Davis-Bacon wage rates · New York

Nassau County residential construction wage rates

Federal prevailing wage rates for residential construction in Nassau County, New York, from the wage determination SAM.gov lists for this county. Rates are shown exactly as published.

Data from SAM.gov, fetched October 7, 20261 wage determination
Wage determination
NY20260012
Modification
2
Published
May 18, 2026
Classifications
59
Other types here
Building, Heavy, Highway

These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See New York prevailing wage for how the two fit together.

WD NY20260012, Mod 2

Make a WH-347 with these rates
Published May 18, 2026 59 classifications Covers 2 counties Types: Building, Heavy, Highway, Residential Source: SAM.gov

Scope as published: Building Construction Projects · Heavy Construction Projects · Highway Construction Projects

Davis-Bacon rates in NY20260012 Mod 2, published 05/18/2026. Total is base plus the hourly fringe printed in the WD; footnote benefits (paid holidays, vacation) are extra and listed below the table.
ClassificationRate IDBaseFringeTotal / hour
ASBESTOS WORKERS/INSULATOR (INCLUDES APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS.) ASBE0012-001
06/01/2025
$71.76 $36.81 $108.57
BOILERMAKER Footnote A below BOIL0005-001
01/01/2025
$68.88 $49.83 $118.71
BRICKLAYER BRNY0001-001
07/01/2024
$67.39 $35.90 $103.29
CARPENTER (SOFT FLOOR LAYERS) CARP2287-003
07/01/2025
$59.05 $48.08 $107.13
CARPENTERS: (DIVERS TENDERS) CARP1556-008
07/01/2024
$55.00 $55.84 $110.84
CARPENTERS: (DOCKBUILDERS) CARP1556-008
07/01/2024
$60.59 $55.84 $116.43
CARPENTERS: (HEAVY & HIGHWAY) CARP0290-001
07/01/2025
$53.56 $34.28 $87.84
CARPENTERS: (PILEDRIVERMAN) CARP1556-008
07/01/2024
$60.59 $55.84 $116.43
CARPENTERS: (RESIDENTIAL) CARP0290-001
07/01/2025
$34.14 $23.15 $57.29
CARPENTERS: (TIMBERMEN) CARP1556-011
07/01/2024
$55.59 $55.41 $111.00
CARPENTERS: DIVERS CARP1556-008
07/01/2024
$75.46 $55.84 $131.30
CARPENTERS: NASSAU COUNTY (REMAINDER OF COUNTY) AND SUFFOLK COUNTY (BUILDING) CARP0290-001
07/01/2025
$53.56 $34.28 $87.84
CEMENT MASON/CONCRETE FINISHER PLAS0780-001
07/01/2025
$59.87 $41.81 $101.68
ELECTRICIAN ELEC0025-001
04/26/2025
$64.55 $47.40 $111.95
ELECTRICIANS: (MAINTENANCE UNIT) ELEC0025-002
04/26/2025
$49.79 $32.27 $82.06
ELECTRICIANS: (TELEPHONE UNIT) ELEC0025-002
04/26/2025
$42.93 $32.43 $75.36
ELEVATOR MECHANIC (ELEVATOR CONSTRUCTOR) Footnote A, B below ELEV0001-002
03/17/2022
$75.14 $47.45 $122.59
ELEVATOR MECHANIC (MODERNIZATION AND REPAIR) Footnote A, B below ELEV0001-002
03/17/2022
$59.09 $45.56 $104.65
HAZARDOUS MATERIAL HANDLER ASBE0012-001
06/01/2025
$47.75 $13.70 $61.45
IRONWORKER (METALLIC LATHERS AND REINFORCING IRONWORKERS) IRON0046-003
07/01/2025
$57.00 $32.96 $89.96
IRONWORKER (STONE DERRICKMAN) IRON0197-001
07/01/2024
$60.40 $60.14 $120.54
IRONWORKER: ORNAMENTAL IRON0580-001
07/01/2025
$48.15 $67.62 $115.77
IRONWORKER: STRUCTURAL IRON0361-001
07/01/2025
$58.95 $92.02 $150.97
LABORERS (BUILDING) LABO0066-001
07/01/2025
$42.55 $34.79 $77.34
LABORERS: ASBESTOS (REMOVAL, ABATEMENT, ENCAPSULATION OR DECONTAMINATION OF ASBESTOS); LEAD; & HAZARDOUS WASTE LABORERS (HAZARDOUS WASTE, HAZARDOUS MATERIALS, BIOCHEMICAL AND MOLD REMEDIATION, HVAC, D...LABORERS: ASBESTOS (REMOVAL, ABATEMENT, ENCAPSULATION OR DECONTAMINATION OF ASBESTOS); LEAD; & HAZARDOUS WASTE LABORERS (HAZARDOUS WASTE, HAZARDOUS MATERIALS, BIOCHEMICAL AND MOLD REMEDIATION, HVAC, DUCT CLEANING, RE-SPRAY FIREPROOFING, ETC) (BUILDING CONSTRUCTION)
LABO0078-001
01/06/2025
$41.15 $20.90 $62.05
LABORERS: ASPHALT RAKERS; FORMSETTERS (HEAVY & HIGHWAY) A Footnote NOTE below LABO1298-001
06/01/2023
$51.43 $35.98 $87.41
LABORERS: ASPHALT SHOVELERS, ROLLER BOYS & TAMPERS (HEAVY & HIGHWAY) A Footnote NOTE below LABO1298-001
06/01/2023
$49.96 $35.98 $85.94
LABORERS: PLASTERERS TENDERS (BUILDING) LABO0066-001
07/01/2025
$42.55 $34.79 $77.34
LABORERS: REGULAR LABORERS (HEAVY & HIGHWAY) A Footnote NOTE below LABO1298-001
06/01/2023
$45.49 $35.98 $81.47
LINE CONSTRUCTION: GROUNDMAN (SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/ TRANSMISSION SYSTEMS MAINTENANCE (WHE...LINE CONSTRUCTION: GROUNDMAN (SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/ TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NOT PERFORMED BY RAILROAD EMPLOYEES) OVERHEAD AND UNDERGROUND TRANSMISSION/DISTRIBUTION LINE WORK. FIBER OPTIC, TELEPHONE CABLE AND EQUIPMENT;)
ELEC1049-002
03/30/2025
$42.34 $30.05 $72.39
LINE CONSTRUCTION: HEAVY EQUIPMENT OPERATOR (SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/ TRANSMISSION SYSTEMS M...LINE CONSTRUCTION: HEAVY EQUIPMENT OPERATOR (SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/ TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NOT PERFORMED BY RAILROAD EMPLOYEES) OVERHEAD AND UNDERGROUND TRANSMISSION/DISTRIBUTION LINE WORK. FIBER OPTIC, TELEPHONE CABLE AND EQUIPMENT;)
ELEC1049-002
03/30/2025
$56.46 $34.63 $91.09
LINE CONSTRUCTION: LINEMAN & CABLE SPLICER (SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/ TRANSMISSION SYSTEMS MA...LINE CONSTRUCTION: LINEMAN & CABLE SPLICER (SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/ TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NOT PERFORMED BY RAILROAD EMPLOYEES) OVERHEAD AND UNDERGROUND TRANSMISSION/DISTRIBUTION LINE WORK. FIBER OPTIC, TELEPHONE CABLE AND EQUIPMENT;)
ELEC1049-002
03/30/2025
$70.57 $39.19 $109.76
LINE CONSTRUCTION: MATERIAL MAN (SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/ TRANSMISSION SYSTEMS MAINTENANCE (...LINE CONSTRUCTION: MATERIAL MAN (SUBSTATION AND SWITCHING STRUCTURES PIPE TYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS; RAILROAD ELECTRICAL DISTRIBUTION/ TRANSMISSION SYSTEMS MAINTENANCE (WHEN WORK IS NOT PERFORMED BY RAILROAD EMPLOYEES) OVERHEAD AND UNDERGROUND TRANSMISSION/DISTRIBUTION LINE WORK. FIBER OPTIC, TELEPHONE CABLE AND EQUIPMENT;)
ELEC1049-002
03/30/2025
$61.40 $36.24 $97.64
MASON - STONE BRNY0001-001
07/01/2024
$69.91 $44.02 $113.93
MILLWRIGHT CARP0740-001
07/01/2025
$60.83 $58.03 $118.86
PAINTER (GLAZIERS) PAIN0009-002
05/01/2025
$49.20 $57.20 $106.40
PAINTER (PAINTERS, DRYWALL FINISHERS) PAIN0009-002
05/01/2025
$44.75 $44.11 $88.86
PAINTER (SPRAY, SCAFFOLD, SANDBLASTING) PAIN0009-002
05/01/2025
$47.75 $44.11 $91.86
PAINTERS: (DRYWALL TAPERS/POINTERS) PAIN1974-002
06/28/2025
$48.47 $35.91 $84.38
PAINTERS: (STUCTURAL STEEL AND BRIDGE) PAIN0806-010
10/01/2024
$56.25 $55.14 $111.39
PLASTERER PLAS0262-003
08/01/2025
$48.51 $32.78 $81.29
PLUMBER (BUILDING CONSTRUCTION:) PLUM0200-001
05/01/2025
$60.73 $45.75 $106.48
PLUMBER (RESIDENTIAL CONSTRUCTION:) PLUM0200-001
05/01/2025
$36.05 $19.63 $55.68
PLUMBER, SERVICE FITTERS PLUM0638-001
01/01/2026
$47.85 $23.96 $71.81
POWER EQUIPMENT OPERATORS: GROUP 1 (BUILDING CONSTRUCTION) ASPHALT SPREADER, BACKHOE CRAWLER CAPACITY OVER CATER- PILLER 225 AND LOMATSU 300, BOILER (THERMOPLASTIC), CHERRY PICKER, OVER 50 TONS, CMI O...POWER EQUIPMENT OPERATORS: GROUP 1 (BUILDING CONSTRUCTION) ASPHALT SPREADER, BACKHOE CRAWLER CAPACITY OVER CATER- PILLER 225 AND LOMATSU 300, BOILER (THERMOPLASTIC), CHERRY PICKER, OVER 50 TONS, CMI OR MAXIM SPREADER, CONCRETE PUMP (WITH OILER), CRANE (CRAWLER TRUCK), CRANE (ON BARGE), CRANE (STONE SETTING), CRANE (STRUCTURAL STEEL), CRANE (WITH CLAM SHELL), DERRICK, DRAGLINE, DREDGE, GRADALL, GRADER, HOIST (3 DRUM), LOADING MACHINE (BUCKET) CAP OF 10 YDS OR OVER MICRO-TRAP, WITH COMPRESSOR (NEGATIVE AIR MACHINE), MILLING MACHINE, LARGE PILE DRIVER, POWER WINCH, STONE SETTING/STRUCTURAL STEEL, POWER WINCH (TRUCK MOUNTED/STONE STEEL) POWERHOUSE, ROAD PAVER SCOOP, CARRY-ALL, SCRAPER IN TANDEM SHOVEL, SIDEBOOM TRACTOR, SIDEBOOM TRACTOR (USED IN TANK WORK), STONE SPREADER (SELF PROPELLED TANK WORK), ZAMBONI (ICE MACHINE) NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-001
06/01/2025
$80.43 $39.99 $120.42
POWER EQUIPMENT OPERATORS: GROUP 1 (HEAVY & HIGHWAY) ASPHALT SPREADER, BACKHOE CRAWLER (CAPACITY OVER CATERPILLER 225 AND KOMATSU 300), BOILER (THERMOPLASTIC), BORING MACHINE (POST HOLE), CGHERRY PICK...POWER EQUIPMENT OPERATORS: GROUP 1 (HEAVY & HIGHWAY) ASPHALT SPREADER, BACKHOE CRAWLER (CAPACITY OVER CATERPILLER 225 AND KOMATSU 300), BOILER (THERMOPLASTIC), BORING MACHINE (POST HOLE), CGHERRY PICKER (OVER 50 TON), CMI OR MAXIM SPREADER, CONCRETE PUMP, WITH OILER, CRANE (CRAWLER TRUCK), CRANE (ON BARGE), CRANE (STONE SETTING) CRANE (STRUCTURAL STEEL), CRANE (WITH CLAM SHELL), DERRICK, DRAGLINE, DREDGE, GRADALL, GRADER, HOIST (3 DRUMS), LOADING MACHINE (BUCKET) CAPACITY OF 10 YARDS OR OVER, MICRO-TRAP (WITH COMPRESSOR-NEGATIVE AIR MACHINE), MILLING MACHINE (LARGE), PILEDRIVER, POWER WINCH (STONE SETTING STRUCTURAL STEEL), POWER WINCH (TRUCK MOUNTED/STONE STEEL), POWER-HOUSE, ROAD PAVER, SCOOP, CARRY ALL (SCRAPER IN TANDEM), SHOVEL, SIDEBOOM TRACTOR, SIDEBOOM TRACTOR (USED IN TANK WORK), STONE SPREADER (SELF-PROPELLED), TANK WORK, TOWER CRANE NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 TRUCK AND CRAWLER CRANES LONG BOOM PREMIUMS: BOOM LENGTHS (INCLUDING JIB) 100-149 FT 1.00 BOOM LENGHTS (INCLUDING JIB) 150-249 FT 1.50 BOOM LENGHTS (INCLUDING JIB) 250-349 FT 2.00 BOOM LENGTHS (INCLUDING JIB) 350 FT 3.00 CRANES USING CLAMSHELL BUCKETS.25 FRONT END LOADER 10 YDS AND ABOVE.25 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-002
06/01/2025
$84.70 $40.15 $124.85
POWER EQUIPMENT OPERATORS: GROUP 2 (BUILDING CONSTRUCTION) BACKHOE, BOOM TRUCK, BULLDOZER, CHERYPICKER, CONVEYOR (MULTI), DINKY LOCOMOTIVE, FORKLIFT, HOIST, 2 DRUM, LOADING MACHINE, LOADING MACHINE (F...POWER EQUIPMENT OPERATORS: GROUP 2 (BUILDING CONSTRUCTION) BACKHOE, BOOM TRUCK, BULLDOZER, CHERYPICKER, CONVEYOR (MULTI), DINKY LOCOMOTIVE, FORKLIFT, HOIST, 2 DRUM, LOADING MACHINE, LOADING MACHINE (FRONT END) MECHANICAL COMPACTORS, (MACHINE DRAWN), MULCH MACHINE (MACHINE-FED), MECHANIC, POWER WINCH, OTHER THAN STONE/STRUCTURAL STEEL, POWER WINCH (TRUCK MOUNTED OTHER THAN STONE STEEL) PUMP (HYDRAULIC, WITH BORING MACHINE), ROLLER, (ASPHALT), SCOOP (CARRY-ALL SCRAPER), TOWER CRANE (MAINTENANCE MAN), TRENCHING MACHINE NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-001
06/01/2025
$76.44 $39.99 $116.43
POWER EQUIPMENT OPERATORS: GROUP 2 (HEAVY & HIGHWAY) BULLDOZER, BACKHOE, BOOM TRUCK, BORING MACHINE/AUGUR, CHERRYPICKER, CONVEYOR (MULTI), DINKY LOCOMOTIVE, FORKLIFT, HOIST (2 DRUM), LOADING MACHINE, ...POWER EQUIPMENT OPERATORS: GROUP 2 (HEAVY & HIGHWAY) BULLDOZER, BACKHOE, BOOM TRUCK, BORING MACHINE/AUGUR, CHERRYPICKER, CONVEYOR (MULTI), DINKY LOCOMOTIVE, FORKLIFT, HOIST (2 DRUM), LOADING MACHINE, LOADING MACHINE (FRONT END), MECHANICAL COMPACTOR (MACHINE DRAWN), MECHANIC, MULCH MACHINE (MACHINE- FED), POWER WINCH (OTHER THAN STONE/STRUCTURAL STEEL), POWER WINCH (TRUCK MOUNTED/OTHER THAN STONE STEEL), PUMP HYDRAULIC (WITH BORING MACHINE), ROLLER (ASPHALT), SCOOP (CARRY-ALL, SCRAPER), TOWER CRANE (MAINTENANCE MAN), TRENCHING MACHINE, VERMEER CUTTER, WORK BOAT NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 TRUCK AND CRAWLER CRANES LONG BOOM PREMIUMS: BOOM LENGTHS (INCLUDING JIB) 100-149 FT 1.00 BOOM LENGHTS (INCLUDING JIB) 150-249 FT 1.50 BOOM LENGHTS (INCLUDING JIB) 250-349 FT 2.00 BOOM LENGTHS (INCLUDING JIB) 350 FT 3.00 CRANES USING CLAMSHELL BUCKETS.25 FRONT END LOADER 10 YDS AND ABOVE.25 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-002
06/01/2025
$79.33 $40.15 $119.48
POWER EQUIPMENT OPERATORS: GROUP 3 (HEAVY & HIGHWAY) CURB MACHINE (ASPHALT OR CONCRETE), MAINTENANCE ENGINEER (SMALL EQUIPMENT), MAINTENANCE ENGINEER (WELL-POINT) MECHANIC (FIELDMAN), MICRO-TRAP (SELF...POWER EQUIPMENT OPERATORS: GROUP 3 (HEAVY & HIGHWAY) CURB MACHINE (ASPHALT OR CONCRETE), MAINTENANCE ENGINEER (SMALL EQUIPMENT), MAINTENANCE ENGINEER (WELL-POINT) MECHANIC (FIELDMAN), MICRO-TRAP (SELF CONTAINED, NEGATIVE AIR MACHINE), MILLING MACHINE (SMALL), PULVI-MIXER, PUMP (4 INCHES OR OVER), PUMP HYDRAULIC, PUMP JET, PUMP SUBMERSIBLE, PUMP (WELL POINT), ROLLER DIRT, VAC-ALL, WELDING AND BURNING, COMPRESSOR (STRUCTURAL STEEL), COMPRESSOR (2 OR MORE BATTERY), CONCRETE FINISHING MACHINE, CONCRETE SPREADER, CONVEYOR, CURING MACHINE, FIREMAN, HOIST (ONE DRUM), RIDGE CUTTER, STRIPING MACHINE, WELDING MACHINE (PILE WORK), WELDING MACHINE (STRUCTURAL STEEL). NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 TRUCK AND CRAWLER CRANES LONG BOOM PREMIUMS: BOOM LENGTHS (INCLUDING JIB) 100-149 FT 1.00 BOOM LENGHTS (INCLUDING JIB) 150-249 FT 1.50 BOOM LENGHTS (INCLUDING JIB) 250-349 FT 2.00 BOOM LENGTHS (INCLUDING JIB) 350 FT 3.00 CRANES USING CLAMSHELL BUCKETS.25 FRONT END LOADER 10 YDS AND ABOVE.25 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-002
06/01/2025
$76.61 $40.15 $116.76
POWER EQUIPMENT OPERATORS: GROUP 3(BUILDING CONSTRUCTION) COMRPESSOR (STRUCTURAL STEEL), COMPRESSOR (2 OR MORE IN BATTERY), CONCRETE FINISHING MCHINE, CONCRETE SPREADER, CONVEYOR, CURB MACHINE (ASPHAL...POWER EQUIPMENT OPERATORS: GROUP 3(BUILDING CONSTRUCTION) COMRPESSOR (STRUCTURAL STEEL), COMPRESSOR (2 OR MORE IN BATTERY), CONCRETE FINISHING MCHINE, CONCRETE SPREADER, CONVEYOR, CURB MACHINE (ASPHALT OR CONCRETE), CURING MACHINE, FIREMAN, HOIST (1 DRUM), MICRO-TRAP, (SELF CONTAINED, NEGATIVE AIR MACHINE), PUMP (4 INCHES OR OVER), PUMP (HYDRAULIC), PUMP (JET), PUMP (SUMBERSIBLE), PUMP (WELL POINT), PULVI-MIXER, RIDGE CUTTER, ROLLER (DIRT), STRIPING MACHINE, VAC-ALL, WELDING AND BURNING, WELDING MACHINE (PILE WORK), WELDING MACHINE (STRUCTURAL STEEL) NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-001
06/01/2025
$73.78 $39.99 $113.77
POWER EQUIPMENT OPERATORS: GROUP 4 (BUILDING CONSTRUCTION) COMPRESSOR, COMPRESSOR (ON CRANE), COMPRESSOR (PILE WORK), COMPRESSOR (STONE SETTING), CONCRETE BREAKER, CONCRETE SAW OR CUTTER, FORKLIFT (WA...POWER EQUIPMENT OPERATORS: GROUP 4 (BUILDING CONSTRUCTION) COMPRESSOR, COMPRESSOR (ON CRANE), COMPRESSOR (PILE WORK), COMPRESSOR (STONE SETTING), CONCRETE BREAKER, CONCRETE SAW OR CUTTER, FORKLIFT (WALK BEHIND, POWER OPERATED), GENERATOR-PILE WORK, GENERATOR, HYDRA HAMMER, MECHANICAL COMPACTORS (HAND OPERATED), OILER (TRUCK CRANE), PIN PULLER, PORTABLE HEATERS, POWERBROOM, POWER BUGGIES, PUMP (DOUBLE ACTION DIAPHGRGM), PUMP (GYPSUM), TRENCH MACHINE (HAND), WELDING MACHINE NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-001
06/01/2025
$56.54 $39.99 $96.53
POWER EQUIPMENT OPERATORS: GROUP 4 (HEAVY & HIGHWAY) COMPRESSOR, COMPRESSOR ON CRANE, COMPRESSOR (PILE WORK), COMPRESSOR (STONE SETTING), CONCRETE BREAKER, CONCRETE SAW OR CUTTER, FORK LIFT (WALK BEHI...POWER EQUIPMENT OPERATORS: GROUP 4 (HEAVY & HIGHWAY) COMPRESSOR, COMPRESSOR ON CRANE, COMPRESSOR (PILE WORK), COMPRESSOR (STONE SETTING), CONCRETE BREAKER, CONCRETE SAW OR CUTTER, FORK LIFT (WALK BEHIND, POWER OPERATED), GENERATOR- PILE WORK, GENERATOR, HYDRA HAMMER, MECHANICAL COMPOACTORS (HAND OPERATED), OILER (TRUCK CRANE), PIN PULLER, PORTABLE HEATERS, POWERBROOM, POWER BUGGIES, POWER GRINDERS, PUMP (DOUBLE ACTION DIAPHRAGM), PUMP GYPSUM, PUMP (SINGLE ACTION 1 TO 3 INCHES), TRENCH MACHINE HAND, WELDING MACHINE NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 TRUCK AND CRAWLER CRANES LONG BOOM PREMIUMS: BOOM LENGTHS (INCLUDING JIB) 100-149 FT 1.00 BOOM LENGHTS (INCLUDING JIB) 150-249 FT 1.50 BOOM LENGHTS (INCLUDING JIB) 250-349 FT 2.00 BOOM LENGTHS (INCLUDING JIB) 350 FT 3.00 CRANES USING CLAMSHELL BUCKETS.25 FRONT END LOADER 10 YDS AND ABOVE.25 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-002
06/01/2025
$58.93 $40.15 $99.08
POWER EQUIPMENT OPERATORS: GROUP 5 (BUILDING CONSTRUCTION) BATCHING PLANT (ON SITE OF JOB), GENERATOR (SMALL), MIXER (WITH SKIP), MIXER (2 SMALL WITH OR WITHOUT SKIP), MIXER (2 BAG OR OVER, WITH OR WI...POWER EQUIPMENT OPERATORS: GROUP 5 (BUILDING CONSTRUCTION) BATCHING PLANT (ON SITE OF JOB), GENERATOR (SMALL), MIXER (WITH SKIP), MIXER (2 SMALL WITH OR WITHOUT SKIP), MIXER (2 BAG OR OVER, WITH OR WITHOUT SKIP), MULCH MACHINE, OILER, PUMP (CENTRIFUGAL, UP TO 3 INCHES), ROOT CUTTER, STUMP CHIPPER, TOWER CRANE (OILER), TRACTOR (CATERPILLAR OR WHEEL VIBRATOR) NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-001
06/01/2025
$54.21 $39.99 $94.20
POWER EQUIPMENT OPERATORS: GROUP 5 (HEAVY & HIGHWAY) BATCHING PLANT (ON SITE OF JOB), GENERATOR (SMALL), GRINDER, MIXER (WITH SKIP), MIXER (2 SMALL WITH OR WITHOUT SKIP), MIXER (2 BAG OR OVER, WITH OR...POWER EQUIPMENT OPERATORS: GROUP 5 (HEAVY & HIGHWAY) BATCHING PLANT (ON SITE OF JOB), GENERATOR (SMALL), GRINDER, MIXER (WITH SKIP), MIXER (2 SMALL WITH OR WITHOUT SKIP), MIXER (2 BAG OR OVER, WITH OR WITHOUT SKIP), MULCH MACHINE, OILER, PUMP (CENTRIFUGAL, UP TO 3 INCHES), ROOT CUTTER, STUMP CHIPPER, TOWER CRANE (OILER), TRACK TAMPER (2 ENGINEERS, EACH), TRACTOR (CATERPILLAR OR WHEEL), VIBRATOR, WORK BOAT (DECKHAND), NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 TRUCK AND CRAWLER CRANES LONG BOOM PREMIUMS: BOOM LENGTHS (INCLUDING JIB) 100-149 FT 1.00 BOOM LENGHTS (INCLUDING JIB) 150-249 FT 1.50 BOOM LENGHTS (INCLUDING JIB) 250-349 FT 2.00 BOOM LENGTHS (INCLUDING JIB) 350 FT 3.00 CRANES USING CLAMSHELL BUCKETS.25 FRONT END LOADER 10 YDS AND ABOVE.25 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-002
06/01/2025
$56.55 $40.15 $96.70
POWER EQUIPMENT OPERATORS: GROUP 6 (HEAVY & HIGHWAY) WELL DRILLERS NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 TRUCK AND CRAWLER CRANES LONG BOOM PREMIUMS: BOOM LENGTHS...POWER EQUIPMENT OPERATORS: GROUP 6 (HEAVY & HIGHWAY) WELL DRILLERS NOTES: HAZMAT PREMIUMS: LEVEL A 3.50 LEVEL B 2.50 LEVEL C 1.50 LEVEL D 1.00 TRUCK AND CRAWLER CRANES LONG BOOM PREMIUMS: BOOM LENGTHS (INCLUDING JIB) 100-149 FT 1.00 BOOM LENGHTS (INCLUDING JIB) 150-249 FT 1.50 BOOM LENGHTS (INCLUDING JIB) 250-349 FT 2.00 BOOM LENGTHS (INCLUDING JIB) 350 FT 3.00 CRANES USING CLAMSHELL BUCKETS.25 FRONT END LOADER 10 YDS AND ABOVE.25 OILER ON TRUCK CRANES WITH BOOM LENGTH OF 100 FT. OR MORE.25
Footnote A below
ENGI0138-002
06/01/2025
$44.37 $12.95 $57.32
ROOFER ROOF0154-001
05/01/2025
$51.25 $47.36 $98.61
SHEET METAL WORKER (BUILDING CONSTRUCTION) SHEE0028-002
11/02/2023
$53.60 $60.74 $114.34
SHEET METAL WORKER (RESIDENTIAL CONSTRUCTION) SHEE0028-002
11/02/2023
$35.79 $25.37 $61.16
TRUCK DRIVER Footnote A below TEAM0282-002
07/01/2025
$45.65 $56.20 $101.85
Footnotes in NY20260012 (7)
  • BOIL0005-001 A: PAID HOLIDAYS: NEW YEAR'S DAY, THANKSGIVING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY AND GOOD FRIDAY, FRIDAY AFTER THANKSGIVING, CHRISTMAS EVE DAY AND NEW YEAR'S EVE
  • ELEV0001-002 A: PAID HOLIDAYS: NEW YEAR'S DAY, GOOD FRIDAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY.
  • ELEV0001-002 B: PAID VACATION: AN EMPLOYEE WHO HAS WORKED LESS THAN 5 YEARS SHALL RECIEVE VACATION PAY CREDIT ON THE BASIS OF 4% OF HIS HOURLY RATE FOR ALL HOURS WORKED; AN EMPLOYEE WHO HAS WORKED 5 TO 15 YEARS SHALL RECEIVE VACATION PAY CREDIT ON THE BASIS OF 6% OF HIS HOURLY RATE FOR ALL HOURS WORKED; AN EMPLOYEE WHO HAS WORKED 15 OR MORE YEARS SHALL RECEIVE VACATION PAY CREDIT ON THE BASIS OF 8% OF HIS HOURLY RATE FOR ALL HOURS WORKED
  • ENGI0138-001 A: PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY OR PRESIDENT'S DAY (IN LIEU OF LINCOLN'S OR WASHINGTON'S BIRTHDAY), GOOD FRIDAY, MEMORIAL DAY, INDPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, CHRISTMAS DAY OR DAYS CELEBRATED AS SUCH. ANY HOLIDAY THAT FALLS ON A SATURDAY WILL BE CELEBRATED ON FRIDAY
  • ENGI0138-002 A: PAID HOLIDAYS: NEW YEARS DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY OR PRESIDENTS DAY (IN LIEU OF LINCOLN'S OR WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, CHRISTMAS DAY OR DAYS CELEBRATED AS SUCH. ANY HOLIDAY THAT FALLS ON SATURDAY WILL BE CELEBRATED ON FRIDAY
  • LABO1298-001 NOTE: LABORERS WORKING IN A HAZARDOUS MATERIAL HOT ZONE SHALL RECEIVE AN ADDITIONAL 20% PREMIUM. WHERE THE CONTRACT PROVIDES FOR NIGHT WORK OUTSIDE THE REGULAR HOURS OF WORK, THE EMPLOYEES SHALL BE PAID AT STRAIGHT TIME PLUS A 30% NIGHT WORK PREMIUM FOR THE 8 HOURS WORKED DURING THE NIGHT. FIREWATCH WORK PERFORMED AFTER REGULAR HOURS SHALL BE PAID AN ADDITIONAL 10% PREMIUM. SECOND AND THIRD SHIFT WORK WILL BE PAID AT A 30% PREMIUM. CONTRACTOR REQUESTING LABORERS CERTIFIED FOR HAZARDOUS MATERIAL WORK AND/OR EMPLOYED ON HAZARDOUS MATERIAL SHALL BE REQUIRED TO PAY AN ADDITIONAL 10% PREMIUM
  • TEAM0282-002 A: PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, ELECTION DAY, VETERANS' DAY (ARMISTICE DAY), THANKSGIVING DAY, DAY AFTER THANKSGIVING AND CHRISTMAS DAY. EMPLOYEES WORKING TWO (2) DAYS IN THE CALENDAR WEEK IN WHICH A HOLIDAY FALLS ARE TO BE PAID FOR SUCH HOLIDAY, PROVIDED THAT THEY SHAPE EACH REMAINING WORKDAY DURING SUCH CALENDAR WEEK

Questions about these rates

What is the Davis-Bacon rate for electricians on residential work in Nassau County?
On WD NY20260012 Mod 2, published May 18, 2026, the row "ELECTRICIAN" is $64.55 base plus $47.40 fringe, $111.95 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for plumbers on residential work in Nassau County?
On WD NY20260012 Mod 2, published May 18, 2026, the row "PLUMBER (RESIDENTIAL CONSTRUCTION:)" is $36.05 base plus $19.63 fringe, $55.68 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for carpenters on residential work in Nassau County?
On WD NY20260012 Mod 2, published May 18, 2026, the row "CARPENTERS: (RESIDENTIAL)" is $34.14 base plus $23.15 fringe, $57.29 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
Which wage determination applies to my project?
The one in your contract. A WD is generally locked in when the contract is awarded (for sealed bids, a modification published at least 10 days before bid opening applies), and later modifications do not change it except in cases such as added out-of-scope work or option extensions. See 29 CFR 1.6(c).
What counts as residential construction?
Single family houses and apartment buildings of no more than 4 stories. The contracting agency picks the construction type; it is written into your contract with the WD. Source: DOL All Agency Memorandum 130.
What if my worker's trade is not on the list?
Work that needs a classification the WD does not list is added after award through a conformance request, which goes through the contracting agency to the Department of Labor (29 CFR 5.5(a)(1)(iii)). Do not use a different classification because its rate looks close.

Using these rates on a WH-347

Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.

Make this week's WH-347 with NY20260012

Other counties: all New York counties · WD lookup

Your first certified payroll is free.

Upload last week's payroll, get a checked WH-347 back today.