Davis-Bacon wage rates · New York
Tompkins County highway construction wage rates
Federal prevailing wage rates for highway construction in Tompkins County, New York, from the wage determination SAM.gov lists for this county. Rates are shown exactly as published.
- Wage determination
- NY20260024
- Modification
- 2
- Published
- May 18, 2026
- Classifications
- 55
- Other types here
- Building, Residential, Heavy
These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See New York prevailing wage for how the two fit together.
WD NY20260024, Mod 2
Make a WH-347 with these rates| Classification | Rate ID | Base | Fringe | Total / hour |
|---|---|---|---|---|
| BRICKLAYERS, CEMENT MASONS, STONE MASONS, POINTERS, CAULKERS AND CLEANERS: BUILDING CONSTRUCTION (ITHACA CHAPTER) | BRNY0003-006 07/01/2025 | $33.68 | $29.89 | $63.57 |
| CARPENTER | CARP0277-021 07/01/2025 | $39.52 | $27.16 | $66.68 |
| CEMENT MASONS: HEAVY/HIGHWAY CONSTRUCTION (ITHACA CHAPTER) | BRNY0003-006 07/01/2025 | $38.63 | $25.05 | $63.68 |
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OP...ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES: LINEMAN AND TECHNICIAN | ELEC1249-004 05/05/2025 | $61.56 | $36.21 | $97.77 |
| ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER Footnote A below | ELEC1249-004 05/05/2025 | $49.25 | $31.15 | $80.40 |
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUD...ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) | ELEC1249-004 05/05/2025 | $49.25 | $31.15 | $80.40 |
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY,...ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | ELEC1249-008 01/01/2025 | $40.81 | $6.99 | $47.80 |
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THA...ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | ELEC1249-008 01/01/2025 | $20.53 | $6.39 | $26.92 |
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORA...ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | ELEC1249-008 01/01/2025 | $38.73 | $6.93 | $45.66 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN Footnote A below | ELEC1249-003 05/05/2025 | $31.72 | $29.87 | $61.59 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS...ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) | ELEC1249-003 05/05/2025 | $42.29 | $30.66 | $72.95 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS...ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) | ELEC1249-003 05/05/2025 | $47.57 | $31.03 | $78.60 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS...ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN | ELEC1249-003 05/05/2025 | $52.86 | $35.60 | $88.46 |
| ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC Footnote A below | ELEC1249-003 05/05/2025 | $42.29 | $30.66 | $72.95 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) | ELEC1249-004 05/05/2025 | $63.14 | $33.82 | $96.96 |
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable inst...ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | ELEC1249-004 05/05/2025 | $64.59 | $42.92 | $107.51 |
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wir...ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:) | ELEC1249-004 05/05/2025 | $35.34 | $30.12 | $65.46 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) | ELEC1249-004 05/05/2025 | $35.34 | $30.12 | $65.46 |
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installati...ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | ELEC1249-004 05/05/2025 | $35.34 | $30.12 | $65.46 |
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:) | ELEC1249-004 05/05/2025 | $55.40 | $31.78 | $87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | ELEC1249-004 05/05/2025 | $55.40 | $31.78 | $87.18 |
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission c...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | ELEC1249-004 05/05/2025 | $55.40 | $31.78 | $87.18 |
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber o...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:) | ELEC1249-004 05/05/2025 | $49.25 | $31.15 | $80.40 |
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and c...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | ELEC1249-004 05/05/2025 | $49.25 | $31.15 | $80.40 |
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work includ...ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:) | ELEC1249-004 05/05/2025 | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | ELEC1249-004 05/05/2025 | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) | ELEC1249-004 05/05/2025 | $61.56 | $36.21 | $97.77 |
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit...ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | ELEC1249-004 05/05/2025 | $61.56 | $36.21 | $97.77 |
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wi...ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities:) | ELEC1249-004 05/05/2025 | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) | ELEC1249-004 05/05/2025 | $49.25 | $31.15 | $80.40 |
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installat...ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | ELEC1249-004 05/05/2025 | $49.25 | $31.15 | $80.40 |
| ELECTRICIANS: CABLE SPLICING (GROTON TOWNSHIP ONLY) | ELEC0043-002 06/01/2025 | $55.55 | $35.03 | $90.58 |
| ELECTRICIANS: ELECTRICIANS (GROTON TOWNSHIP ONLY) | ELEC0043-002 06/01/2025 | $50.50 | $35.03 | $85.53 |
| IRONWORKER (STRUCTURAL, ORNAMENTAL, REINFORCING, PRE-CAST CONCRETE ERECTOR, MACHINERY MOVER & RIGGER, FENCE ERECTOR, STONE DERRICK-MAN, WELDER, SHEETER, SHEETER BUCKER-UP) | IRON0060-004 07/01/2025 | $37.16 | $30.68 | $67.84 |
LABORER (HEAVY & HIGHWAY): GROUP 2 BULL FLOAT; CHAIN SAW; CONCRETE AGGREGATE BIN; CONCRETE BOOTMAN; GIN BUGGY; HAND OR MACHINE VIBRATOR; JACKHAMMER; MASON TENDER; MORTAR MIXER; PAVEMENT BREAKER; HANDL...LABORER (HEAVY & HIGHWAY): GROUP 2 BULL FLOAT; CHAIN SAW; CONCRETE AGGREGATE BIN; CONCRETE BOOTMAN; GIN BUGGY; HAND OR MACHINE VIBRATOR; JACKHAMMER; MASON TENDER; MORTAR MIXER; PAVEMENT BREAKER; HANDLERS OF ALL STEEL MESH; SMALL GENERATORS FOR LABORERS' TOOLS; INSTALLATION OF BRIDGE DRAINAGE PIPE; PIPELAYERS; VIBRATOR TYPE ROLLERS; TAMPERS; DRILL DOCTOR; TAIL OR SCREW OPERATOR ON ASPHALT PAVER; WATER PUMP OPERATOR (1-1/2" AND SINGLE DIAPHRAM); NOZZLE (ASPHALT, GUNNITE, SEEDING AND SANDBLASTING); LABORERS ON CHAIN LINK FENCE ERECTION; ROCK SPLITTER AND POWER UNIT; PUSHER TYPE CONCRETE SAW AND ALL OTHER GAS, ELECTRIC, OIL AND AIR TOOL OPERATORS; WRECKING LABORERS | LABO0785-018 07/01/2024 | $35.76 | $25.60 | $61.36 |
| LABORER (HEAVY & HIGHWAY): GROUP 3 ALL ROCK OR DRILL MACHINE OPERATORS (EXCEPT QUARRY MASTER AND SIMILAR TYPE); ACETYLENE TORCH OPERATOR; ASPHALT RAKER; POWDERMAN Footnote A below | LABO0785-018 07/01/2024 | $35.96 | $25.60 | $61.56 |
| LABORER (HEAVY & HIGHWAY): GROUP 4 BLASTERS; FORM SETTERS; STONE OR GRANITE CURB SETTERS Footnote A below | LABO0785-018 07/01/2024 | $36.16 | $25.60 | $61.76 |
| LABORER (HEAVY & HIGHWAY): GROUP 5 HAZARDOUS WASTE REMOVAL Footnote A below | LABO0785-018 07/01/2024 | $38.76 | $25.60 | $64.36 |
| LABORER GROUP 1 (HEAVY & HIGHWAY:) LABORERS; FLAGGERS; OUTBOARD AND HAND BOATS | LABO0785-018 07/01/2024 | $35.56 | $25.60 | $61.16 |
| MARBLE MASONS, TILE LAYERS AND TERRAZZO WORKERS: BUILDING CONSTRUCTION (ITHACA CHAPTER) | BRNY0003-006 07/01/2025 | $33.68 | $29.89 | $63.57 |
| PAINTERS: (BRUSH & ROLL EPOXY) | PAIN0004-014 05/01/2025 | $29.30 | $24.73 | $54.03 |
| PAINTERS: (SANDBLASTING) | PAIN0004-014 05/01/2025 | $29.10 | $24.73 | $53.83 |
| PAINTERS: (SPRAY EPOXY) | PAIN0004-014 05/01/2025 | $29.10 | $24.73 | $53.83 |
| PAINTERS: (SPRAY PAINTING) | PAIN0004-014 05/01/2025 | $29.70 | $24.73 | $54.43 |
| PAINTERS: (SWING & SCAFFOLD, BOSUN CHAIR, STRUCTURAL STEEL, WINDOW PLATFORM) | PAIN0004-014 05/01/2025 | $28.80 | $24.73 | $53.53 |
| PLUMBER, PIPEFITTER, STEAMFITTER (INCLUDING HVAC WORK) | PLUM0267-006 05/01/2019 | $35.51 | $24.57 | $60.08 |
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED), BACKHO...POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED), BACKHOE EXCAVATOR FULL SWING (CAT 212 OR SIMILAR TYPE), BACK FILLING MACHINE, BELT PLACER (CMI TYPE), BLACKTOP PLANT (AUTOMATED), BOOM TRUCK, CABLEWAY, CAISSON AUGER, CENTRAL MIX CONCRETE PLANT (AUTOMATED), CONCRETE CURB MACHINE, SELF PROPELLED, SLIPFORM, CONCRETE PUMP, CRANE, CHERRY PICKER, DERRICKS (STEEL ERECTION), DRAGLINE, OVERHEAD CRANE (GANTRY OR STRADDLE TYPE), PILE DRIVER, TRUCK CRANE, DIRECTIONAL DRILLING MACHINE, DREDGE, DUAL DRUM PAVER, EXCAVATOR (ALL PURPOSE HYDRAULICALLY OPERATED) (GRADALL OR SIMILAR), FRONT END LOADER ( 4 CU. YD. AND OVER), HEAD TOWER (SAUERMAN OR EQUAL), HOIST (TWO OR THREE DRUM), HOLLAND LOADER, MAINTENANCE ENGINEER, MINE HOIST, MUCKING MACHINE OR MOLE PAVEMENT BREAKER(SP) WERTGEN; PB-4 AND SIMILAR TYPE, POWER GRADER, PROFILER (OVER 105 H.P.) QUAD 9, QUARRY MASTER (OR EQUIVALENT), SCRAPER, FIREMAN, FORK LIFT, FORM TAMPER, GROUT PUMP, GUNITE MACHINE, HAMMERS (HYDRAULIC SELF-PROPELLED), HYDRA-SPIKER, RIDE-ON, HYDRAULIC PUMP (JACKING SYSTEM), HYDRO-BLASTER (WATER), MULCHING MACHINE, OILER, PARAPET CONCRETE OR PAVEMENT, SHOVEL, SIDE BOOM, SLIP FORM PAVER, TRACTOR DRAWN, BELTTYPE LOADER, TRUCK OR TRAILER MOUNTED LOG, CHIPPER (SELF FEEDER), TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVEL | ENGI0158-020 07/01/2025 | $55.85 | $33.40 | $89.25 |
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DR...POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED), BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT (NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS, CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED, CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR MOUNTED, FRONT END LOADER (UNDER 4 CU. YD.), GREASEMAN/LUBRICATION ENGINEER, HIPRESSURE BOILER (15 LBS. AND OVER), HOIST (ONE DRUM), HYDRO-AXE, KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS, L.C.M. WORK BOAT OPERATOR, LOCOMOTIVE MIXER (FOR STABILIZED BASE SELFPROPELLED), MONORAIL MACHINE, PLANT ENGINEER, PROFILER (105 H.P. AND UNDER), GRINDER, POST HOLE DIGGER AND POST DRIVER, POWER BROOM (TOWED), POWER HEATERMAN, POWER SWEEPER, REVINIUS WIDENER, ROLLER (GRADE AND FILL), SCARIFIER, RIDE-ON, SHELL WINDER, SKID STEER LOADER (BOBCAT OR SIMILAR), SPAN-SAW, RIDE-ON, STEAM CLEANER, PUG MILL, PUMP CRETE READY MIX CONCRETE PLANT REFRIGERATION EQUIPMENT (FOR SOIL STABILIZATION)ROAD WIDENER, ROLLER (ALL ABOVE SUBGRADE), SEA MULE, SELF-CONTAINED RIDE-ON ROCK DRILL, EXCLUDING AIR-TRACK TYPE DRILL, SKIDDER, TRACTOR WITH DOZER AND/OR PUSHER, TRENCHER. TUGGER HOIST, VERMEER SAW (RIDE ON, ANY SIZE OR TYPE), WINCH, WINCH CAT | ENGI0158-020 07/01/2025 | $54.97 | $33.40 | $88.37 |
| POWER EQUIPMENT OPERATORS: GROUP 3 | ENGI0158-020 07/01/2025 | $51.69 | $33.40 | $85.09 |
| POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES Footnote A below | ENGI0158-020 07/01/2025 | $65.51 | $33.40 | $98.91 |
| POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER Footnote A below | ENGI0158-020 07/01/2025 | $60.35 | $33.40 | $93.75 |
| POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW Footnote A below | ENGI0158-020 07/01/2025 | $58.85 | $33.40 | $92.25 |
| POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC Footnote A below | ENGI0158-020 07/01/2025 | $57.20 | $33.40 | $90.60 |
TRUCK DRIVER GROUP 1 YARDMAN; PICKUPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS (STRAIGHT JOBS); SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN, TANDEMS; BATCH TRUCK; MECHANICS; ...TRUCK DRIVER GROUP 1 YARDMAN; PICKUPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS (STRAIGHT JOBS); SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN, TANDEMS; BATCH TRUCK; MECHANICS; SEMI- TRAILORS; LOW-BOY TRUCKS; ASPHALT DISTRIBUTOR TRUCKS; AGITATOR; MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES; TRUCK MECHANIC; FUEL TRUCK | TEAM0317-006 06/01/2025 | $35.48 | $31.58 | $67.06 |
TRUCK DRIVER GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRADDLE (ROSS) CARRIER; SELF-CONTAINED CONCRETE MOBILE UNIT; OFF-HIGHWAY...TRUCK DRIVER GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRADDLE (ROSS) CARRIER; SELF-CONTAINED CONCRETE MOBILE UNIT; OFF-HIGHWAY TANDEM BACK DUMP; TWIN ENGINE EQUIPMENT; DOUBLE-HITCHED EQUIPMENT WHERE NOT SELF-LOADED | TEAM0317-006 06/01/2025 | $35.83 | $31.58 | $67.41 |
Footnotes in NY20260024 (5)
- ELEC1249-003 A: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY
- ELEC1249-004 A: PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY
- ENGI0158-020 A: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
- LABO0785-018 A: PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
- TEAM0317-006 A: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY
Questions about these rates
What is the Davis-Bacon rate for electricians on highway work in Tompkins County?
What is the Davis-Bacon rate for plumbers on highway work in Tompkins County?
What is the Davis-Bacon rate for carpenters on highway work in Tompkins County?
Which wage determination applies to my project?
What counts as highway construction?
What if my worker's trade is not on the list?
Using these rates on a WH-347
Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.
Make this week's WH-347 with NY20260024
Other counties: all New York counties · WD lookup
Your first certified payroll is free.