Davis-Bacon wage rates · Pennsylvania

Monroe County residential construction wage rates

Federal prevailing wage rates for residential construction in Monroe County, Pennsylvania, from the wage determination SAM.gov lists for this county. Rates are shown exactly as published.

Data from SAM.gov, fetched October 7, 20261 wage determination
Wage determination
PA20260037
Modification
2
Published
May 18, 2026
Classifications
34
Other types here
Building, Heavy, Highway

These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See Pennsylvania prevailing wage for how the two fit together.

WD PA20260037, Mod 2

Make a WH-347 with these rates
Published May 18, 2026 34 classifications Covers 1 county Types: Residential Source: SAM.gov

Scope as published: Including Tobyhanna Army Depot

Davis-Bacon rates in PA20260037 Mod 2, published 05/18/2026. Total is base plus the hourly fringe printed in the WD; footnote benefits (paid holidays, vacation) are extra and listed below the table.
ClassificationRate IDBaseFringeTotal / hour
ASBESTOS WORKERS/INSULATOR (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS) ASBE0038-004
07/01/2025
$39.18 $26.07 $65.25
BOILERMAKER BOIL0013-006
01/01/2025
$55.00 $35.48 $90.48
BRICKLAYER, STONEMASON (EXCEPT TOBYHANNA) BRPA0005-040
05/01/2016
$32.39 $16.06 $48.45
BRICKLAYER, STONEMASON (TOBYHANNA ARMY DEPOT) BRPA0005-022
05/01/2022
$37.07 $18.82 $55.89
CARPENTER & SOFT FLOOR LAYER CARP0261-006
06/01/2018
$28.02 $12.59 $40.61
CEMENT MASON/CONCRETE FINISHER (REMAINDER OF COUNTY) PLAS0592-002
06/01/2023
$37.13 $14.30 $51.43
CEMENT MASON/CONCRETE FINISHER (TOBYHANNA ARMY DEPOT) PLAS0592-021
06/01/2023
$37.13 $14.30 $51.43
ELECTRICIAN (BARRETT, COLLBAUGH, PARADISE, PRICE, AND TOBYHANNA TOWNSHIPS) ELEC0081-007
06/01/2025
$23.82 $16.66 $40.48
ELECTRICIAN (REMAINDER OF COUNTY) ELEC0102-009
06/03/2024
$63.38 $40.25 $103.63
ELEVATOR MECHANIC Footnote A, B below ELEV0084-002
01/01/2025
$61.41 $38.44 $99.85
IRONWORKERS: (STRUCTURAL & ORNAMENTAL) IRON0404-025
07/01/2024
$37.26 $32.63 $69.89
LABORER: GROUP 1 CLEANING, SCRUBBING, WASHING AND POLISHING OF FLOORS, FURNITURE AND WINDOWS, STRIPPING, DISMANTLING, OILING AND MOVING OF CONCRETE FORMS, LOADING, UNLOADING AND CARRYING OF REINFORCED...LABORER: GROUP 1 CLEANING, SCRUBBING, WASHING AND POLISHING OF FLOORS, FURNITURE AND WINDOWS, STRIPPING, DISMANTLING, OILING AND MOVING OF CONCRETE FORMS, LOADING, UNLOADING AND CARRYING OF REINFORCED STEEL, HANDLING AND DISTRIBUTION OF LUMBER OF ALL OTHER BUILDING MATERIALS, UNLOADING, CARRYING, DISTRIBUTING AND LAYING OF PRE- CAST CONCRETE SLABS AND PLANKS IN ACCORDANCE WITH DECISIONS OF RECORD, WRECKING, MOVING AND DEMOLISHING, UNDERPINNING AND SHORING OF ALL STRUCTURES, SIGNAL PERSON AND FLAG PERSON, LANDSCAPING AND NURSERY WORK, TOOLROOM PERSON, OPERATORS OF SALAMANDERS, SMUDGE POTS, PROPANE GAS AND KEROSENE BURNERS AND ALL OTHER HEATING METHODS. CLEANING OF PRECIPITATORS, OPERATING OF JACKHAMMERS, BUSTERS, DRILLS AND ALL OTHER PNEUMATIC AND ELECTRIC HAND TOOLS, WAGON DRILLS, AIR AND HYDRAULIC, ON OR OFF TRACKS, POWER BUGGIES, CONCRETE MIXERS, PUMP AND VIBRATORS, WALK- ALONG COMPACTING EQUIPMENT, VIBRATING AND TAMPING, GUNNITING MACHINES (INCLUDING THE NOZZLE), OPERATION OF STEAM JENNIES, SANDBLASTING (FILLING THE POT, CLEANING UP OF SAND, USE OF NOZZLE), PUMPS 2: OR UNDER CONVEYORS, VACUUM CLEANERS, ALL TYPES (RIDE OR WALK-ALONG), CONCRETE SAWS AND CUTTING EQUIPMENT, BURNING AND WELDING TORCHES, DYNAMITE BLASTERS AND BLASTER TENDERS, SWING SCAFFOLDS, SLINGS AND BOSUN CHAIRS. LAYING OF NON-METALLIC (CLAY, IRONSTONE, TERRA COTTA, VITRIFIED CONCRETE AND PLASTIC) PIPE AND MAKING OF JOINTS FOR SAME, WALK-ALONG LIFTS AND SIMILAR MACHINES, POURING AND PLACING OF ALL CONCRETE AND RELATED MATERIALS, ALL CONCRETE CURING APPLICATIONS
LABO1174-005
05/01/2016
$24.54 $17.14 $41.68
LABORER: GROUP 2 ASBESTOS REMOVAL, HAZARDOUS AND TOXIC WASTE REMOVAL, ALL WORK IN CONNECTION WITH HANDING, CONTROL, REMOVAL, ABATEMENT, ENCAPSULATION OR DISPOSAL OF ASBESTOS AND/OR TOXIC WASTE WILL BE...LABORER: GROUP 2 ASBESTOS REMOVAL, HAZARDOUS AND TOXIC WASTE REMOVAL, ALL WORK IN CONNECTION WITH HANDING, CONTROL, REMOVAL, ABATEMENT, ENCAPSULATION OR DISPOSAL OF ASBESTOS AND/OR TOXIC WASTE WILL BE ASSIGNED TO THE MEMBER OF THE LABORERS' INTERNATIONAL UNION OF NORTH AMERICA NOT TO BE LIMITED TO THE ERECTION, MOVING, SERVICING AND DISMANTLING OF ALL TOOLS AND EQUIPMENT NORMALLY USED IN THE HANDLING, CONTROL, REMOVAL OR ENCAPSULATION OF HAZARDOUS MATERIAL, THIS AGREEMENT COVERS WORK TASKS ASSOCIATED WITH ANY AND ALL SAFETY REQUIREMENTS AND FINAL CLEAN-UP AND DISPOSAL OF SUCH HAZARDOUS WASTE MATERIAL
LABO1174-005
05/01/2016
$25.57 $17.14 $42.71
LABORER: GROUP 3 MASON TENDERS, MIXING OF MORTAR, PLASTER AND MORTAR PUMPS, PLASTER TENDERS, CAISSON WORK, BLAST FURNACES, COKE OVENS AND ALL RELATED WORK, ERECTION AND DISMANTLING OF ALL SCAFFOLDING,...LABORER: GROUP 3 MASON TENDERS, MIXING OF MORTAR, PLASTER AND MORTAR PUMPS, PLASTER TENDERS, CAISSON WORK, BLAST FURNACES, COKE OVENS AND ALL RELATED WORK, ERECTION AND DISMANTLING OF ALL SCAFFOLDING, INCLUDING TUBULAR FRAME, MANUAL AND POWERED CLIMBING SCAFFOLD, SWING SCAFFOLDS, SLINGS, BOSUM CHAIRS, AND ALL ASSOCIATED SAFETY PROTECTION INCLUDING BARRICADES, NETS AND ROPES, SCAFFOLD WEATHER ENCLOSURES; SHORING; MORTAR BUGGIES; CONCRETE PUMPS; WALK-BEHIND FORKLIFTS; ELECTRIC WELDERS TORCHES, COMPRESSORS, GENERATORS AND THE REPAIR AND MAINTENANCE OF SAME; JACKHAMMERS, TAMPERS; CUT-OFF SAWS & OTHER POWER EQUIPMENT REQUIRED FOR DEMOLITION; ROTARY-HAMMER DRILLS, ELECTRIC & PNEUMATIC HAND-TOOLS; TRANSIT, LEVELS & LASERS; TEMPERING MOTAR; STOCKING SCAFFOLDS WITH MASONRY MATERIALS INCLUDING BRICK, BLOCK, MORTAR, TEERA COTTA, ARCHITECTURAL PRE-CAST CONCRETE, NATURAL STONE, INSULATION & MASTIC, FLASHING, ANCHORS & TIES, GROUNT; MOBILE LIFTING PLATFORM SCAFFORING POWERED BY ANY POWER MODE OR METHOD; CLEANING OF ALL MASONRY DEBRIS
LABO1174-005
05/01/2016
$25.34 $17.14 $42.48
LABORER: GROUP 4 SKID-STEERING LOADER AND FOLKLIFT LABORERS. OPERATION OF ROUGH TERRAIN FORKLIFTS, SKID-STEERING LOADERS LABO1174-005
05/01/2016
$25.34 $17.14 $42.48
PAINTERS: (BRUSH AND ROLLER) PAIN0021-013
05/01/2021
$29.02 $21.14 $50.16
PAINTERS: SPRAY PAIN0021-013
05/01/2021
$30.02 $21.14 $51.16
PLASTERER (REMAINDER OF COUNTY) PLAS0592-002
06/01/2023
$37.81 $13.70 $51.51
PLASTERER (TOBYHANNA ARMY DEPOT) PLAS0592-021
06/01/2023
$37.81 $13.70 $51.51
PLUMBER AND STEAMFITTER PLUM0524-003
12/01/2025
$51.69 $27.07 $78.76
POWER EQUIPMENT OPERATOR: GROUP 1 MACHINES DOING HOOK WORK, ANY MACHINE HANDLING MACHINERY, CABLE SPINNING MACHINES, HELICOPTERS, LULLTYPE FORKLIFT WITH BOOM ATTACHMENT, CONCRETE BOOM. TRUCK, MACHINES...POWER EQUIPMENT OPERATOR: GROUP 1 MACHINES DOING HOOK WORK, ANY MACHINE HANDLING MACHINERY, CABLE SPINNING MACHINES, HELICOPTERS, LULLTYPE FORKLIFT WITH BOOM ATTACHMENT, CONCRETE BOOM. TRUCK, MACHINES SIMILAR TO THE ABOVE INCLUDING REMOTE CONTROL EQUIPMENT
Footnote NOTE below
ENGI0542-020
05/01/2021
$39.87 $27.94 $67.81
POWER EQUIPMENT OPERATOR: GROUP 1A MACHINES DOING HOOK WORK; MACHINES HANDLING MACHINERY; ALL TYPES OF CRANES 15 TON AND OVER FACTORY RATING; CABLEWAYS; DRAGLINES 15 TON AND OVER FACTORY RATING; HIGH ...POWER EQUIPMENT OPERATOR: GROUP 1A MACHINES DOING HOOK WORK; MACHINES HANDLING MACHINERY; ALL TYPES OF CRANES 15 TON AND OVER FACTORY RATING; CABLEWAYS; DRAGLINES 15 TON AND OVER FACTORY RATING; HIGH RAIL/BURRO CRANE 15 TON AND OVER FACTORY RATING; RAIL LOADER (WINCH BOOM TYPE) 15 TON AND OVER FACTORY RATING; CONCRETE PUMPS 145 FEET OF BOOM LENGTH OR LESS (150 YARD POUR, OR LESS); MACHINES SIMILAR TO AVOE, INCLUDING REMOTE CONTROL EQUIPMENT
Footnote NOTE below
ENGI0542-020
05/01/2021
$42.12 $28.60 $70.72
POWER EQUIPMENT OPERATOR: GROUP 2 ALL TYPES OF CRANES (EXCEPT CRANES DOING HOOK WORK) BACKHOES, CABLEWAYS, DRAGLINES, KEYSTONES, SHOVELS, DERRICKS, TRENCH SHOVELS, TRENCHING MACHINES, HOIST WITH TWO T...POWER EQUIPMENT OPERATOR: GROUP 2 ALL TYPES OF CRANES (EXCEPT CRANES DOING HOOK WORK) BACKHOES, CABLEWAYS, DRAGLINES, KEYSTONES, SHOVELS, DERRICKS, TRENCH SHOVELS, TRENCHING MACHINES, HOIST WITH TWO TOWERS, PAVERS 21E AND OVER, OVERHEAD CRANES, BUILDING HOISTS (DOUBLE DRUM) GRADALLS, MUCKING MACHINES IN TUNNELS, FRONT END LOADERS, TANDEM SCRAPERS, PIPPIN TYPE BACKHOES, BOAT CAPTAINS, BATCH PLANT OPERATORS CONCRETE DRILLS, SELF-CONTAINED ROTARY DRILLS, FORK LIFTS, 20FT, LIFT AND OVER, SCRAPERS, TOURNAPULLS, SPREADERS, BULLDOZERS AND TRACTORS, ROLLERS (HIGH GRADE FINISHING), MECHANIC-WELDER, MOTOR PATROLS, CONCRETE PUMPS, GREASE TRUCK, DIRECTIONALL DRILL MACHINES 8" AND UP, SKID STEER, HYDRAULIC PIPE PUSHER 8" AND UP, HYDRO AX, ENVIRONMENTAL RECYCLING MACHINE AND GRINDER TYPE MACHINES, LULL TYPE LIFTS MASONRY TENDERS, SHEAR ATTACHED TO MACHINES, GREASE TRUCK, CONCREATE PLACER MACHINE, MACHINES SIMILAR TO THE ABOVE INCLUDING REMOTE CONTROL EQUIPMENT
Footnote NOTE below
ENGI0542-020
05/01/2021
$39.59 $27.85 $67.44
POWER EQUIPMENT OPERATOR: GROUP 2A CRAWLER BACKHOES AND CRAWLER GRADALLS OVER ONE CUBIC YARD FACTORY RATING; HYRAULIC BACHOES OVER ONE CUBIC YARD FACTORY RATING; EQUIPMENT 15 TON AND OVER FACTORY RATI...POWER EQUIPMENT OPERATOR: GROUP 2A CRAWLER BACKHOES AND CRAWLER GRADALLS OVER ONE CUBIC YARD FACTORY RATING; HYRAULIC BACHOES OVER ONE CUBIC YARD FACTORY RATING; EQUIPMENT 15 TON AND OVER FACTORY RATING; MACHINES SIMILAR TO ABOVE, INCLUDING REMOTE CONTROL EQUIPMENT
Footnote NOTE below
ENGI0542-020
05/01/2021
$41.84 $28.52 $70.36
POWER EQUIPMENT OPERATOR: GROUP 3 CONVEYORS, BUILDING HOIST (SINGLE DRUM), HIGH OR LOW PRESSURE BOILERS, WELL DRILLERS, ASPHALT PLANT ENGINEERS, DITCH WITCH TYPE TRENCHER, CORE DRILL OPERATORS, FORKLI...POWER EQUIPMENT OPERATOR: GROUP 3 CONVEYORS, BUILDING HOIST (SINGLE DRUM), HIGH OR LOW PRESSURE BOILERS, WELL DRILLERS, ASPHALT PLANT ENGINEERS, DITCH WITCH TYPE TRENCHER, CORE DRILL OPERATORS, FORKLIFT TRUCKS UNDER 20FT. LIFT, FINE GRADE MACHINES, DIRECTIONAL DRILL MACHINE 7" OR LESS, HYDRAULIC PIPE PUSHER 7" OR LESS, SKID-STEER FORKLIFT, MACHINES WITH CONCRETE MIXER ATTACHMENT, MACHINES SIMILAR TO THE ABOVE INCLUDING REMOTE CONTROL EQUIPMENT, MISCELLANEOUS EQUIPMENT OPERATOR
Footnote NOTE below
ENGI0542-020
05/01/2021
$36.87 $27.04 $63.91
POWER EQUIPMENT OPERATOR: GROUP 4 WELDING MACHINES, WELL POINTS, COMPRESSORS, PUMPS, HEATERS, FARM TRACTORS, FORM LINE GRADERS, ROAD FINISHING MACHINES, CONCRETE BREAKING MACHINES, ROLLERS, SEAMAN PUL...POWER EQUIPMENT OPERATOR: GROUP 4 WELDING MACHINES, WELL POINTS, COMPRESSORS, PUMPS, HEATERS, FARM TRACTORS, FORM LINE GRADERS, ROAD FINISHING MACHINES, CONCRETE BREAKING MACHINES, ROLLERS, SEAMAN PULVERZING MIXER, POWER BOOM, SEEDING SPREADER, TIREMAN (FOR POWER EQUIPMENT), GROUT PUMP 4" AND UP, POWER BROOM, POWER SWEEPER, SEEDING SPREADER (SELF-PROPELLED) MACHINES SIMILAR TO THE ABOVE INCLUDING REMOTE CONTROL EQUIPMENT
Footnote NOTE below
ENGI0542-020
05/01/2021
$35.72 $26.72 $62.44
POWER EQUIPMENT OPERATOR: GROUP 5 FIREMAN Footnote NOTE below ENGI0542-020
05/01/2021
$35.27 $26.59 $61.86
POWER EQUIPMENT OPERATOR: GROUP 6 OILERS AND DECK HANDS (PERSONNEL BOATS) Footnote NOTE below ENGI0542-020
05/01/2021
$34.40 $26.32 $60.72
ROOFERS: (SHINGLE) ROOF0030-005
05/01/2024
$34.35 $21.85 $56.20
ROOFERS: (SLATE AND TILE) ROOF0030-005
05/01/2024
$37.35 $21.85 $59.20
SHEET METAL WORKER SHEE0044-005
05/01/2024
$36.13 $30.32 $66.45
TRUCK DRIVER: GROUP 1 FLAT BED TRUCK (SINGLE-AXLE), DUMP TRUCKS (UNDER 10 YDS SINGLE AXLE), STAKE BODY TRCK (SINGLE AXLE), DUMPSTER (SINGLE AXLE) WATER TANK, SPRINKLER TRUCKS, WINCH TRUCKS AND FUEL TR...TRUCK DRIVER: GROUP 1 FLAT BED TRUCK (SINGLE-AXLE), DUMP TRUCKS (UNDER 10 YDS SINGLE AXLE), STAKE BODY TRCK (SINGLE AXLE), DUMPSTER (SINGLE AXLE) WATER TANK, SPRINKLER TRUCKS, WINCH TRUCKS AND FUEL TRUCKS SHALL BE GOVERNED BY THE APPROPRIATE CLASSIFICATION AS LISTED ABOVE
TEAM0229-001
05/01/2025
$41.87 $0.00 $41.87
TRUCK DRIVER: GROUP 2 DUMP TRUCK (OVER 10 YDS), ASPHALT DISTRIBUTORS, TRANSIT MIX (UNDER 5 YDS), TRANSIT MIX (OVER 5 YDS.), FLAT OR STAKE BODY (TANDEM), FUEL TRUCK A-FRAME/WINCH TRUCKS, DRY BATCH TRUC...TRUCK DRIVER: GROUP 2 DUMP TRUCK (OVER 10 YDS), ASPHALT DISTRIBUTORS, TRANSIT MIX (UNDER 5 YDS), TRANSIT MIX (OVER 5 YDS.), FLAT OR STAKE BODY (TANDEM), FUEL TRUCK A-FRAME/WINCH TRUCKS, DRY BATCH TRUCK, TRUCK MOUNTED SWEEPER AND VAC TRUCKS, BUSES, DUMPSTER (TANDEM) WATER TANK, SPRINKLER TRUCKS, WINCH TRUCKS AND FUEL TRUCKS SHALL BE GOVERNED BY THE APPROPRIATE CLASSIFICATION AS LISTED ABOVE
TEAM0229-001
05/01/2025
$41.94 $0.00 $41.94
TRUCK DRIVER: GROUP 3 EUCLID-TYPE, OFF HIGHWAY EQUIPMENT-BACK OR DOUBLE BOTTOM DUMP TRUCKS (OVER 20 TONS), STRADDLE TRUCKS, PUSHER, ARTICULATE DUMPED TRUCKS, LOW BOY TRAILERS, SEMI TRAILERS WATER TANK...TRUCK DRIVER: GROUP 3 EUCLID-TYPE, OFF HIGHWAY EQUIPMENT-BACK OR DOUBLE BOTTOM DUMP TRUCKS (OVER 20 TONS), STRADDLE TRUCKS, PUSHER, ARTICULATE DUMPED TRUCKS, LOW BOY TRAILERS, SEMI TRAILERS WATER TANK, SPRINKLER TRUCKS, WINCH TRUCKS AND FUEL TRUCKS SHALL BE GOVERNED BY THE APPROPRIATE CLASSIFICATION AS LISTED ABOVE
TEAM0229-001
05/01/2025
$42.43 $0.00 $42.43
Footnotes in PA20260037 (3)
  • ELEV0084-002 A: VACATION CREDIT: EMPLOYER CONTRIBUTES 8% BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE AS VACATION PAY CREDIT, AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE.
  • ELEV0084-002 B: EIGHT PAID HOLIDAYS (PROVIDED EMPLOYEE HAS WORKED 5 CONSECUTIVE DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY): NEW YEARS'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERAN'S DAY; THANKSGIVING DAY AND THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY
  • ENGI0542-020 NOTE: A - PAID HOLIDAYS: WASHINGTON 'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERANS DAY; THANKSGIVING DAY AND CHRISTMAS DAY. ***TOXIC/HAZARDOUS WASTE REMOVAL*** ADD 20% TO BASIC HOURLY RATE FOR ALL CLASSIFICATIONS

Questions about these rates

What is the Davis-Bacon rate for electricians on residential work in Monroe County?
On WD PA20260037 Mod 2, published May 18, 2026, the row "ELECTRICIAN (REMAINDER OF COUNTY)" is $63.38 base plus $40.25 fringe, $103.63 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for plumbers on residential work in Monroe County?
On WD PA20260037 Mod 2, published May 18, 2026, the row "PLUMBER AND STEAMFITTER" is $51.69 base plus $27.07 fringe, $78.76 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for carpenters on residential work in Monroe County?
On WD PA20260037 Mod 2, published May 18, 2026, the row "CARPENTER & SOFT FLOOR LAYER" is $28.02 base plus $12.59 fringe, $40.61 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
Which wage determination applies to my project?
The one in your contract. A WD is generally locked in when the contract is awarded (for sealed bids, a modification published at least 10 days before bid opening applies), and later modifications do not change it except in cases such as added out-of-scope work or option extensions. See 29 CFR 1.6(c).
What counts as residential construction?
Single family houses and apartment buildings of no more than 4 stories. The contracting agency picks the construction type; it is written into your contract with the WD. Source: DOL All Agency Memorandum 130.
What if my worker's trade is not on the list?
Work that needs a classification the WD does not list is added after award through a conformance request, which goes through the contracting agency to the Department of Labor (29 CFR 5.5(a)(1)(iii)). Do not use a different classification because its rate looks close.

Using these rates on a WH-347

Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.

Make this week's WH-347 with PA20260037

Other counties: all Pennsylvania counties · WD lookup

Your first certified payroll is free.

Upload last week's payroll, get a checked WH-347 back today.

No card. Same full report, no watermark.