEMENT.)
ASBE0030-001
05/01/2025
$43.25 $27.29 $70.54
BOILERMAKER BOIL0197-001
01/01/2025
$43.34 $27.66 $71.00
BRICKLAYER, MARBLE, TILE & TERRAZZO FINISHERS (UTICA CHAPTER) BUILDING CONSTRUCTION BRNY0002-002
07/01/2024
$28.52 $19.59 $48.11
BRICKLAYER, MARBLE, TILE & TERRAZZO WORKERS (UTICA CHAPTER) BUILDING CONSTRUCTION BRNY0002-002
07/01/2024
$35.85 $20.37 $56.22
BRICKLAYERS & STONE MASONS, CEMENT MASONS, PLASTERERS, POINTERS, CLEANERS & CAULKERS: BUILDING CONSTRUCTION (UTICA CHAPTER) BRNY0002-002
07/01/2024
$39.24 $22.02 $61.26
CABLE SPLICER ELEC0043-005
06/01/2025
$55.55 $35.03 $90.58
CARPENTER (HEAVY & HIGHWAY CONSTRUCTION) CARP0277-005
07/01/2025
$44.52 $27.16 $71.68
CARPENTER: CARPENTERS, MILLWRIGHTS (BUILDING CONSTRUCTION) CARP0277-005
07/01/2025
$30.85 $21.32 $52.17
CARPENTER: PILEDRIVER (BUILDING CONSTRUCTION) CARP0277-005
07/01/2025
$30.85 $21.32 $52.17
CEMENT MASON/CONCRETE FINISHER, HEAVY/HIGHWAY CONSTRUCION (UTICA CHAPTER) Footnote A below BRNY0002-010
06/01/2018
$37.23 $19.51 $56.74
ELECTRICIAN ELEC0043-005
06/01/2025
$50.50 $35.03 $85.53
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OP...ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES: LINEMAN AND TECHNICIAN
Footnote A below
ELEC1249-004
05/05/2025
$61.56 $36.21 $97.77
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER Footnote A below ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUD...ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT)
Footnote A below
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY,...ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
ELEC1249-008
01/01/2025
$40.81 $6.99 $47.80
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THA...ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
ELEC1249-008
01/01/2025
$20.53 $6.39 $26.92
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORA...ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
ELEC1249-008
01/01/2025
$38.73 $6.93 $45.66
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN Footnote A below ELEC1249-003
05/05/2025
$31.72 $29.87 $61.59
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS...ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER)
Footnote A below
ELEC1249-003
05/05/2025
$42.29 $30.66 $72.95
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS...ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT)
Footnote A below
ELEC1249-003
05/05/2025
$47.57 $31.03 $78.60
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS...ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN
Footnote A below
ELEC1249-003
05/05/2025
$52.86 $35.60 $88.46
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC Footnote A below ELEC1249-003
05/05/2025
$42.29 $30.66 $72.95
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) ELEC1249-004
05/05/2025
$63.14 $33.82 $96.96
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable inst...ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)
ELEC1249-004
05/05/2025
$64.59 $42.92 $107.51
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wir...ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$35.34 $30.12 $65.46
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) ELEC1249-004
05/05/2025
$35.34 $30.12 $65.46
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installati...ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)
ELEC1249-004
05/05/2025
$35.34 $30.12 $65.46
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$55.40 $31.78 $87.18
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) ELEC1249-004
05/05/2025
$55.40 $31.78 $87.18
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission c...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab
ELEC1249-004
05/05/2025
$55.40 $31.78 $87.18
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber o...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and c...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work includ...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) ELEC1249-004
05/05/2025
$61.56 $36.21 $97.77
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit...ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins
ELEC1249-004
05/05/2025
$61.56 $36.21 $97.77
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wi...ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installat...ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELEVATOR CONSTRUCTOR Footnote A, B below ELEV0035-002
01/01/2025
$57.73 $38.44 $96.17
GLAZIER PAIN0677-002
05/01/2025
$30.00 $27.59 $57.59
HAZARDOUS MATERIAL HANDLER (SCOPE OF WORK: DUTIES LIMITED TO PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING, AND DISPOSING OF ALL INSULATION MATERIALS, WHETHER THEY CONTAIN AS...HAZARDOUS MATERIAL HANDLER (SCOPE OF WORK: DUTIES LIMITED TO PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING, AND DISPOSING OF ALL INSULATION MATERIALS, WHETHER THEY CONTAIN ASBESTOS OR NOT FROM MECHANICAL SYSTEM)
ASBE0030-001
05/01/2025
$38.50 $25.04 $63.54
IRONWORKER: STRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY MOVER, RIGGER, FENCE ERECTOR, REINFORCEMENT, AND STONE DERRICKMAN (REMANINDER OF COUNTY) IRON0440-001
07/01/2025
$35.50 $31.39 $66.89
LABORERS: BUILDING CONSTRUCTION: ASBESTOS REMOVAL Footnote A below LABO0035-005
07/01/2017
$24.00 $20.64 $44.64
LABORERS: BUILDING CONSTRUCTION: BLASTERS, FORM SETTERS, MOTORBUGGY OPERATOR (RIDER TYPE) Footnote A below LABO0035-005
07/01/2017
$23.00 $20.64 $43.64
LABORERS: BUILDING CONSTRUCTION: HAZARDOUS WASTE REMOVAL (HAZARDOUS WASTE REMOVAL INCLUDES, WETTING,STRIPPING, REMOVAL, SCRAPPING, VACCUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS, WHEATH...LABORERS: BUILDING CONSTRUCTION: HAZARDOUS WASTE REMOVAL (HAZARDOUS WASTE REMOVAL INCLUDES, WETTING,STRIPPING, REMOVAL, SCRAPPING, VACCUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS, WHEATHER THEY CONTAIN ASBESTOS OR NOT, FROM MECHANICAL SYSTEMS)
Footnote A below
LABO0035-005
07/01/2017
$24.00 $20.64 $44.64
LABORERS: BUILDING CONSTRUCTION: LABORERS Footnote A below LABO0035-005
07/01/2017
$22.50 $20.64 $43.14
LABORERS: BUILDING CONSTRUCTION: PIPELAYERS, MOTOR MIXERS, MOTOR BUGGY OPERATOR (WALK BEHIND) POWER LIFT (WALK BEHIND) Footnote A below LABO0035-005
07/01/2017
$22.65 $20.64 $43.29
LABORERS: BUILDING CONSTRUCTION: WAGON DRILL OPERATOR Footnote A below LABO0035-005
07/01/2017
$22.90 $20.64 $43.54
LABORERS: GROUP 1: (HEAVY & HIGHWAY CONSTRUCTION:) COMMON LABORERS, FLAGMAN, OUTBOARD AND HAND BOATS Footnote A below LABO0035-005
07/01/2017
$28.05 $23.74 $51.79
LABORERS: GROUP 2: (HEAVY & HIGHWAY CONSTRUCTION:) BULL FLOAT, CHAIN SAW, CONCRETE AGGREGATE BIN, CONCRETE BOOTMAN, GIN BUGGY, HAND OR MACHINE VIBRATOR, JACKHAMMER, MASON TENDER, MORTOR MIXER, PAVEMEN...LABORERS: GROUP 2: (HEAVY & HIGHWAY CONSTRUCTION:) BULL FLOAT, CHAIN SAW, CONCRETE AGGREGATE BIN, CONCRETE BOOTMAN, GIN BUGGY, HAND OR MACHINE VIBRATOR, JACKHAMMER, MASON TENDER, MORTOR MIXER, PAVEMENT BREAKER, HANDLERS OF ALL STEEL MESH, SMALL GENERATORS FOR LABORERS'S TOOLS, INSTALLATION OF BRIDGE DRAINAGE, PIPELAYERS, VIBRATOR TYPE ROLLERS, TAMPER, DRILL DOCTOR, TAIL OR SCREW OPERATOR ON ASPHALT PAVER, WATER PUMP OPERATOR (1 1/2" AND SINGLE DIAPHRAM), NOZZLE (APHLAT, GUNNITE, SEEDING AND SAND BLASTING), LABORERS ON CHAIN LINK FENCE ERECTION, ROCK SPLITTER AND POWER UNIT, PUSHER TYPE CONCRETE SAW AND ALL OTHER GAS, ELECTRIC, OIL, AND AIR TOOL OPERATORS, WRECKING LABORERS
Footnote A below
LABO0035-005
07/01/2017
$28.25 $23.74 $51.99
LABORERS: GROUP 3: (HEAVY & HIGHWAY CONSTRUCTION:) ALL ROCK OR DRILLING MACHINE OPERATORS (EXCEPT QUARRY MASTER AMD SIMILAR TYPE), ACETYLENE TORCH OPERATORS, AND ASPHALT PAVER, POWERMAN Footnote A below LABO0035-005
07/01/2017
$28.45 $23.74 $52.19
LABORERS: GROUP 4: (HEAVY & HIGHWAY CONSTRUCTION:) BLASTERERS, FORM SETTERS, STONE OR GRANITE CURB SETTERS Footnote A below LABO0035-005
07/01/2017
$28.65 $23.74 $52.39
PAINTERS: BRUSH & ROLL, DRYWALL TAPING/FINISHING (BUILDING CONSTRUCTION) PAIN0004-025
05/01/2024
$27.27 $26.23 $53.50
PAINTERS: SPRAY, SANDBLASTING, STRUCTURAL STEEL (BUILDING CONSTRUCTION) PAIN0004-025
05/01/2024
$27.77 $26.23 $54.00
PLUMBER, INCLUDING STEAMFITTING (NORTHERN ZONE) PLUM0112-003
05/01/2025
$45.93 $33.77 $79.70
POWER EQUIPMENT OPERATORS: BUILDING GROUP 1 AIR PLAKO, ASPHALT AND BLACKTOP ROLLER, AUTOMATED CONCRETE SPREADER (CMI OR EQUIVALENT), AUTOMATED FINE GRADE MACHINE (CMI), BACKHOE, ELT PALCER, BLACKTOP S...POWER EQUIPMENT OPERATORS: BUILDING GROUP 1 AIR PLAKO, ASPHALT AND BLACKTOP ROLLER, AUTOMATED CONCRETE SPREADER (CMI OR EQUIVALENT), AUTOMATED FINE GRADE MACHINE (CMI), BACKHOE, ELT PALCER, BLACKTOP SPREADER (SUCH AS BARBER GREEN & BLAW KNOX), BLACKTOP PLANT (AUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR CAT MOUNTED), BOOM TRUCK, CABLEWAY, CAISSON AUGER, CENTRAL MIX PLANT (AUTOMATED), CHERRY PICKER (15 TONS), CONCRETE PUMP, CRANE, CRUSHER (ROCK), DERRICK, DIESEL POWER UNIT, DRAGLINE, DREDGE, DUAL DRUM PAVER, ELEVATING GRADER (SELF-PROPELLED), ELEVATOR HOIST (2 CAGE), EXCAVATOR (ALL PURPOSE-HYDRAULICALLY OPERATED), FORK LIFT (LOED AND LULL AND OTHER ROUGH TERRAIN TYPE), FRONT END LOADER (4 C.Y. AND OVER), GRADALL, GRADER (POWER), HEAD TOWER (SAURMAN OR EQUAL), HOST ( 2 OR 3 DRUM), HYDROBLASTER (LASER PUMP), WORK BOAT OPERATOR (LCM), LIGHT PLANTS (COMPRESSORS AND GENERATORS), LOCOMOTIVE,MAINTENANCE ENGINEER, MAINTENANCE WELDER, MINE HOIST, MUCKING MACHINE OR MOLE, OVERHEAD CRANE -FIXED PERMANENT, PILE DRIVER, QUARRY MASTER OR EQUIVALENT, REFRIGERATION EQUIPMENT (FOR SOIL STABILIZATION), SCRAPER SEA MULE, SHOVEL, SIDE BOOM, SLIP FORM PAVER, STRADDLE BUGGY (ROSS CARRIER, LUMBER CARRIER), TRACTOR DRAWN BELT TYPE LOADER (EUCLID LOADER), TRANCHING MACHINE (DIGGING CAPACITY OF OVER 4 FT DEPTH), TRUCK CRANE (OPERATOR), TRUCK OF TRAILER MOUNTED LOG CHIPPER (SELF FEEDER), TUG OPERATOR (MANNED, RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVEL, VIBRO OR SONIC HAMMER CONTROLS (WHEN NOT MOUNTED IN PROXIMITY TO THE RIG OPERATOR HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) PREMIUMS: HAZMAT WORK 2.50 QUAD 9 BULLDOZER OR MULTIBOWL SCRAPER.50 CRANE PREMIUMS (ADD TO GROUP 1 RATE): ALL LATTIC BOOM CRANES (65 TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.25 ALL HYDRAULIC CRANES (100 TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.75 ALL HYDRAULIC CRANES (80 TON CAPACITY TO 99 TON CAPACITY) GROUP 1 RATE PLUS 1.25 ALL HYDRAULIC CRANES (65 TON CAPACITY TO 79 TON CAPACITY) GROUP 1 RATE PLUS 1.10
Footnote A below
ENGI0158-012
07/01/2024
$54.90 $32.45 $87.35
POWER EQUIPMENT OPERATORS: BUILDING GROUP 2 "A" FRAME TRUCK, BLACKTOP PLANT (NON AUTOMATIC), ALL BACK DUMPS, BORING MACHINE, BULLDOZER, CAGEHOIST, CENTRAL MIX PLANT (NON AUTOMATED), CHERRY PICKER 15 T...POWER EQUIPMENT OPERATORS: BUILDING GROUP 2 "A" FRAME TRUCK, BLACKTOP PLANT (NON AUTOMATIC), ALL BACK DUMPS, BORING MACHINE, BULLDOZER, CAGEHOIST, CENTRAL MIX PLANT (NON AUTOMATED), CHERRY PICKER 15 TONS AND UNDER), THAN 5), CONCRETE PAVER (SINGLE DRUM OVER 16S), CORE BORING MACHINE, DRILL RIGS (TRACTOR MOUNTED), ELEVATOR (AS A MATERIAL HOIST), FORK LIFT (ALL OTHERS), FRONT END LOADER (UNDER 4 C.Y.), GUNITE MACHINE, HIGH PRESSURE BOILER 915 LBS & OVER), HOIST (ONE DRUM), HYDRAULIC BREAKING HAMMER (DROP HAMMER), KOLMAN PLANT LOADER (SCREENING GRAVEL), MAINTENANCE GREASE MAN, MIZER FOR STABILIZED BASE (SELF PROPELLED SEAMAN MIXER), MONRAIL MACHINE, PARAPET CONCRETE OR PAVEMENT GRINDER, PARTS MAN, POST HOLE DIGGER (TRUCK OR TRACTOR MOUNTED), POWER SWEEPER (WAYNE OR SIMILAR), GROUT PUMP, PUMP- CRETE OR SQEEZE-CRETE, ROAD WIDENER (FRONT END OF GRADER OR SELF PROP.), ROLLER, SELF CONTAINED HYDRAULIC BENCH DRILL, SHELL WINDER (MOTORIZED), SNORKEL (OVERHEAD ARMS), SNOWBLOWER CONTROL MAN, TRENCHING MACHINE (DIGGING CAPACITY OF 4 FT OR LESS), TUGGER HOIST, VIBROTAMP, WELL DRILL, WELL POINT SYSTEM, WINCH (MOTOR DRIVEN), WINCH CAT, WINCH TRUCK HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) PREMIUMS: HAZMAT WORK 2.50 QUAD 9 BULLDOZER OR MULTIBOWL SCRAPER.50
Footnote A below
ENGI0158-012
07/01/2024
$53.99 $32.45 $86.44
POWER EQUIPMENT OPERATORS: BUILDING GROUP 3 COMPRESSOR (UP TO 500 C.F.), CONCRETE PAVE ROR MIXER (UNDER 16S), CONCRETE PAVEMENT SPREADERS AND FINISHERS (NOT AUTOMATED), CONVEYOR (OVER 12 FT), ELECTRIC...POWER EQUIPMENT OPERATORS: BUILDING GROUP 3 COMPRESSOR (UP TO 500 C.F.), CONCRETE PAVE ROR MIXER (UNDER 16S), CONCRETE PAVEMENT SPREADERS AND FINISHERS (NOT AUTOMATED), CONVEYOR (OVER 12 FT), ELECTRIC SUBMERSIBLE PUMP (4" AND OVER), FARM TRACTOR WITH OR WITHOUT ACCESSORIES, FINE GRADE MACHINE (NOT AUTOMATED), FIREMAN, FORM TAMPER, GENERATOR (2,500 WATTS AND OVER), HYDRAULIC PUMP, MECHANICAL HEATERS (MORE THAN 2 WHOSW COMBINED OUTPUT EXCEEDS 640,000 BTU PER HOUR (MANUFACTURER'S RATING) PLUS ONE SELF CONTAINED HEATING UNIT (SUNDOG, AIR HEAT TYPE, NEW HOLLAND HAY DRYER TYPE EXCLUDED), POWER HEATERMAN (HAY DRYER), PUMPS (WATER AND TRASH), REVINUS WIDENER (ROAD WIDENER), SINGLE LIGHT PLANT, STEAM CLEANER OR JENNY, TRACTOR WITH OR WITHOUT TOWED ACCESSORIES HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) PREMIUMS: HAZMAT WORK 2.50 QUAD 9 BULLDOZER OR MULTIBOWL SCRAPER.50
Footnote A below
ENGI0158-012
07/01/2024
$51.42 $32.45 $83.87
POWER EQUIPMENT OPERATORS: BUILDING GROUP 4 MASTER MECHANIC HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) PREMIUMS: HAZMAT WORK 2.50 QUAD 9...POWER EQUIPMENT OPERATORS: BUILDING GROUP 4 MASTER MECHANIC HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) PREMIUMS: HAZMAT WORK 2.50 QUAD 9 BULLDOZER OR MULTIBOWL SCRAPER.50
Footnote A below
ENGI0158-012
07/01/2024
$57.01 $32.45 $89.46
POWER EQUIPMENT OPERATORS: BUILDING: GROUP A(1): CRANE, HYDRAULIC CRANES, TOWER CRANE, LOCOMOTIVE CRANE, PILEDRIVER, CABLEWAY, DERRICKS, WHIRLIES, DRAGLINE. HERKIMER COUNTY (AREA EAST OF A LINE RUNNIN...POWER EQUIPMENT OPERATORS: BUILDING: GROUP A(1): CRANE, HYDRAULIC CRANES, TOWER CRANE, LOCOMOTIVE CRANE, PILEDRIVER, CABLEWAY, DERRICKS, WHIRLIES, DRAGLINE. HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) GROUP A(1): CRANE PREMIUMS 1 OVER 150':ADD $1.00 2 OVER 200': ADD $2.00
ENGI0158-004
07/01/2025
$55.42 $33.20 $88.62
POWER EQUIPMENT OPERATORS: GROUP 1 (HEAVY & HIGHWAY) ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUB...POWER EQUIPMENT OPERATORS: GROUP 1 (HEAVY & HIGHWAY) ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED), BACKHOE EXCAVATOR FULL SWING (CAT 212 OR SIMILAR TYPE), BACK FILLING MACHINE, BELT PLACER (CMI TYPE), BLACKTOP PLANT (AUTOMATED), BOOM TRUCK, CABLEWAY, CAISSON AUGER, CENTRAL MIX CONCRETE PLANT (AUTOMATED), CONCRETE CURB MACHINE, SELF PROPELLED, SLIPFORM, CONCRETE PUMP, CRANE, CHERRY PICKER, DERRICKS (STEEL ERECTION), DRAGLINE, OVERHEAD CRANE (GANTRY OR STRADDLE TYPE), PILE DRIVER, TRUCK CRANE, DIRECTIONAL DRILLING MACHINE, DREDGE, DUAL DRUM PAVER, EXCAVATOR (ALL PURPOSE HYDRAULICALLY OPERATED) (GRADALL OR SIMILAR), FRONT END LOADER ( 4 CU. YD. AND OVER), HEAD TOWER (SAUERMAN OR EQUAL), HOIST (TWO OR THREE DRUM), HOLLAND LOADER, MAINTENANCE ENGINEER, MINE HOIST, MUCKING MACHINE OR MOLE PAVEMENT BREAKER(SP) WERTGEN; PB-4 AND SIMILAR TYPE, POWER GRADER, PROFILER (OVER 105 H.P.) QUAD 9, QUARRY MASTER (OR EQUIVALENT), SCRAPER, FIREMAN, FORM TAMPER, GROUT PUMP, GUNITE MACHINE, HAMMERS (HYDRAULIC SELF-PROPELLED), HYDRA-SPIKER, RIDE-ON, HYDRAULIC PUMP (JACKING SYSTEM), HYDRO-BLASTER (WATER), MULCHING MACHINE, OILER, PARAPET CONCRETE OR PAVEMENT, SHOVEL, SIDE BOOM, SLIP FORM PAVER, TRACTOR DRAWN, BELTTYPE LOADER, TRUCK OR TRAILER MOUNTED LOG, CHIPPER (SELF FEEDER), TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVEL HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)
Footnote A below
ENGI0158-017
07/01/2025
$57.30 $33.55 $90.85
POWER EQUIPMENT OPERATORS: GROUP 1 (HEAVY AND HIGHWAY) ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, R...POWER EQUIPMENT OPERATORS: GROUP 1 (HEAVY AND HIGHWAY) ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED), BACKHOE EXCAVATOR FULL SWING (CAT 212 OR SIMILAR TYPE), BACK FILLING MACHINE, BELT PLACER (CMI TYPE), BLACKTOP PLANT (AUTOMATED), BOOM TRUCK, CABLEWAY, CAISSON AUGER, CENTRAL MIX CONCRETE PLANT (AUTOMATED), CONCRETE CURB MACHINE, SELF PROPELLED, SLIPFORM, CONCRETE PUMP, CRANE, CHERRY PICKER, DERRICKS (STEEL ERECTION), DRAGLINE, OVERHEAD CRANE (GANTRY OR STRADDLE TYPE), PILE DRIVER, TRUCK CRANE, DIRECTIONAL DRILLING MACHINE, DREDGE, DUAL DRUM PAVER, EXCAVATOR (ALL PURPOSE HYDRAULICALLY OPERATED) (GRADALL OR SIMILAR), FRONT END LOADER ( 4 CU. YD. AND OVER), HEAD TOWER (SAUERMAN OR EQUAL), HOIST (TWO OR THREE DRUM), HOLLAND LOADER, MAINTENANCE ENGINEER, MINE HOIST, MUCKING MACHINE OR MOLE PAVEMENT BREAKER(SP) WERTGEN; PB-4 AND SIMILAR TYPE, POWER GRADER, PROFILER (OVER 105 H.P.) QUAD 9, QUARRY MASTER (OR EQUIVALENT), SCRAPER, FIREMAN, FORK LIFT, FORM TAMPER, GROUT PUMP, GUNITE MACHINE, HAMMERS (HYDRAULIC SELF-PROPELLED), HYDRA-SPIKER, RIDE-ON, HYDRAULIC PUMP (JACKING SYSTEM), HYDRO-BLASTER (WATER), MULCHING MACHINE, OILER, PARAPET CONCRETE OR PAVEMENT, SHOVEL, SIDE BOOM, SLIP FORM PAVER, TRACTOR DRAWN, BELTTYPE LOADER, TRUCK OR TRAILER MOUNTED LOG, CHIPPER (SELF FEEDER), TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVEL (HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)
Footnote A below
ENGI0158-022
07/01/2024
$54.90 $32.45 $87.35
POWER EQUIPMENT OPERATORS: GROUP 2 (HEAVY & HIGHWAY) ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), ...POWER EQUIPMENT OPERATORS: GROUP 2 (HEAVY & HIGHWAY) ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED), BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT (NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS, CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED, CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR MOUNTED, FRONT END LOADER (UNDER 4 CU. YD.), GREASEMAN/LUBRICATION ENGINEER, HIPRESSURE BOILER (15 LBS. AND OVER), HOIST (ONE DRUM), HYDRO-AXE, KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS, L.C.M. WORK BOAT OPERATOR, LOCOMOTIVE MIXER (FOR STABILIZED BASE SELFPROPELLED), MONORAIL MACHINE, PLANT ENGINEER, PROFILER (105 H.P. AND UNDER), GRINDER, POST HOLE DIGGER AND POST DRIVER, POWER BROOM (TOWED), POWER HEATERMAN, POWER SWEEPER, REVINIUS WIDENER, ROLLER (GRADE AND FILL), SCARIFIER, RIDE-ON, SHELL WINDER, SKID STEER LOADER (BOBCAT OR SIMILAR), SPAN-SAW, RIDE-ON, STEAM CLEANER, PUG MILL, PUMP CRETE READY MIX CONCRETE PLANT REFRIGERATION EQUIPMENT (FOR SOIL STABILIZATION)ROAD WIDENER, ROLLER (ALL ABOVE SUBGRADE), SEA MULE, SELF-CONTAINED RIDE-ON ROCK DRILL, EXCLUDING AIR-TRACK TYPE DRILL, SKIDDER, TRACTOR WITH DOZER AND/OR PUSHER, TRENCHER. TUGGER HOIST, VERMEER SAW (RIDE ON, ANY SIZE OR TYPE), WINCH, WINCH CAT HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)
Footnote A below
ENGI0158-017
07/01/2025
$56.39 $33.55 $89.94
POWER EQUIPMENT OPERATORS: GROUP 2 (HEAVY AND HIGHWAY) ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED)...POWER EQUIPMENT OPERATORS: GROUP 2 (HEAVY AND HIGHWAY) ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED), BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT (NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS, CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED, CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR MOUNTED, FRONT END LOADER (UNDER 4 CU. YD.), GREASEMAN/LUBRICATION ENGINEER, HIPRESSURE BOILER (15 LBS. AND OVER), HOIST (ONE DRUM), HYDRO-AXE, KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS, L.C.M. WORK BOAT OPERATOR, LOCOMOTIVE MIXER (FOR STABILIZED BASE SELFPROPELLED), MONORAIL MACHINE, PLANT ENGINEER, PROFILER (105 H.P. AND UNDER), GRINDER, POST HOLE DIGGER AND POST DRIVER, POWER BROOM (TOWED), POWER HEATERMAN, POWER SWEEPER, REVINIUS WIDENER, ROLLER (GRADE AND FILL), SCARIFIER, RIDE-ON, SHELL WINDER, SKID STEER LOADER (BOBCAT OR SIMILAR), SPAN-SAW, RIDE-ON, STEAM CLEANER, PUG MILL, PUMP CRETE READY MIX CONCRETE PLANT REFRIGERATION EQUIPMENT (FOR SOIL STABILIZATION)ROAD WIDENER, ROLLER (ALL ABOVE SUBGRADE), SEA MULE, SELF-CONTAINED RIDE-ON ROCK DRILL, EXCLUDING AIR-TRACK TYPE DRILL, SKIDDER, TRACTOR WITH DOZER AND/OR PUSHER, TRENCHER. TUGGER HOIST, VERMEER SAW (RIDE ON, ANY SIZE OR TYPE), WINCH, WINCH CAT HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)
Footnote A below
ENGI0158-022
07/01/2024
$53.99 $32.45 $86.44
POWER EQUIPMENT OPERATORS: GROUP 3 (HEAVY & HIGHWAY) A FRAME WINCH HOIST ON TRUCK, ARTICULATED HEAVY HAULER, AGGREGATE PLANT, ASPHALT OR CONCRETE GROOVING, MACHINE (RIDE ON), BALLAST REGULATOR, RIDE-O...POWER EQUIPMENT OPERATORS: GROUP 3 (HEAVY & HIGHWAY) A FRAME WINCH HOIST ON TRUCK, ARTICULATED HEAVY HAULER, AGGREGATE PLANT, ASPHALT OR CONCRETE GROOVING, MACHINE (RIDE ON), BALLAST REGULATOR, RIDE-ON BOILER (USED IN CONJUNCTION WITH PRODUCTION), BITUMINOUS HEATER, SELF-PROPELLED, BOAT (POWERED), CEMENT AND BIN OPERATOR, COMPRESSORS, DUST COLLECTORS, FORK LIFT, GENERATORS, PUMPS, WELDING MACHINES, LIGHT PLANTS, HEATERS (HANDS-OFF EQUIPMENT), CONCRETE PAVEMENT SPREADER AND FINISHER, CONCRETE PAVER OR MIXER (16S AND UNDER), CONCRETE SAW (SELF-PROPELLED), CONVEYOR, DECK HAND, DIRECTIONAL DRILL MACHINE LOCATOR, DRILL, (CORE), DRILL, (WELL,) FARM TRACTOR WITH ACCESSORIES, FINE GRADE MACHINE, TAMPER, RIDE-ON, TIE EXTRACTOR, RIDE-ON, TIE HANDLER, RIDE-ON, TIE INSERTER, RIDE-ON, TIE SPACER, RIDE-ON, TIRE REPAIR, TRACK LINER, RIDE-ON, TRACTOR, TRACTOR (WITH TOWED ACCESSORIES), VIBRATORY COMPACTOR, VIBRO TAMP, WELL POINT HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)
Footnote A below
ENGI0158-017
07/01/2025
$53.82 $33.55 $87.37
POWER EQUIPMENT OPERATORS: GROUP 3 (HEAVY AND HIGHWAY) A FRAME WINCH HOIST ON TRUCK, ARTICULATED HEAVY HAULER, AGGREGATE PLANT, ASPHALT OR CONCRETE GROOVING, MACHINE (RIDE ON), BALLAST REGULATOR, RIDE...POWER EQUIPMENT OPERATORS: GROUP 3 (HEAVY AND HIGHWAY) A FRAME WINCH HOIST ON TRUCK, ARTICULATED HEAVY HAULER, AGGREGATE PLANT, ASPHALT OR CONCRETE GROOVING, MACHINE (RIDE ON), BALLAST REGULATOR, RIDE-ON BOILER (USED IN CONJUNCTION WITH PRODUCTION), BITUMINOUS HEATER, SELF-PROPELLED, BOAT (POWERED), CEMENT AND BIN OPERATOR, COMPRESSORS, DUST COLLECTORS, GENERATORS, PUMPS, WELDING MACHINES, LIGHT PLANTS, HEATERS (HANDS-OFF EQUIPMENT), CONCRETE PAVEMENT SPREADER AND FINISHER, CONCRETE PAVER OR MIXER (16S AND UNDER), CONCRETE SAW (SELF-PROPELLED), CONVEYOR, DECK HAND, DIRECTIONAL DRILL MACHINE LOCATOR, DRILL, (CORE), DRILL, (WELL,) FARM TRACTOR WITH ACCESSORIES, FINE GRADE MACHINE, TAMPER, RIDE-ON, TIE EXTRACTOR, RIDE-ON, TIE HANDLER, RIDE-ON, TIE INSERTER, RIDE-ON, TIE SPACER, RIDE-ON, TIRE REPAIR, TRACK LINER, RIDE-ON, TRACTOR, TRACTOR (WITH TOWED ACCESSORIES), VIBRATORY COMPACTOR, VIBRO TAMP, WELL POINT HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)
Footnote A below
ENGI0158-022
07/01/2024
$51.42 $32.45 $83.87
POWER EQUIPMENT OPERATORS: GROUP 4 (HEAVY & HIGHWAY) TOWER CRANES HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) Footnote A below ENGI0158-017
07/01/2025
$63.30 $33.55 $96.85
POWER EQUIPMENT OPERATORS: GROUP 4 (HEAVY AND HIGHWAY) TOWER CRANES HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) Footnote A below ENGI0158-022
07/01/2024
$60.90 $32.45 $93.35
POWER EQUIPMENT OPERATORS: GROUP 5 (HEAVY & HIGHWAY) CRANES 50 TONS AND OVER HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) Footnote A below ENGI0158-017
07/01/2025
$61.80 $33.55 $95.35
POWER EQUIPMENT OPERATORS: GROUP 5 (HEAVY AND HIGHWAY) CRANES 50 TONS AND OVER HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) Footnote A below ENGI0158-022
07/01/2024
$59.40 $32.45 $91.85
POWER EQUIPMENT OPERATORS: GROUP 6 (HEAVY & HIGHWAY) CRANES 49 TONS AND BELOW HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) Footnote A below ENGI0158-017
07/01/2025
$60.30 $33.55 $93.85
POWER EQUIPMENT OPERATORS: GROUP 6 (HEAVY AND HIGHWAY) CRANES 49 TONS AND BELOW HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) Footnote A below ENGI0158-022
07/01/2024
$57.90 $32.45 $90.35
POWER EQUIPMENT OPERATORS: GROUP 7 (HEAVY & HIGHWAY) MASTER MECHANIC HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) Footnote A below ENGI0158-017
07/01/2025
$58.91 $33.55 $92.46
POWER EQUIPMENT OPERATORS: GROUP 7 (HEAVY AND HIGHWAY) MASTER MECHANIC HERKIMER COUNTY (AREA WEST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS) Footnote A below ENGI0158-022
07/01/2024
$57.01 $32.45 $89.46
POWER EQUIPMENT OPERATORS:, BUILDING: GROUP A (HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)) SHOVEL, ALL BACKHOE (EXCEPT TRACTOR MOUNTED R...POWER EQUIPMENT OPERATORS:, BUILDING: GROUP A (HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)) SHOVEL, ALL BACKHOE (EXCEPT TRACTOR MOUNTED RUBBER TIRED JOHN DEERE 510 OR SMALLER), GRADALLS, POWER ROAD GRADER, ALL CMI EQUIPMENT, FRONT-END RUBBER TIRE LOADER, TRACTOR-MOUNTED DRILL (QUARRY MASTER), MUCKING MACHINE, CONCRETE CENTRAL MIX PLANT, CONCRETE PUMP, BELCRETE SYSTEM, AUTOMATED ASPHALT CONCRETE PLANT AND TRACTOR ROAD PAVER
ENGI0158-004
07/01/2025
$54.93 $33.20 $88.13
POWER EQUIPMENT OPERATORS:, BUILDING: GROUP B (HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)) BACKHOE, (TRACTOR MOUNTED RUBBER TIRED EQUIVA...POWER EQUIPMENT OPERATORS:, BUILDING: GROUP B (HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)) BACKHOE, (TRACTOR MOUNTED RUBBER TIRED EQUIVALENT TO JOHN DEERE 510 OR LESS), BULLDOZER, PUSHCAT, TRACTOR, TRAXCAVATOR, SCRAPER, LETOURNEAU GRADER, FORM FINE GRADER, ROAD ROLLER, BLACKTOP ROLLER, BLACKTOP SPREADER, POWER BROOMS, SWEEPERS, TRENCHING MACHINE, BARBER GREEN LOADER, SIDE BOOMS, HYDROHAMMER, CONCRETE SPREADER, CONCRETE FINISHING MACHINE, ONE DRUM HOIST, POWER HOSTING (SINGLE DRUM), HOIST - TWO DRUM OR MORE, THREE DRUM ENGINE, POWER HOISTING (TWO DRUM AND OVER), TWO DRUM AND SWINGING ENGINE, THREE DRUM SWINGING ENGINE, HOD HOIST, A-L FRAME WINCHES, CORD AND WELL DRILLERS (ONE DRUM), POST HOLE DIGGER, MODEL CHB VIBRO-TAMP OR SIMILAR MACHINE, BATCH BIN AND PLANT OPERATOR, DINKEY LOCOMOTIVE, SKID STEER LOADER, TRACK EXCAVATOR 5/8 CU. YD. OR SMALLER
ENGI0158-004
07/01/2025
$53.91 $33.20 $87.11
POWER EQUIPMENT OPERATORS:, BUILDING: GROUP C (HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)) FORK LIFT, HIGH LIFT, LULL, OILER, FIREMAN AN...POWER EQUIPMENT OPERATORS:, BUILDING: GROUP C (HERKIMER COUNTY (AREA EAST OF A LINE RUNNING NORTH AND SOUTH THROUGH THE RAILROAD STATION AT LITTLE FALLS)) FORK LIFT, HIGH LIFT, LULL, OILER, FIREMAN AND HEAVY- DUTY GREASER, BOILERS, AND STEAM GENERATORS, PUMP, VIBRATOR, MOTOR MIXER, AIR COMPRESSOR, DUST COLLECTOR, WELDING MACHINE, WELL POINT, MECHANICAL HEATER, GENERATORS, TEMPORARY LIGHT PLANTS, CONCRETE PUMPS, ELECTRIC SUBMERSIBLE PUMP 4" AND OVER, MURPHY TYPE DIESEL GENERATOR, CONVEYOR, ELEVATORS, CONCRETE MIXER AND BELCRETE POWER PACK (BELCRETE SYSTEM), SEEDING, AND MULCHING MACHINES, PUMPS
Footnote A below
ENGI0158-004
07/01/2025
$51.01 $33.20 $84.21
ROOFER ROOF0195-001
07/01/2025
$35.80 $25.99 $61.79
SHEET METAL WORKER (PROJECTS 10 MILLION OR LESS) SHEE0058-001
05/01/2025
$36.29 $23.31 $59.60
SHEET METAL WORKER (PROJECTS OVER $10 MILLION) SHEE0058-001
05/01/2025
$46.29 $23.31 $69.60
SPRINKLER FITTER SFNY0669-001
01/01/2026
$47.85 $28.94 $76.79
Footnotes in NY20260031 (10)
  • BRNY0002-010 A: PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, AND THANKSGIVING DAY (PROVIDED THE EMPLOYEE IS EMPLOYED ONE DAY BEFORE AND ONE DAY AFTER THE HOLIDAY)
  • ELEC1249-003 A: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY
  • ELEC1249-004 A: PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY
  • ELEV0035-002 A: VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED.
  • ELEV0035-002 B: PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY
  • ENGI0158-004 A: PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY
  • ENGI0158-012 A: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED FIVE CONSECUTIVE WORKING DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
  • ENGI0158-017 A: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY
  • ENGI0158-022 A: PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
  • LABO0035-005 A: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY

2 of 2: WD NY20260001, Mod 2

Make a WH-347 with these rates
Published May 18, 2026 7 classifications Covers 62 counties Types: Heavy Source: SAM.gov

Scope as published: All dredging, except self propelled hopper dredging, on the Atlantic Coast and tributary waters emptying into the Atlantic Ocean

Davis-Bacon rates in NY20260001 Mod 2, published 05/18/2026. Total is base plus the hourly fringe printed in the WD; footnote benefits (paid holidays, vacation) are extra and listed below the table.
ClassificationRate IDBaseFringeTotal / hour
DREDGING: CLASS A1: DECK CAPTAIN; MECHANICAL DREDGE OPERATOR, LEVERMAN, LICENSED TUG OPERATOR OVER 1000 HP. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TU...DREDGING: CLASS A1: DECK CAPTAIN; MECHANICAL DREDGE OPERATOR, LEVERMAN, LICENSED TUG OPERATOR OVER 1000 HP. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55
Footnote A, B below
ENGI0025-001
10/01/2025
$48.48 $15.34 $63.82
DREDGING: CLASS A2: CRANE OPERATOR (360 SWING) INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED M...DREDGING: CLASS A2: CRANE OPERATOR (360 SWING) INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55
Footnote A, B below
ENGI0025-001
10/01/2025
$43.20 $14.99 $58.19
DREDGING: CLASS B1: DERRICK OPERATOR (180 SWING), SPIDER/SPILL BARGE OPERATOR, ENGINEER, ELECTRICIAN, CHIEF WELDER, CHIEF MATE, FILL PLACER, OPERATOR II, MAINTENANCE ENGINEER, LICENSED BOAT OPERATOR, ...DREDGING: CLASS B1: DERRICK OPERATOR (180 SWING), SPIDER/SPILL BARGE OPERATOR, ENGINEER, ELECTRICIAN, CHIEF WELDER, CHIEF MATE, FILL PLACER, OPERATOR II, MAINTENANCE ENGINEER, LICENSED BOAT OPERATOR, LICENSED CREW BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55
Footnote A, B below
ENGI0025-001
10/01/2025
$41.93 $14.90 $56.83
DREDGING: CLASS B2: CERTIFIED WELDER. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF ...DREDGING: CLASS B2: CERTIFIED WELDER. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55
Footnote A, B below
ENGI0025-001
10/01/2025
$39.46 $14.73 $54.19
DREDGING: CLASS C1: MATE, DRAG BARGE OPERATOR, ASSISTANT FILL PLACER, WELDER, STEWARD. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 ...DREDGING: CLASS C1: MATE, DRAG BARGE OPERATOR, ASSISTANT FILL PLACER, WELDER, STEWARD. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55
Footnote A, B below
ENGI0025-001
10/01/2025
$38.38 $14.66 $53.04
DREDGING: CLASS C2: BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOW...DREDGING: CLASS C2: BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55
Footnote A, B below
ENGI0025-001
10/01/2025
$37.15 $14.57 $51.72
DREDGING: CLASS D: OILER, DECKHAND, SHOREMAN, RODMAN, SCOWMAN, COOK, MESSMAN, PORTER/JANITOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVE...DREDGING: CLASS D: OILER, DECKHAND, SHOREMAN, RODMAN, SCOWMAN, COOK, MESSMAN, PORTER/JANITOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55
Footnote A, B below
ENGI0025-001
10/01/2025
$30.86 $14.15 $45.01
Footnotes in NY20260001 (2)
  • ENGI0025-001 A: PAID HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING, JR.'S BIRTHDAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY AND CHRISTMAS DAY
  • ENGI0025-001 B: VACATION: EIGHT PERCENT (8%) OF THE STRAIGHT TIME RATE, MULTIPLIED BY THE TOTAL HOURS WORKED

Questions about these rates

What is the Davis-Bacon rate for electricians on heavy work in Herkimer County?
On WD NY20260031 Mod 2, published May 18, 2026, the row "ELECTRICIAN" is $50.50 base plus $35.03 fringe, $85.53 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for plumbers on heavy work in Herkimer County?
On WD NY20260031 Mod 2, published May 18, 2026, the row "PLUMBER, INCLUDING STEAMFITTING (NORTHERN ZONE)" is $45.93 base plus $33.77 fringe, $79.70 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for carpenters on heavy work in Herkimer County?
On WD NY20260031 Mod 2, published May 18, 2026, the row "CARPENTER (HEAVY & HIGHWAY CONSTRUCTION)" is $44.52 base plus $27.16 fringe, $71.68 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
Which wage determination applies to my project?
The one in your contract. A WD is generally locked in when the contract is awarded (for sealed bids, a modification published at least 10 days before bid opening applies), and later modifications do not change it except in cases such as added out-of-scope work or option extensions. See 29 CFR 1.6(c).
What counts as heavy construction?
Projects that are not building, residential or highway: for example dams, sewer and water lines, utilities and other civil work. The contracting agency picks the construction type; it is written into your contract with the WD. Source: DOL All Agency Memorandum 130.
What if my worker's trade is not on the list?
Work that needs a classification the WD does not list is added after award through a conformance request, which goes through the contracting agency to the Department of Labor (29 CFR 5.5(a)(1)(iii)). Do not use a different classification because its rate looks close.

Using these rates on a WH-347

Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.

Make this week's WH-347 with NY20260031

Other counties: all New York counties · WD lookup

Your first certified payroll is free.

Upload last week's payroll, get a checked WH-347 back today.

No card. Same full report, no watermark.