Davis-Bacon wage rates · New York
Kings County heavy construction wage rates
Federal prevailing wage rates for heavy construction in Kings County, New York, from the wage determinations SAM.gov lists for this county. Rates are shown exactly as published.
- Wage determination
- NY20260003
- Modification
- 6
- Published
- August 13, 2026
- Classifications
- 120
- Other types here
- Building, Residential, Highway
2 wage determinations cover heavy work in Kings County. They differ by scope (for example landscaping, dredging or part of the county). Use the WD number written in your contract; the scope text under each one says what it covers.
These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See New York prevailing wage for how the two fit together.
1 of 2: WD NY20260003, Mod 6
Make a WH-347 with these ratesScope as published: BUILDING CONSTRUCTION PROJECTS · RESIDENTIAL CONSTRUCTION PROJECTS (consisting of single family homes and apartments up to and including 4 stories) · HIGHWAY CONSTRUCTION PROJECTS · HEAVY CONSTRUCTION PROJECTS
| Classification | Rate ID | Base | Fringe | Total / hour |
|---|---|---|---|---|
| ASBESTOS WORKERS/INSULATOR (INCLUDES APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS.) | ASBE0012-001 06/01/2025 | $71.76 | $36.81 | $108.57 |
| BOILERMAKER Footnote A below | BOIL0005-001 01/01/2025 | $68.88 | $49.83 | $118.71 |
| BRICKLAYER | BRNY0001-001 07/01/2024 | $67.39 | $35.90 | $103.29 |
| BRICKLAYER (MARBLE POLISHERS) | BRNY0024-001 06/03/2024 | $52.32 | $36.25 | $88.57 |
| CARPENTER, BUILDING & RESIDENTIAL (BRONX AND NEW YORK COUNTIES) | CARP0157-001 07/01/2025 | $59.05 | $48.08 | $107.13 |
| CARPENTER, BUILDING & RESIDENTIAL (KINGS COUNTY) | CARP0926-001 07/01/2025 | $59.05 | $48.08 | $107.13 |
| CARPENTER, BUILDING & RESIDENTIAL (QUEENS COUNTY) | CARP0045-001 07/01/2025 | $59.05 | $48.08 | $107.13 |
| CARPENTER, BUILDING & RESIDENTIAL (RICHMOND COUNTY) | CARP0020-001 07/01/2025 | $59.05 | $48.08 | $107.13 |
| CARPENTER: HEAVY & HIGHWAY (BRONX AND NEW YORK COUNTIES) | CARP0157-002 07/01/2025 | $61.59 | $55.84 | $117.43 |
| CARPENTER: HEAVY & HIGHWAY (KINGS COUNTY) | CARP0926-002 07/01/2025 | $61.59 | $55.84 | $117.43 |
| CARPENTER: HEAVY & HIGHWAY (QUEENS COUNTY) | CARP0045-002 07/01/2025 | $61.59 | $55.84 | $117.43 |
| CARPENTER: HEAVY & HIGHWAY (RICHMOND COUNTY) | CARP0020-002 07/01/2025 | $61.59 | $55.84 | $117.43 |
| CARPENTERS: (SOFT FLOOR LAYERS) | CARP2287-004 07/01/2025 | $59.05 | $48.08 | $107.13 |
| CARPENTERS: (TIMBERMEN) | CARP1556-011 07/01/2024 | $55.59 | $55.41 | $111.00 |
| CEMENT MASON/CONCRETE FINISHER | PLAS0780-001 07/01/2025 | $59.87 | $41.81 | $101.68 |
| DIVER | CARP1556-007 07/01/2024 | $75.46 | $55.84 | $131.30 |
| DIVER TENDER | CARP1556-007 07/01/2024 | $55.00 | $55.84 | $110.84 |
| DOCK BUILDER & PILEDRIVERMEN | CARP1556-006 07/01/2024 | $60.59 | $55.84 | $116.43 |
| ELECTRICIAN Footnote A below | ELEC0003-001 04/10/2024 | $62.00 | $65.81 | $127.81 |
| ELECTRICIAN (JOBBING, AND MAINTENANCE AND REPAIR WORK) Footnote A below | ELEC0003-001 04/10/2024 | $32.00 | $27.16 | $59.16 |
| ELEVATOR MECHANIC (ELEVATOR CONSTRUCTOR) Footnote A, B below | ELEV0001-002 03/17/2022 | $75.14 | $47.45 | $122.59 |
| ELEVATOR MECHANIC (MODERNIZATION AND REPAIR) Footnote A, B below | ELEV0001-002 03/17/2022 | $59.09 | $45.56 | $104.65 |
| GLAZIER | PAIN0009-001 05/01/2025 | $49.20 | $57.20 | $106.40 |
| HAZARDOUS MATERIAL HANDLER | ASBE0012-001 01/01/2025 | $47.75 | $13.70 | $61.45 |
| IRONWORKER (METALLIC LATHERS AND REINFORCING IRONWORKERS) | IRON0046-003 07/01/2025 | $57.00 | $32.96 | $89.96 |
| IRONWORKER (STONE DERRICKMAN) | IRON0197-001 07/01/2024 | $60.40 | $60.14 | $120.54 |
| IRONWORKER, STRUCTURAL (BRONX, NEW YORK, RICHMOND) | IRON0040-002 07/01/2025 | $58.95 | $92.02 | $150.97 |
| IRONWORKER: ORNAMENTAL | IRON0580-001 07/01/2025 | $48.15 | $67.62 | $115.77 |
| IRONWORKERS: (STRUCTURAL) (KINGS, QUEENS) | IRON0361-002 07/01/2025 | $58.95 | $92.02 | $150.97 |
| LABORER (CEMENT AND CONCRETE WORKERS) | LABO0006-001 07/01/2022 | $49.28 | $27.05 | $76.33 |
| LABORER BUILDING, HEAVY AND RESIDENTIAL CONSTRUCTION LABORER: (ASBESTOS, LEAD, HAZARDOUS WASTE REMOVAL (INCLUDING SOIL)/CEMENT/CONCRETE | LABO0731-001 07/01/2023 | $44.50 | $52.08 | $96.58 |
| LABORER BUILDING, HEAVY AND RESIDENTIAL CONSTRUCTION UTILITY LABORER Footnote NOTE below | LABO0731-001 07/01/2023 | $44.35 | $52.08 | $96.43 |
LABORER, BUILDING CONSTRUCTION: DEMOLITION LABORERS (INTERIOR) (Tier A- RESPONSIBLE FOR THE REMOVAL OF ALL INTERIOR PETITIONS AND STRUCTURAL PETITIONS THAT CAN CONSIST OF SHEET ROCK, BLOCK OR MASONRY....LABORER, BUILDING CONSTRUCTION: DEMOLITION LABORERS (INTERIOR) (Tier A- RESPONSIBLE FOR THE REMOVAL OF ALL INTERIOR PETITIONS AND STRUCTURAL PETITIONS THAT CAN CONSIST OF SHEET ROCK, BLOCK OR MASONRY. ALSO AL STRUCTURAL SLAB OPENINGS AND EXTERIOR WALLS WHERE THE BUILDING IS NOT BEING COMPLETELY DEMOLITIONED) | LABO0079-001 07/01/2025 | $40.22 | $25.17 | $65.39 |
| LABORER, BUILDING CONSTRUCTION: DEMOLITION LABORERS (INTERIOR) (Tier B- RESPONSIBLE FOR SHOVELING OF DEBRIS INTO CONTAINER, PUSHING CONTAINERS FROM THE INSIDE TO THE OUTSIDE OF THE BUILDING) | LABO0079-001 07/01/2025 | $29.29 | $20.29 | $49.58 |
| LABORER, BUILDING CONSTRUCTION: MASON TENDER/GENERAL LABORER | LABO0079-001 07/01/2025 | $44.70 | $29.55 | $74.25 |
| LABORERS-ASPHALT CONSTRUCTION: (MICRO PAVER) | LABO1010-002 07/01/2025 | $50.80 | $54.05 | $104.85 |
| LABORERS-ASPHALT CONSTRUCTION: (RAKER) | LABO1010-002 07/01/2025 | $50.20 | $54.05 | $104.25 |
| LABORERS-ASPHALT CONSTRUCTION: (SCREEDPERSON) | LABO1010-002 07/01/2025 | $50.80 | $54.05 | $104.85 |
| LABORERS-ASPHALT CONSTRUCTION: (SHOVELER (PRODUCTION PAVING ONLY)) | LABO1010-002 07/01/2025 | $46.33 | $54.05 | $100.38 |
| LABORERS-ASPHALT CONSTRUCTION: (SMALL EQUIPMENT OPERATOR (ASPHALT)) | LABO1010-002 07/01/2025 | $46.33 | $54.05 | $100.38 |
LABORERS: ASBESTOS (REMOVAL, ABATEMENT, ENCAPSULATION OR DECONTAMINATION OF ASBESTOS); LEAD; & HAZARDOUS WASTE LABORERS (HAZARDOUS WASTE, HAZARDOUS MATERIALS, BIOCHEMICAL AND MOLD REMEDIATION, HVAC, D...LABORERS: ASBESTOS (REMOVAL, ABATEMENT, ENCAPSULATION OR DECONTAMINATION OF ASBESTOS); LEAD; & HAZARDOUS WASTE LABORERS (HAZARDOUS WASTE, HAZARDOUS MATERIALS, BIOCHEMICAL AND MOLD REMEDIATION, HVAC, DUCT CLEANING, RE-SPRAY FIREPROOFING, ETC) (BUILDING CONSTRUCTION) | LABO0078-001 01/06/2025 | $41.15 | $20.90 | $62.05 |
| LABORERS: FENCE INSTALLER & REPAIRER (HIGHWAY CONSTRUCTION) Footnote A below | LABO1010-001 07/01/2025 | $46.33 | $54.04 | $100.37 |
| LABORERS: FORMSETTERS (HIGHWAY CONSTRUCTION) Footnote A below | LABO1010-001 07/01/2025 | $50.80 | $54.04 | $104.84 |
LABORERS: FREE AIR & TUNNEL MAINTENANCE MEN, INSIDE MUCK LOCK TENDERS, PUMP MEN, ELECTRICIANS, CEMENT FINISHERS, CAULKERS, HYDRAULIC MEN, SHIELD MEN, MONORAIL OPERATORS, MOTOR MEN, CONVEYOR MEN, POWDE...LABORERS: FREE AIR & TUNNEL MAINTENANCE MEN, INSIDE MUCK LOCK TENDERS, PUMP MEN, ELECTRICIANS, CEMENT FINISHERS, CAULKERS, HYDRAULIC MEN, SHIELD MEN, MONORAIL OPERATORS, MOTOR MEN, CONVEYOR MEN, POWDER CARRIERS, PAN MEN, RIGGERS, CHUCK TENDERS, TRACK MEN PAINTERS, NIPPERS, BRAKEMEN, CABLE MEN, HOSE MEN, GROUT MEN, GRAVEL MEN, FORM WORKERS, CONCRETE WORKERS, TUNNEL LABORERS, MOLE NIPPER (ONE (1) MOLE SIPPER PER WORKING SHAFT PER SHIFT FOR UP TO AND INCLUDING TWO (2) MOLES | LABO0147-001 07/01/2022 | $64.08 | $54.00 | $118.08 |
| LABORERS: HEAVY (BLASTERS (HYDRAULIC TRAC DRILL)) | LABO0731-002 07/01/2023 | $51.85 | $52.08 | $103.93 |
| LABORERS: HEAVY (BLASTERS) | LABO0731-002 07/01/2023 | $57.71 | $52.08 | $109.79 |
| LABORERS: HEAVY (HYDRAULIC TRAC DRILL) | LABO0731-002 07/01/2023 | $51.85 | $52.08 | $103.93 |
| LABORERS: HEAVY (POWDER CARRIERS) | LABO0731-002 07/01/2023 | $44.50 | $52.08 | $96.58 |
| LABORERS: LABORERS (HIGHWAY CONSTRUCTION) Footnote A below | LABO1010-001 07/01/2025 | $46.33 | $54.04 | $100.37 |
| LABORERS: LANDSCAPE PLANTING & MAINTENANCE (HIGHWAY CONSTRUCTION) Footnote A below | LABO1010-001 07/01/2025 | $46.33 | $54.04 | $100.37 |
| LABORERS: MAINTENANCE SAFETY SURFACE (HIGHWAY CONSTRUCTION) Footnote A below | LABO1010-001 07/01/2025 | $46.33 | $54.04 | $100.37 |
| LABORERS: SLURRY/SEALCOATER/PLAY EQUIPMENT INSTALLER (HIGHWAY CONSTRUCTION) Footnote A below | LABO1010-001 07/01/2025 | $46.33 | $54.04 | $100.37 |
| LABORERS: SMALL EQUIPMENT OPERATOR (NOT OPERATING ENGINEER) (HIGHWAY CONSTRUCTION) Footnote A below | LABO1010-001 07/01/2025 | $46.33 | $54.04 | $100.37 |
| LABORERS: SMALL POWER TOOLS OPERATOR (HIGHWAY CONSTRUCTION) Footnote A below | LABO1010-001 07/01/2025 | $46.33 | $54.04 | $100.37 |
| LABORERS:, HEAVY (JACKHAMMERS, CHIPPERS, SPADERS, CONCRETE BREAKERS, ALL OTHER PNEUMATIC TOOLS, WALK BEHIND SELF-PROPELLED HYDRAULIC ASPHALT AND CONCRETE BREAKER) | LABO0731-002 07/01/2023 | $44.50 | $52.08 | $96.58 |
LINE CONSTRUCTION, SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NO...LINE CONSTRUCTION, SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NOT PERFORMED BY RAILROAD EMPLOYEES) OVERHEAD AND UNDERGROUND TRANSMISSION/DISTRIBUTION LINE WORK. FIBER OPTIC, TELEPHONE CABLE AND EQUIPMENT: GROUNDMAN (QUEENS COUNTY) | ELEC1049-001 03/30/2025 | $42.34 | $30.05 | $72.39 |
LINE CONSTRUCTION, SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NO...LINE CONSTRUCTION, SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NOT PERFORMED BY RAILROAD EMPLOYEES) OVERHEAD AND UNDERGROUND TRANSMISSION/DISTRIBUTION LINE WORK. FIBER OPTIC, TELEPHONE CABLE AND EQUIPMENT: HEAVY EQUIPMENT OPERATOR (QUEENS COUNTY) | ELEC1049-001 03/30/2025 | $56.46 | $34.63 | $91.09 |
LINE CONSTRUCTION, SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NO...LINE CONSTRUCTION, SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NOT PERFORMED BY RAILROAD EMPLOYEES) OVERHEAD AND UNDERGROUND TRANSMISSION/DISTRIBUTION LINE WORK. FIBER OPTIC, TELEPHONE CABLE AND EQUIPMENT: LINEMAN AND CABLE SPLICER (QUEENS COUNTY) | ELEC1049-001 03/30/2025 | $70.57 | $39.19 | $109.76 |
| MARBLE FINISHER | BRNY0020-001 07/01/2024 | $49.99 | $37.54 | $87.53 |
| MARBLE MASON | BRNY0004-001 07/01/2024 | $63.92 | $40.20 | $104.12 |
| MASON - STONE | BRNY0001-001 05/01/2024 | $69.91 | $44.02 | $113.93 |
| MILLWRIGHT | CARP0740-001 07/01/2025 | $60.83 | $58.03 | $118.86 |
| PAINTER (PAINTERS, DRYWALL FINISHERS, LEAD ABATEMENT WORKER) | PAIN0009-001 05/01/2025 | $44.75 | $44.11 | $88.86 |
| PAINTER (SPRAY, SCAFFOLD AND SANDBLASTING) | PAIN0009-001 05/01/2025 | $47.75 | $44.11 | $91.86 |
| PAINTERS: (DRYWALL TAPERS/POINTERS) | PAIN1974-001 06/28/2025 | $48.47 | $35.91 | $84.38 |
| PAINTERS: (STRUCTURAL STEEL AND BRIDGE) | PAIN0806-001 10/01/2024 | $56.25 | $55.14 | $111.39 |
| PLASTERER | PLAS0262-001 08/01/2025 | $48.51 | $32.78 | $81.29 |
| PLASTERER (KINGS AND QUEENS COUNTIES) | PLAS0262-002 08/01/2025 | $48.51 | $32.78 | $81.29 |
| PLUMBER | PLUM0001-001 07/01/2025 | $73.00 | $32.81 | $105.81 |
| PLUMBER: MECHANICAL EQUIPMENT AND SERVICE (ANY REPAIR AND/OR REPLACEMENT OF THE PRESENT PLUMBING SYSTEM THAT DOES NOT CHANGE THE EXISTING ROUGHING) | PLUM0001-001 07/01/2025 | $48.90 | $22.26 | $71.16 |
PLUMBER: SERVICE FITTERS (SERVICE FITTER WORK SHALL CONSIST OF ALL REPAIR, SERVICE AND MAINTENANCE WORK ON DOMESTIC, COMMERICAL AND INDUSTRIAL REFRIGERATION, AIR CONDITIONING AND AIR COOLING, STOKER A...PLUMBER: SERVICE FITTERS (SERVICE FITTER WORK SHALL CONSIST OF ALL REPAIR, SERVICE AND MAINTENANCE WORK ON DOMESTIC, COMMERICAL AND INDUSTRIAL REFRIGERATION, AIR CONDITIONING AND AIR COOLING, STOKER AND OIL BURNER APPARATUS AND HEATING APPARATUS ETC., INCLUDING BUTNOT EXCLUSIVELY FOR CHARGING, EVACUATION, LEAK TESTING AND ASSEMBLING FOR ALL MACHINES FOR DOMESTIC, COMMERCIAL AND INDUSTRIAL REFRIGERATION, AIR CONDITIONING AND HEATING APPARATUS. ALSO, WORK SHALL INCLUDE ADJUSTING, INCLUDING CAPACITY ADJUSTMENTS, CHECKING AND REPAIRING OR REPLACEMENT OF ALL CONTROLS AND START UP OF ALL MACHINES AND REPAIRING ALL DEFECTS THAT MAY DEVELOP ON ANY SYSTEM FOR DOMESTIC, COMMERCIAL AND INDUSTRIAL REFRIGERATION AND ALL AIR CONDITIONING, AIR COOLING, SOKER AND OIL BURNER APPARATUS AND HEATING APPARATUS REGARDLESS OF SIZE OR TYPE.) | PLUM0638-001 01/01/2026 | $47.85 | $23.96 | $71.81 |
| PLUMBER: SPRINKLER FITTERS, STEAMFITTERS | PLUM0638-001 01/01/2026 | $70.36 | $54.24 | $124.60 |
| POINTER, CLEANER AND CAULKER | BRNY0001-002 07/01/2024 | $63.69 | $32.42 | $96.11 |
| POWER EQUIPMENT OPERATOR GROUP 1 (BUILDING & RESIDENTIAL) DOUBLE DRUM Footnote A below | ENGI0014-002 07/01/2025 | $92.32 | $38.95 | $131.27 |
| POWER EQUIPMENT OPERATOR GROUP 1 (BUILDING) OILER Footnote A below | ENGI0015-002 07/01/2016 | $65.94 | $32.95 | $98.89 |
POWER EQUIPMENT OPERATOR GROUP 1 (HEAVY AND HIGHWAY) CHERRYPICKERS 20 TONS AND OVER AND LOADERS (RUBBER-TIRED AND/OR TRACTOR TYPE WITH A MANFUFACTURER'S RATED CAPACITY OF SIX CUBIC YARDS AND OVER PREM...POWER EQUIPMENT OPERATOR GROUP 1 (HEAVY AND HIGHWAY) CHERRYPICKERS 20 TONS AND OVER AND LOADERS (RUBBER-TIRED AND/OR TRACTOR TYPE WITH A MANFUFACTURER'S RATED CAPACITY OF SIX CUBIC YARDS AND OVER PREMIUMS FOR CRANES: 100'-149' BOOM - ADD 1.75 150'-249' BOOM - ADD 2.00 250'-349' BOOM - ADD 2.25 350'-450' BOOM - ADD 2.75 TOWER CRANES ADD 2.00 | ENGI0015-001 07/01/2021 | $74.65 | $38.00 | $112.65 |
POWER EQUIPMENT OPERATOR GROUP 2 (BUILDING & RESIDENTIAL) STONE DERRICK, CRANES, HYDRAULIC CRANES, BOOM TRUCKS PREMIUMS FOR CRANES: 100'-149' BOOM - ADD 1.75 150'-249' BOOM - ADD 2.00 250'-349' BOOM -...POWER EQUIPMENT OPERATOR GROUP 2 (BUILDING & RESIDENTIAL) STONE DERRICK, CRANES, HYDRAULIC CRANES, BOOM TRUCKS PREMIUMS FOR CRANES: 100'-149' BOOM - ADD 1.75 150'-249' BOOM - ADD 2.00 250'-349' BOOM - ADD 2.25 350'-450' BOOM - ADD 2.75 TOWER CRANES ADD 2.00 | ENGI0014-002 07/01/2025 | $97.79 | $38.95 | $136.74 |
| POWER EQUIPMENT OPERATOR GROUP 2 (BUILDING) OILERS ON CRAWLER CRANES, BACKHOES, TRENCHING MACHINES, GUNITE MACHINES, COMPRESSORS (3 OR MORE IN BATTERY) Footnote A below | ENGI0015-002 07/01/2016 | $63.98 | $32.95 | $96.93 |
POWER EQUIPMENT OPERATOR GROUP 2 (HEAVY AND HIGHWAY) RUBBER TIRE BACKHOES UP TO AND INCLUDING 37,000 LBS, BASIN MACHINES, GROOVER, MECHANICAL SWEEPERS, BOBCAT, BOOM TRUCK, BARRIER TRANSPORT (BARRIER M...POWER EQUIPMENT OPERATOR GROUP 2 (HEAVY AND HIGHWAY) RUBBER TIRE BACKHOES UP TO AND INCLUDING 37,000 LBS, BASIN MACHINES, GROOVER, MECHANICAL SWEEPERS, BOBCAT, BOOM TRUCK, BARRIER TRANSPORT (BARRIER MOVER) AND MACHINES OF A SIMILAR NATURE, BOAT CAPTAINS, BOAT OPERATORS, OPERATION OF CHURN DRILLS AND MACHINES OF A SIMILAR NATURE, STETCO SILENT HOIST AND MACHINES OF A SIMILAR NATURE, VAC-ALLS, MEYERS MACHINES, JOHN BEAM AND MACHINES OF A SIMILAR NATURE, ROSS CARRIERS AND TRAVEL LIFTS AND MACHINES OF A SIMILAR NATURE, BULLDOZERS, SCRAPERS, AND TURN-A PULLS, TUGGER HOIST (USED EXCLUSIVELY FOR HANDLING EXCAVATED MATERIAL), TRACTORS WITH ATTACHMENTS, HYSTER AND ROUSTABOUT CRANES, CHERRYPICKERS, AUSTIN WESTERN, GROVE AND MACHINES OF A SIMILAR NATURE, SCOOPMOBILES, MONORAILS, CONVEYORS, TRENCHERS, LOADERS- RUBBER-TIRED AND TRACTOR, BARBER GREENE, EIMCO LOADERS AND EIMCO BACKHOES, MIGHTY MIDGET AND SIMILAR BREAKERS AND TAMPERS, CURB AND GUTTER PAVERS AND MOTOR PATROL, MOTOR GRADERS AND ALL MACHINES OF A SIMILAR NATURE, LOCOMOTIVES TEN (10) TONS OR UNDER, MINI-MAX, BREAK-TECH AND MACHINES OF A SIMILAR NATURE, MILLING MACHINES, ROBOTIC AND DEMOLITION MACHINES AND MACHINES OF A SIMILAR NATURE INCLUDING BOBCAT, PILE RIG RUBBER-TIRED EXCAVATOR (37,000 LBS. AND UNDER), 2 MAN AUGER PREMIUMS FOR CRANES: 100'-149' BOOM - ADD 1.75 150'-249' BOOM - ADD 2.00 250'-349' BOOM - ADD 2.25 350'-450' BOOM - ADD 2.75 TOWER CRANES ADD 2.00 | ENGI0015-001 07/01/2021 | $72.40 | $38.00 | $110.40 |
| POWER EQUIPMENT OPERATOR GROUP 3 (BUILDING & RESIDENTIAL) 4 POLE HOIST, SINGLE DRUM HOISTS Footnote A below | ENGI0014-002 07/01/2025 | $79.70 | $38.95 | $118.65 |
| POWER EQUIPMENT OPERATOR GROUP 3 (BUILDING) GRADALLS: CONCRETE PUMPS, POWER HOUSES - ALL EQUIPMENT IN SAME IS MANNED BY TWO (2) MEN ONLY, DRIVING TRUCK CRANES Footnote A below | ENGI0015-002 07/01/2016 | $57.42 | $32.95 | $90.37 |
POWER EQUIPMENT OPERATOR GROUP 3 (HEAVY AND HIGHWAY) MINOR EQUIPMENT SUCH AS TRACTORS, POST HOLE DIGGERS AND DRIVERS, DITCH WITCH (WALK BEHIND), ROAD FINISHING MACHINES, ROLLERS (FIVE (5) TONS AND UND...POWER EQUIPMENT OPERATOR GROUP 3 (HEAVY AND HIGHWAY) MINOR EQUIPMENT SUCH AS TRACTORS, POST HOLE DIGGERS AND DRIVERS, DITCH WITCH (WALK BEHIND), ROAD FINISHING MACHINES, ROLLERS (FIVE (5) TONS AND UNDER), TUGGER HOISTS, DUAL PURPOSE TRUCKS, FORK LIFTS AND DEMPSEY DUMPSTERS PREMIUMS FOR CRANES: 100'-149' BOOM - ADD 1.75 150'-249' BOOM - ADD 2.00 250'-349' BOOM - ADD 2.25 350'-450' BOOM - ADD 2.75 TOWER CRANES ADD 2.00 | ENGI0015-001 07/01/2021 | $68.62 | $38.00 | $106.62 |
| POWER EQUIPMENT OPERATOR GROUP 4 (BUILDING & RESIDENTIAL) FORK LIFT, HOUSE CARS, PLASTER (PLATFORM MACHINE), PLASTER BUCKET, CONCRETE PUMP AND ALL OTHER EQUIPMENT USED FOR HOISTING MATERIAL Footnote A below | ENGI0014-002 07/01/2025 | $72.46 | $38.95 | $111.41 |
POWER EQUIPMENT OPERATOR GROUP 4 (HEAVY AND HIGHWAY) OILERS FOR THE FOLLOWING EQUIPMENT: (ALL GASOLINE, ELECTRIC, DIESEL, OR AIR OPERATED) GRADALLS AND CONCRETE PUMPS OR SIMILARLY EQUIPMENT MANNED BY ...POWER EQUIPMENT OPERATOR GROUP 4 (HEAVY AND HIGHWAY) OILERS FOR THE FOLLOWING EQUIPMENT: (ALL GASOLINE, ELECTRIC, DIESEL, OR AIR OPERATED) GRADALLS AND CONCRETE PUMPS OR SIMILARLY EQUIPMENT MANNED BY TWO-MEN PREMIUMS FOR CRANES: 100'-149' BOOM - ADD 1.75 150'-249' BOOM - ADD 2.00 250'-349' BOOM - ADD 2.25 350'-450' BOOM - ADD 2.75 TOWER CRANES ADD 2.00 | ENGI0015-001 07/01/2021 | $64.82 | $38.00 | $102.82 |
POWER EQUIPMENT OPERATOR GROUP 5 (BUILDING & RESIDENTIAL) COMPRESSORS, WELDING MACHINES (CUTTING CONCRETE WORK), PAINT SPRAYING, SAND BLASTING, PUMPS (WITH THE EXCLUSION OF CONCRETE PUMPS), HOUSE CAR ...POWER EQUIPMENT OPERATOR GROUP 5 (BUILDING & RESIDENTIAL) COMPRESSORS, WELDING MACHINES (CUTTING CONCRETE WORK), PAINT SPRAYING, SAND BLASTING, PUMPS (WITH THE EXCLUSION OF CONCRETE PUMPS), HOUSE CAR (SETTLEMENT BASIS ONLY), ALL ENGINES IRRESPECTIVE OF POWER (POWER PAC) USED TO DRIVE AUXILIARY EQUIPMENT, AIR, HYDRAULIC, ETC., BOILERS | ENGI0014-002 07/01/2025 | $54.12 | $38.95 | $93.07 |
POWER EQUIPMENT OPERATOR GROUP 5 (HEAVY AND HIGHWAY) OILERS FOR THE FOLLOWING EQUIPMENT: (ALL GASOLINE, ELECTRIC, DIESEL, OR AIR OPERATED) SHOVELS, CRANES (DRAGLINES), BACKHOES, PAVERS, TRENCHING MACH...POWER EQUIPMENT OPERATOR GROUP 5 (HEAVY AND HIGHWAY) OILERS FOR THE FOLLOWING EQUIPMENT: (ALL GASOLINE, ELECTRIC, DIESEL, OR AIR OPERATED) SHOVELS, CRANES (DRAGLINES), BACKHOES, PAVERS, TRENCHING MACHINES, GUNITE MACHINES, COMPRESSORS (3 OR MORE IN BATTERY) PREMIUMS FOR CRANES: 100'-149' BOOM - ADD 1.75 150'-249' BOOM - ADD 2.00 250'-349' BOOM - ADD 2.25 350'-450' BOOM - ADD 2.75 TOWER CRANES ADD 2.00 | ENGI0015-001 07/01/2021 | $44.45 | $38.00 | $82.45 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 1 TOWER CRANE PREMIUMS ON CRANES (CRAWLER OR TRUCK): 100' TO 149' BOOM - ADD.50 150' TO 249' BOOM - ADD.75 250' TO 349' BOOM - ADD 1.00 350' TO 450' BOOM - ADD 1.50 Footnote A below | ENGI0014-001 07/01/2025 | $117.60 | $38.95 | $156.55 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 10 CONCRETE MIXERS Footnote A below | ENGI0014-001 07/01/2025 | $85.21 | $38.95 | $124.16 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 11 ELEVATORS Footnote A below | ENGI0014-001 07/01/2025 | $79.62 | $38.95 | $118.57 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 12 CONCRETE BREAKING MACHINE, HOISTS (SINGLE DRUM), LOAD MASTERS, LOCOMOTIVE AND DINKIES OVER 10 Footnote A below | ENGI0014-001 07/01/2025 | $81.38 | $38.95 | $120.33 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 13 VIBRATORY Footnote A below | ENGI0014-001 07/01/2025 | $81.97 | $38.95 | $120.92 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 14 COMPRESSORS (PORTABLE 3 OR MORE IN BATTERY), TUGGER MACHINE (CAISSONS), WELL POINT PUMPS, CHUM DRILL Footnote A below | ENGI0014-001 07/01/2025 | $61.87 | $38.95 | $100.82 |
POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 15 BOILERS, (HIGH PRESSURE, COMPRESSORS (PORTABLE, SINGLE, OR 2 IN BATTERY, NOT OVER 100' APART), PUMPS (RIVER COFFERDAM AND WELDING MACHINES (EXCEPT W...POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 15 BOILERS, (HIGH PRESSURE, COMPRESSORS (PORTABLE, SINGLE, OR 2 IN BATTERY, NOT OVER 100' APART), PUMPS (RIVER COFFERDAM AND WELDING MACHINES (EXCEPT WHERE ARC IS OPERATED BY MEMBERS OF LOCAL 15) PUSH BUTTON MACHINES, ALL ENGINES IRRESPECTIVE OF POWER (POWER PAC) USED TO DRIVE AUXILLIARY EQUIPMENT, AIR, HYDRAULIC ETC | ENGI0014-001 07/01/2025 | $57.52 | $38.95 | $96.47 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 2 RUBBER TIRE BACKHOES OVER 37,000 LBS, TRACK BACKHOES, POWER SHOVEL, HYDRAULIC CLAM SHELLS, MOLES AND MACHINES OF A SIMILAR TYPE Footnote A below | ENGI0014-001 07/01/2025 | $97.06 | $38.95 | $136.01 |
POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 3 MINE HOISTS AND CRANE, ETC. USED AS MINE HOISTS REMIUMS ON CRANES (CRAWLER OR TRUCK): 100' TO 149' BOOM - ADD.50 150' TO 249' BOOM - ADD.75 250' TO 3...POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 3 MINE HOISTS AND CRANE, ETC. USED AS MINE HOISTS REMIUMS ON CRANES (CRAWLER OR TRUCK): 100' TO 149' BOOM - ADD.50 150' TO 249' BOOM - ADD.75 250' TO 349' BOOM - ADD 1.00 350' TO 450' BOOM - ADD 1.50 | ENGI0014-001 07/01/2025 | $100.18 | $38.95 | $139.13 |
POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 4 GRADALLS, KEYSTONES, CRANES (WITH DIGGING BUCKETS), BRIDGE CRANES, TRENCHING MACHINES, VERMEER CUTTER AND MACHINES OF A SIMILAR NATURE REMIUMS ON CRA...POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 4 GRADALLS, KEYSTONES, CRANES (WITH DIGGING BUCKETS), BRIDGE CRANES, TRENCHING MACHINES, VERMEER CUTTER AND MACHINES OF A SIMILAR NATURE REMIUMS ON CRANES (CRAWLER OR TRUCK): 100' TO 149' BOOM - ADD.50 150' TO 249' BOOM - ADD.75 250' TO 349' BOOM - ADD 1.00 350' TO 450' BOOM - ADD 1.50 | ENGI0014-001 07/01/2025 | $97.75 | $38.95 | $136.70 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 5 PILEDRIVERS, DERRICK BOATS, TUNNEL SHOVELS Footnote A below | ENGI0014-001 07/01/2025 | $95.83 | $38.95 | $134.78 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 6 ALL DRILLS, AND MACHINES OF A SIMILAR NATURE Footnote A below | ENGI0014-001 07/01/2025 | $92.01 | $38.95 | $130.96 |
POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 7 BACK FILLING MACHINES, CRANES, MUCKING MACHINES, DUAL DRUM PAVERS REMIUMS ON CRANES (CRAWLER OR TRUCK): 100' TO 149' BOOM - ADD.50 150' TO 249' BOOM ...POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 7 BACK FILLING MACHINES, CRANES, MUCKING MACHINES, DUAL DRUM PAVERS REMIUMS ON CRANES (CRAWLER OR TRUCK): 100' TO 149' BOOM - ADD.50 150' TO 249' BOOM - ADD.75 250' TO 349' BOOM - ADD 1.00 350' TO 450' BOOM - ADD 1.50 | ENGI0014-001 07/01/2025 | $93.74 | $38.95 | $132.69 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 8 MIXERS (CONCRETE W/LOADING ATTACHMENTS), CONCRETE PAVERS, CABLEWAYS, LAND DERRICKS, POWER HOUSE (LOW PRESSURE UNITS), CONCRETE PUMPS Footnote A below | ENGI0014-001 07/01/2025 | $91.04 | $38.95 | $129.99 |
| POWER EQUIPMENT OPERATOR, HEAVY & HIGHWAY: GROUP 9 CONCRETE PLANTS, WELL DRILLING MACHINES, STONE CRUSHERS DOUBLE DRUM HOIST, POWER HOUSE (OTHER THAN ABOVE) Footnote A below | ENGI0014-001 07/01/2025 | $88.72 | $38.95 | $127.67 |
| POWER EQUIPMENT OPERATOR, PAVEMENT-HEAVY & HIGHWAY: ASPHALT PLANTS Footnote A below | ENGI0014-001 07/01/2025 | $75.01 | $38.95 | $113.96 |
| POWER EQUIPMENT OPERATOR, PAVEMENT-HEAVY & HIGHWAY: ASPHALT ROLLER Footnote A below | ENGI0014-001 07/01/2025 | $88.72 | $38.95 | $127.67 |
| POWER EQUIPMENT OPERATOR, PAVEMENT-HEAVY & HIGHWAY: ASPHALT SPREADER | ENGI0014-001 07/01/2025 | $91.04 | $38.95 | $129.99 |
| POWER EQUIPMENT OPERATOR, STEEL ERECTION: COMPRESSORS, WELDING MACHINES | ENGI0014-001 07/01/2024 | $56.34 | $36.95 | $93.29 |
| POWER EQUIPMENT OPERATOR, STEEL ERECTION: CRANES, HYDRAULIC CRANES, 2 DRUM DERRICKS, FORKLIFTS, BOOM TRUCKS | ENGI0014-001 07/01/2024 | $96.26 | $36.95 | $133.21 |
| POWER EQUIPMENT OPERATOR, STEEL ERECTION: THREE DRUM DERRICKS Footnote A below | ENGI0014-001 07/01/2024 | $100.14 | $36.95 | $137.09 |
| POWER EQUIPMENT OPERATOR: UTILITY: HORIZONTAL BORING RIG Footnote A below | ENGI0014-001 07/01/2025 | $86.61 | $38.95 | $125.56 |
| POWER EQUIPMENT OPERATOR: UTILITY: OFF SHIFT COMPRESSORS Footnote A below | ENGI0014-001 07/01/2025 | $71.98 | $38.95 | $110.93 |
| POWER EQUIPMENT OPERATOR: UTILITY: UTILITY COMPRESSORS Footnote A below | ENGI0014-001 07/01/2025 | $57.14 | $38.95 | $96.09 |
| ROOFER | ROOF0008-003 05/01/2025 | $50.25 | $32.62 | $82.87 |
| SHEET METAL WORKER (BUILDING CONSTRUCTION) | SHEE0028-002 11/02/2023 | $53.60 | $60.74 | $114.34 |
| SHEET METAL WORKER (RESIDENTIAL CONSTRUCTION) | SHEE0028-002 11/02/2023 | $35.79 | $25.37 | $61.16 |
| TERRAZZO FINISHER | BRNY0007-001 12/02/2024 | $49.59 | $34.25 | $83.84 |
| TERRAZZO WORKER/SETTER | BRNY0007-001 12/02/2024 | $64.62 | $37.63 | $102.25 |
| TILE FINISHER | BRNY0007-002 12/02/2024 | $49.59 | $34.25 | $83.84 |
| TILE LAYER | BRNY0052-001 06/03/2024 | $64.40 | $37.13 | $101.53 |
| TRUCK DRIVER EUCLIDS & TURNAPULLS Footnote NOTE below | TEAM0282-001 07/01/2025 | $49.38 | $57.65 | $107.03 |
| TRUCK DRIVER: ASPHALT Footnote NOTE below | TEAM0282-001 07/01/2025 | $46.12 | $59.65 | $105.77 |
| TRUCK DRIVER: HIGH RISE Footnote NOTE below | TEAM0282-001 07/01/2025 | $65.43 | $53.15 | $118.58 |
Footnotes in NY20260003 (11)
- BOIL0005-001 A: PAID HOLIDAYS: NEW YEAR'S DAY, THANKSGIVING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY AND GOOD FRIDAY, FRIDAY AFTER THANKSGIVING, CHRISTMAS EVE DAY AND NEW YEAR'S EVE
- ELEC0003-001 A: NEW YEARS DAY, MARTIN LUTHER KING, JR.'S BIRTHDAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, ELECTION DAY, THANKSGIVING DAY, THE DAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY
- ELEV0001-002 A: PAID HOLIDAYS: NEW YEAR'S DAY, GOOD FRIDAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY.
- ELEV0001-002 B: PAID VACATION: AN EMPLOYEE WHO HAS WORKED LESS THAN 5 YEARS SHALL RECIEVE VACATION PAY CREDIT ON THE BASIS OF 4% OF HIS HOURLY RATE FOR ALL HOURS WORKED; AN EMPLOYEE WHO HAS WORKED 5 TO 15 YEARS SHALL RECEIVE VACATION PAY CREDIT ON THE BASIS OF 6% OF HIS HOURLY RATE FOR ALL HOURS WORKED; AN EMPLOYEE WHO HAS WORKED 15 OR MORE YEARS SHALL RECEIVE VACATION PAY CREDIT ON THE BASIS OF 8% OF HIS HOURLY RATE FOR ALL HOURS WORKED
- ENGI0014-001 A: PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; WASHINGTON'S BIRTHDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY; PROVIDED THE EMPLOYEE WORKS ONE DAY THE PAYROLL WEEK IN WHICH THE HOLIDAY OCCURS
- ENGI0014-002 A: PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, COLUMBUS DAY, ELECTION DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ONE DAY IN THE PAYROLL WEEK IN WHICH THE HOLIDAY OCCURS
- ENGI0015-001 A: PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, COLUMBUS DAY, ELECTION DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ONE DAY IN THE PAYROLL WEEK IN WHICH THE HOLIDAY OCCURS
- ENGI0015-002 A: PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, COLUMBUS DAY, ELECTION DAY, THANKSGIVING DAY, AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS ONE DAY IN THE PAYROLL WEEK IN WHICH THE HOLIDAY OCCURS
- LABO0731-001 NOTE: PAID HOLIDAYS: LABOR DAY AND THANKSGIVING DAY
- LABO1010-001 A: PAID HOLIDAYS: MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, COLUMBUS DAY, ELECTION DAY AND THANKSGIVING DAY, PROVIDED THE EMPLOYEE HAS WORKED ONE (1) DAY IN THE CALENDAR WEEK IN WHICH THE SAID HOLIDAY OCCURS
- TEAM0282-001 NOTE: PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, ELECTION DAY, VETERANS' DAY (ARMISTICE DAY), THANKSGIVING DAY, DAY AFTER THANKSGIVING AND CHRISTMAS DAY. EMPLOYEES WORKING TWO (2) DAYS IN THE CALENDAR WEEK IN WHICH A HOLIDAY FALLS ARE TO BE PAID FOR SUCH HOLIDAY, PROVIDED THAT THEY SHAPE EACH REMAINING WORKDAY DURING SUCH CALENDAR WEEK
2 of 2: WD NY20260001, Mod 2
Make a WH-347 with these ratesScope as published: All dredging, except self propelled hopper dredging, on the Atlantic Coast and tributary waters emptying into the Atlantic Ocean
| Classification | Rate ID | Base | Fringe | Total / hour |
|---|---|---|---|---|
DREDGING: CLASS A1: DECK CAPTAIN; MECHANICAL DREDGE OPERATOR, LEVERMAN, LICENSED TUG OPERATOR OVER 1000 HP. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TU...DREDGING: CLASS A1: DECK CAPTAIN; MECHANICAL DREDGE OPERATOR, LEVERMAN, LICENSED TUG OPERATOR OVER 1000 HP. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | ENGI0025-001 10/01/2025 | $48.48 | $15.34 | $63.82 |
DREDGING: CLASS A2: CRANE OPERATOR (360 SWING) INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED M...DREDGING: CLASS A2: CRANE OPERATOR (360 SWING) INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | ENGI0025-001 10/01/2025 | $43.20 | $14.99 | $58.19 |
DREDGING: CLASS B1: DERRICK OPERATOR (180 SWING), SPIDER/SPILL BARGE OPERATOR, ENGINEER, ELECTRICIAN, CHIEF WELDER, CHIEF MATE, FILL PLACER, OPERATOR II, MAINTENANCE ENGINEER, LICENSED BOAT OPERATOR, ...DREDGING: CLASS B1: DERRICK OPERATOR (180 SWING), SPIDER/SPILL BARGE OPERATOR, ENGINEER, ELECTRICIAN, CHIEF WELDER, CHIEF MATE, FILL PLACER, OPERATOR II, MAINTENANCE ENGINEER, LICENSED BOAT OPERATOR, LICENSED CREW BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | ENGI0025-001 10/01/2025 | $41.93 | $14.90 | $56.83 |
DREDGING: CLASS B2: CERTIFIED WELDER. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF ...DREDGING: CLASS B2: CERTIFIED WELDER. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | ENGI0025-001 10/01/2025 | $39.46 | $14.73 | $54.19 |
DREDGING: CLASS C1: MATE, DRAG BARGE OPERATOR, ASSISTANT FILL PLACER, WELDER, STEWARD. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 ...DREDGING: CLASS C1: MATE, DRAG BARGE OPERATOR, ASSISTANT FILL PLACER, WELDER, STEWARD. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | ENGI0025-001 10/01/2025 | $38.38 | $14.66 | $53.04 |
DREDGING: CLASS C2: BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOW...DREDGING: CLASS C2: BOAT OPERATOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | ENGI0025-001 10/01/2025 | $37.15 | $14.57 | $51.72 |
DREDGING: CLASS D: OILER, DECKHAND, SHOREMAN, RODMAN, SCOWMAN, COOK, MESSMAN, PORTER/JANITOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVE...DREDGING: CLASS D: OILER, DECKHAND, SHOREMAN, RODMAN, SCOWMAN, COOK, MESSMAN, PORTER/JANITOR. INCENTIVE PAY: (ADD TO HOURLY RATE) OPERATOR (NCCCO LICENSE/CERTIFICATION) $1.80 LICENSED TUG OPERATOR OVER 1000 HP (ASSIGNED AS MASTER) (USCG LICENSED MASTER OF TOWING VESSELS (MOTV) $1.80; LICENSED BOAT OPERATOR (ASSIGNED AS LEAD BOAT CAPTAIN) USCG LICENSED BOAT OPERATOR $1.30; ENGINEER (QMED AND TANKERMAN ENDORSEMENT OR LICENSED ENGINEER (USCG) $1.80 OILER (QMED AND TANKERMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (TANKERMAN ENDORSEMENT ONLY) USCG $1.55; DECKHAND OR MATE (AB WITH LIFEBOATMAN ENDORSEMENT (USCG) $1.80; ALL CLASSIFICATIONS (LIFEBOATMAN ENDORSEMENT ONLY (USCG) $1.55; WELDER (ABS CERTIFICATION) $1.55 | ENGI0025-001 10/01/2025 | $30.86 | $14.15 | $45.01 |
Footnotes in NY20260001 (2)
- ENGI0025-001 A: PAID HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING, JR.'S BIRTHDAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY AND CHRISTMAS DAY
- ENGI0025-001 B: VACATION: EIGHT PERCENT (8%) OF THE STRAIGHT TIME RATE, MULTIPLIED BY THE TOTAL HOURS WORKED
Questions about these rates
What is the Davis-Bacon rate for electricians on heavy work in Kings County?
What is the Davis-Bacon rate for plumbers on heavy work in Kings County?
What is the Davis-Bacon rate for carpenters on heavy work in Kings County?
Which wage determination applies to my project?
What counts as heavy construction?
What if my worker's trade is not on the list?
Using these rates on a WH-347
Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.
Make this week's WH-347 with NY20260003
Other counties: all New York counties · WD lookup
Your first certified payroll is free.
Upload last week's payroll, get a checked WH-347 back today.
No card. Same full report, no watermark.