Davis-Bacon wage rates · New York

Seneca County highway construction wage rates

Federal prevailing wage rates for highway construction in Seneca County, New York, from the wage determination SAM.gov lists for this county. Rates are shown exactly as published.

Data from SAM.gov, fetched October 7, 20261 wage determination
Wage determination
NY20260040
Modification
2
Published
May 18, 2026
Classifications
48
Other types here
Building, Residential, Heavy

These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See New York prevailing wage for how the two fit together.

WD NY20260040, Mod 2

Make a WH-347 with these rates
Published May 18, 2026 48 classifications Covers 1 county Types: Highway Source: SAM.gov
Davis-Bacon rates in NY20260040 Mod 2, published 05/18/2026. Total is base plus the hourly fringe printed in the WD; footnote benefits (paid holidays, vacation) are extra and listed below the table.
ClassificationRate IDBaseFringeTotal / hour
CARPENTER Footnote A below CARP0277-019
07/01/2025
$39.52 $27.16 $66.68
ELECTRICIAN (REMAINDER OF COUNTY) ELEC0840-006
06/01/2025
$45.00 $31.12 $76.12
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OP...ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES: LINEMAN AND TECHNICIAN
Footnote A below
ELEC1249-004
05/05/2025
$61.56 $36.21 $97.77
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER Footnote A below ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUD...ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT)
Footnote A below
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY,...ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
ELEC1249-008
01/01/2025
$40.81 $6.99 $47.80
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THA...ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
ELEC1249-008
01/01/2025
$20.53 $6.39 $26.92
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORA...ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
ELEC1249-008
01/01/2025
$38.73 $6.93 $45.66
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN Footnote A below ELEC1249-003
05/05/2025
$31.72 $29.87 $61.59
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS...ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER)
Footnote A below
ELEC1249-003
05/05/2025
$42.29 $30.66 $72.95
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS...ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT)
Footnote A below
ELEC1249-003
05/05/2025
$47.57 $31.03 $78.60
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS...ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN
Footnote A below
ELEC1249-003
05/05/2025
$52.86 $35.60 $88.46
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC Footnote A below ELEC1249-003
05/05/2025
$42.29 $30.66 $72.95
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) ELEC1249-004
05/05/2025
$63.14 $33.82 $96.96
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable inst...ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)
ELEC1249-004
05/05/2025
$64.59 $42.92 $107.51
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wir...ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$35.34 $30.12 $65.46
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) ELEC1249-004
05/05/2025
$35.34 $30.12 $65.46
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installati...ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)
ELEC1249-004
05/05/2025
$35.34 $30.12 $65.46
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$55.40 $31.78 $87.18
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) ELEC1249-004
05/05/2025
$55.40 $31.78 $87.18
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission c...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab
ELEC1249-004
05/05/2025
$55.40 $31.78 $87.18
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber o...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and c...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work includ...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) ELEC1249-004
05/05/2025
$61.56 $36.21 $97.77
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit...ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins
ELEC1249-004
05/05/2025
$61.56 $36.21 $97.77
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wi...ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:)
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installat...ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)
ELEC1249-004
05/05/2025
$49.25 $31.15 $80.40
IRONWORKER (STRUCTURAL, ORNAMENTAL, REINFORCING, PRE-CAST CONCRETE ERECTOR, MACHINERY MOVER & RIGGER, FENCE ERECTOR, STONE DERRICKMAN, WELDER, SHEETER, SHEETER BUCKER-UP) IRON0060-009
07/01/2025
$37.16 $30.68 $67.84
LABORERS: GROUP 1 (HEAVY AND HIGHWAY:) FLAGGERS Footnote A below LABO0435-007
07/01/2024
$32.96 $25.30 $58.26
LABORERS: GROUP 2 (HEAVY AND HIGHWAY:) LABORERS Footnote A below LABO0435-007
07/01/2024
$33.66 $25.30 $58.96
LABORERS: GROUP 3 (HEAVY AND HIGHWAY:) RAKERS, DRILLERS, PIPELAYERS AND TORCH OPERATORS Footnote A below LABO0435-007
07/01/2024
$33.86 $25.30 $59.16
LABORERS: GROUP 4 (HEAVY AND HIGHWAY:) BLASTERS Footnote A below LABO0435-007
07/01/2024
$34.69 $25.30 $59.99
LABORERS: GROUP 5 (HEAVY AND HIGHWAY:) HAZARDOUS WASTE REMOVAL Footnote A below LABO0435-007
07/01/2024
$35.44 $25.30 $60.74
PAINTERS: (BRIDGES) PAIN0004-020
05/01/2023
$42.06 $30.59 $72.65
PLUMBER AND STEAMFITTER (FAYETTE, JUNIUS, ROMULUS, SENECA FALLS, TYRE, VARICK AND WATERLOO TOWNSHIPS) PLUM0013-005
05/06/2025
$42.68 $27.88 $70.56
PLUMBER, PIPEFITTER, STEAMFITTER: INCLUDING HVAC WORK (REMAINDER OF COUNTY) PLUM0267-008
05/01/2019
$35.51 $24.57 $60.08
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED), BACKHO...POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED), BACKHOE EXCAVATOR FULL SWING (CAT 212 OR SIMILAR TYPE), BACK FILLING MACHINE, BELT PLACER (CMI TYPE), BLACKTOP PLANT (AUTOMATED), BOOM TRUCK, CABLEWAY, CAISSON AUGER, CENTRAL MIX CONCRETE PLANT (AUTOMATED), CONCRETE CURB MACHINE, SELF PROPELLED, SLIPFORM, CONCRETE PUMP, CRANE, CHERRY PICKER, DERRICKS (STEEL ERECTION), DRAGLINE, OVERHEAD CRANE (GANTRY OR STRADDLE TYPE), PILE DRIVER, TRUCK CRANE, DIRECTIONAL DRILLING MACHINE, DREDGE, DUAL DRUM PAVER, EXCAVATOR (ALL PURPOSE HYDRAULICALLY OPERATED) (GRADALL OR SIMILAR), FRONT END LOADER ( 4 CU. YD. AND OVER), HEAD TOWER (SAUERMAN OR EQUAL), HOIST (TWO OR THREE DRUM), HOLLAND LOADER, MAINTENANCE ENGINEER, MINE HOIST, MUCKING MACHINE OR MOLE PAVEMENT BREAKER(SP) WERTGEN; PB-4 AND SIMILAR TYPE, POWER GRADER, PROFILER (OVER 105 H.P.) QUAD 9, QUARRY MASTER (OR EQUIVALENT), SCRAPER, FIREMAN, FORK LIFT, FORM TAMPER, GROUT PUMP, GUNITE MACHINE, HAMMERS (HYDRAULIC SELF-PROPELLED), HYDRA-SPIKER, RIDE-ON, HYDRAULIC PUMP (JACKING SYSTEM), HYDRO-BLASTER (WATER), MULCHING MACHINE, OILER, PARAPET CONCRETE OR PAVEMENT, SHOVEL, SIDE BOOM, SLIP FORM PAVER, TRACTOR DRAWN, BELTTYPE LOADER, TRUCK OR TRAILER MOUNTED LOG, CHIPPER (SELF FEEDER), TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVEL
Footnote A below
ENGI0158-020
07/01/2025
$55.85 $33.40 $89.25
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DR...POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED), BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT (NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS, CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED, CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR MOUNTED, FRONT END LOADER (UNDER 4 CU. YD.), GREASEMAN/LUBRICATION ENGINEER, HIPRESSURE BOILER (15 LBS. AND OVER), HOIST (ONE DRUM), HYDRO-AXE, KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS, L.C.M. WORK BOAT OPERATOR, LOCOMOTIVE MIXER (FOR STABILIZED BASE SELFPROPELLED), MONORAIL MACHINE, PLANT ENGINEER, PROFILER (105 H.P. AND UNDER), GRINDER, POST HOLE DIGGER AND POST DRIVER, POWER BROOM (TOWED), POWER HEATERMAN, POWER SWEEPER, REVINIUS WIDENER, ROLLER (GRADE AND FILL), SCARIFIER, RIDE-ON, SHELL WINDER, SKID STEER LOADER (BOBCAT OR SIMILAR), SPAN-SAW, RIDE-ON, STEAM CLEANER, PUG MILL, PUMP CRETE READY MIX CONCRETE PLANT REFRIGERATION EQUIPMENT (FOR SOIL STABILIZATION)ROAD WIDENER, ROLLER (ALL ABOVE SUBGRADE), SEA MULE, SELF-CONTAINED RIDE-ON ROCK DRILL, EXCLUDING AIR-TRACK TYPE DRILL, SKIDDER, TRACTOR WITH DOZER AND/OR PUSHER, TRENCHER. TUGGER HOIST, VERMEER SAW (RIDE ON, ANY SIZE OR TYPE), WINCH, WINCH CAT
Footnote A below
ENGI0158-020
07/01/2025
$54.97 $33.40 $88.37
POWER EQUIPMENT OPERATORS: GROUP 3 ENGI0158-020
07/01/2025
$51.69 $33.40 $85.09
POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES Footnote A below ENGI0158-020
07/01/2025
$65.51 $33.40 $98.91
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER Footnote A below ENGI0158-020
07/01/2025
$60.35 $33.40 $93.75
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW Footnote A below ENGI0158-020
07/01/2025
$58.85 $33.40 $92.25
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC Footnote A below ENGI0158-020
07/01/2025
$57.20 $33.40 $90.60
TRUCK DRIVERS: GROUP 1 PICK-UPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS (STRAIGHT JOBS); SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN, TANDEMS; BATCH TRUCK; MECHANICS; SEMI-T...TRUCK DRIVERS: GROUP 1 PICK-UPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS (STRAIGHT JOBS); SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN, TANDEMS; BATCH TRUCK; MECHANICS; SEMI-TRAILERS; LOW-BOY TRUCKS; ASPHALT DISTRIBUTOR TRUCKS; AGITATOR; MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES; TRUCK MECHANIC, FUEL TRUCK
Footnote A below
TEAM0317-001
06/01/2025
$35.48 $31.58 $67.06
TRUCK DRIVERS: GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT- EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRAFFLE (ROSS) CARRIER; SELF-CONTAINED CONCRETE UNIT, OFF-HIGHWAY TANDE...TRUCK DRIVERS: GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT- EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRAFFLE (ROSS) CARRIER; SELF-CONTAINED CONCRETE UNIT, OFF-HIGHWAY TANDEM BACK DUMP; TWIN ENGINE EQUIPMENT; DOUBLE HITCHED EQUIPMENT SHERE NOT SELF LOADED
Footnote A below
TEAM0317-001
06/01/2025
$35.83 $31.58 $67.41
Footnotes in NY20260040 (6)
  • CARP0277-019 A: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING AND CHRISTMAS
  • ELEC1249-003 A: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY
  • ELEC1249-004 A: PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY
  • ENGI0158-020 A: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
  • LABO0435-007 A: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
  • TEAM0317-001 A: PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAOBR DAY; THANKSGIVING DAY; CHRISTMAS DAY

Questions about these rates

What is the Davis-Bacon rate for electricians on highway work in Seneca County?
On WD NY20260040 Mod 2, published May 18, 2026, the row "ELECTRICIAN (REMAINDER OF COUNTY)" is $45.00 base plus $31.12 fringe, $76.12 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for plumbers on highway work in Seneca County?
On WD NY20260040 Mod 2, published May 18, 2026, the row "PLUMBER, PIPEFITTER, STEAMFITTER: INCLUDING HVAC WORK (REMAINDER OF COUNTY)" is $35.51 base plus $24.57 fringe, $60.08 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for carpenters on highway work in Seneca County?
On WD NY20260040 Mod 2, published May 18, 2026, the row "CARPENTER" is $39.52 base plus $27.16 fringe, $66.68 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
Which wage determination applies to my project?
The one in your contract. A WD is generally locked in when the contract is awarded (for sealed bids, a modification published at least 10 days before bid opening applies), and later modifications do not change it except in cases such as added out-of-scope work or option extensions. See 29 CFR 1.6(c).
What counts as highway construction?
Roads, streets, highways, runways, bridges, parking areas and related work. The contracting agency picks the construction type; it is written into your contract with the WD. Source: DOL All Agency Memorandum 130.
What if my worker's trade is not on the list?
Work that needs a classification the WD does not list is added after award through a conformance request, which goes through the contracting agency to the Department of Labor (29 CFR 5.5(a)(1)(iii)). Do not use a different classification because its rate looks close.

Using these rates on a WH-347

Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.

Make this week's WH-347 with NY20260040

Other counties: all New York counties · WD lookup