Davis-Bacon wage rates · Texas

Grayson County heavy construction wage rates

Federal prevailing wage rates for heavy construction in Grayson County, Texas, from the wage determinations SAM.gov lists for this county. Rates are shown exactly as published.

Data from SAM.gov, fetched October 7, 20263 wage determinations
Wage determination
TX20260058
Modification
1
Published
May 18, 2026
Classifications
15
Other types here
Building, Residential, Highway

3 wage determinations cover heavy work in Grayson County. They differ by scope (for example landscaping, dredging or part of the county). Use the WD number written in your contract; the scope text under each one says what it covers.

These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See Texas prevailing wage for how the two fit together.

1 of 3: WD TX20260058, Mod 1

Make a WH-347 with these rates
Published May 18, 2026 15 classifications Covers 1 county Types: Heavy Source: SAM.gov
Davis-Bacon rates in TX20260058 Mod 1, published 05/18/2026. Total is base plus the hourly fringe printed in the WD; footnote benefits (paid holidays, vacation) are extra and listed below the table.
ClassificationRate IDBaseFringeTotal / hour
BRICKLAYER SUTX1981-002
03/01/1981
$8.50 $0.00 $8.50
CARPENTER SUTX1981-002
03/01/1981
$7.79 $0.00 $7.79
CONCRETE FINISHER SUTX1981-002
03/01/1981
$8.50 $0.00 $8.50
ELECTRICIAN SUTX1981-002
03/01/1981
$11.43 $0.00 $11.43
IRONWORKER SUTX1981-002
03/01/1981
$10.07 $0.00 $10.07
LABORERS: (COMMON) SUTX1981-002
03/01/1981
$7.25 $0.00 $7.25
LABORERS: FORM SETTERS SUTX1981-002
03/01/1981
$7.25 $0.00 $7.25
LABORERS: PIPELAYERS SUTX1981-002
03/01/1981
$7.50 $0.00 $7.50
MECHANIC (UNDEFINED) SUTX1981-002
03/01/1981
$9.20 $0.00 $9.20
PAINTER SUTX1981-002
03/01/1981
$7.50 $0.00 $7.50
PLUMBERS AND PIPEFITTERS SUTX1981-002
03/01/1981
$10.96 $0.00 $10.96
POWER EQUIPMENT OPERATORS: (CRANES, CLAMSHELLS, BACKHOES, DERRICKS, DRAGLINES, & SHOVEL) SUTX1981-002
03/01/1981
$8.08 $0.00 $8.08
POWER EQUIPMENT OPERATORS: FRONT END LOADERS SUTX1981-002
03/01/1981
$7.25 $0.00 $7.25
POWER EQUIPMENT OPERATORS: MOTOR GRADERS SUTX1981-002
03/01/1981
$9.00 $0.00 $9.00
TRUCK DRIVER SUTX1981-002
03/01/1981
$7.25 $0.00 $7.25

2 of 3: WD TX20260019, Mod 1

Make a WH-347 with these rates
Published May 18, 2026 70 classifications Covers 1 county Types: Heavy Source: SAM.gov

Scope as published: Water and Sewer Lines

Davis-Bacon rates in TX20260019 Mod 1, published 05/18/2026. Total is base plus the hourly fringe printed in the WD; footnote benefits (paid holidays, vacation) are extra and listed below the table.
ClassificationRate IDBaseFringeTotal / hour
AIR TOOL OPERATOR SUTX1992-003
04/10/1992
$7.50 $0.00 $7.50
ASPHALT HEATER OPERATOR SUTX1992-003
04/10/1992
$8.00 $0.00 $8.00
ASPHALT RAKER SUTX1992-003
04/10/1992
$9.00 $0.00 $9.00
ASPHALT SHOVELER SUTX1992-003
04/10/1992
$8.25 $0.00 $8.25
BATCHING PLANT SCALE OPERATOR SUTX1992-003
04/10/1992
$8.50 $0.00 $8.50
BATTERBOARD SETTER SUTX1992-003
04/10/1992
$8.45 $0.00 $8.45
CARPENTER SUTX1992-003
04/10/1992
$9.10 $0.00 $9.10
CONCRETE FINISHER (PAVING) SUTX1992-003
04/10/1992
$9.20 $0.00 $9.20
CONCRETE FINISHER (STRUCTURES) SUTX1992-003
04/10/1992
$8.90 $0.00 $8.90
CONCRETE RUBBER SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
ELECTRICIAN SUTX1992-003
04/10/1992
$11.95 $0.00 $11.95
FLAGGER SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
FORM BUILDER (STRUCTURES) SUTX1992-003
04/10/1992
$8.20 $0.00 $8.20
FORM LINER - PAVING & CURB SUTX1992-003
04/10/1992
$8.50 $0.00 $8.50
FORM SETTER - PAVING & CURB SUTX1992-003
04/10/1992
$8.55 $0.00 $8.55
FORM SETTER-STRUCTURES SUTX1992-003
04/10/1992
$8.10 $0.00 $8.10
LABORERS: (COMMON) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
LABORERS: (UTILITY) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
MECHANIC (UNDEFINED) SUTX1992-003
04/10/1992
$10.00 $0.00 $10.00
OILER SUTX1992-003
04/10/1992
$8.50 $0.00 $8.50
PAINTER (STRUCTURES) SUTX1992-003
04/10/1992
$10.00 $0.00 $10.00
PIPELAYER SUTX1992-003
04/10/1992
$7.45 $0.00 $7.45
PNEUMATIC MORTAR OPERATOR SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
POWER EQUIPMENT OPERATORS: (ASPHALT DISTRIBUTOR) SUTX1992-003
04/10/1992
$7.85 $0.00 $7.85
POWER EQUIPMENT OPERATORS: (ASPHALT PAVING MACHINE) SUTX1992-003
04/10/1992
$8.95 $0.00 $8.95
POWER EQUIPMENT OPERATORS: (BROOM OR SWEEPER OPERATOR) SUTX1992-003
04/10/1992
$8.75 $0.00 $8.75
POWER EQUIPMENT OPERATORS: (BULLDOZER 150 HP OR LESS) SUTX1992-003
04/10/1992
$8.05 $0.00 $8.05
POWER EQUIPMENT OPERATORS: (BULLDOZER OVER 150 HP) SUTX1992-003
04/10/1992
$9.05 $0.00 $9.05
POWER EQUIPMENT OPERATORS: (CONCRETE PAVING CURING MACHINE) SUTX1992-003
04/10/1992
$8.40 $0.00 $8.40
POWER EQUIPMENT OPERATORS: (CONCRETE PAVING FINISHING MACHINE) SUTX1992-003
04/10/1992
$9.05 $0.00 $9.05
POWER EQUIPMENT OPERATORS: (CONCRETE PAVING FORM GRADER) SUTX1992-003
04/10/1992
$9.75 $0.00 $9.75
POWER EQUIPMENT OPERATORS: (CONCRETE PAVING JOINT MACHINE) SUTX1992-003
04/10/1992
$8.00 $0.00 $8.00
POWER EQUIPMENT OPERATORS: (CONCRETE PAVING SAW) SUTX1992-003
04/10/1992
$8.30 $0.00 $8.30
POWER EQUIPMENT OPERATORS: (CONCRETE PAVING SPREADER) SUTX1992-003
04/10/1992
$8.60 $0.00 $8.60
POWER EQUIPMENT OPERATORS: (CRANE, CLAMSHELL, BACKHOE, DERRICK, DRAGLINE, SHOVEL (1.5 CU YD AND OVER)) SUTX1992-003
04/10/1992
$9.80 $0.00 $9.80
POWER EQUIPMENT OPERATORS: (CRANE, CLAMSHELL, BACKHOE, DERRICK, DRAGLINE, SHOVEL (LESS THAN 1.5 CU. YD.)) SUTX1992-003
04/10/1992
$9.10 $0.00 $9.10
POWER EQUIPMENT OPERATORS: (CRUSHER OR SCREENING PLANT) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
POWER EQUIPMENT OPERATORS: (FORM LOADER) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
POWER EQUIPMENT OPERATORS: (FOUNDATION DRILL OPERATOR (TRUCK MOUNTED)) SUTX1992-003
04/10/1992
$10.05 $0.00 $10.05
POWER EQUIPMENT OPERATORS: (FRONT END LOAD (OVER 2.5 CU YD)) SUTX1992-003
04/10/1992
$9.05 $0.00 $9.05
POWER EQUIPMENT OPERATORS: (FRONT END LOADER (2.5 CU YD OR LESS)) SUTX1992-003
04/10/1992
$8.30 $0.00 $8.30
POWER EQUIPMENT OPERATORS: (MIXER (16 CF & LESS)) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
POWER EQUIPMENT OPERATORS: (MOTOR GRADER OPERATOR (FINE GRADE)) SUTX1992-003
04/10/1992
$9.75 $0.00 $9.75
POWER EQUIPMENT OPERATORS: (MOTOR GRADER OPERATOR) SUTX1992-003
04/10/1992
$9.00 $0.00 $9.00
POWER EQUIPMENT OPERATORS: (ROLLER, PNEUMATIC (SELF-PROPELLED)) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
POWER EQUIPMENT OPERATORS: (ROLLER, STEEL WHEEL (PLANT-MIX PAVEMENT)) SUTX1992-003
04/10/1992
$8.10 $0.00 $8.10
POWER EQUIPMENT OPERATORS: (ROLLER, STEEL WHEEL OTHER-FLAT WHEEL OR TAMPING)) SUTX1992-003
04/10/1992
$8.05 $0.00 $8.05
POWER EQUIPMENT OPERATORS: (SCRAPER (17 CU YD & LESS)) SUTX1992-003
04/10/1992
$7.90 $0.00 $7.90
POWER EQUIPMENT OPERATORS: (SCRAPER (OVER 17 CU YD)) SUTX1992-003
04/10/1992
$8.30 $0.00 $8.30
POWER EQUIPMENT OPERATORS: (SELF-PROPELLED HAMMER) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
POWER EQUIPMENT OPERATORS: (SIDE BOOM) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
POWER EQUIPMENT OPERATORS: (TRACTOR (CRAWLER) 150 HP & LESS) SUTX1992-003
04/10/1992
$8.00 $0.00 $8.00
POWER EQUIPMENT OPERATORS: (TRACTOR (CRAWLER) OVER 150 HP) SUTX1992-003
04/10/1992
$8.30 $0.00 $8.30
POWER EQUIPMENT OPERATORS: (TRACTOR (PNEUMATIC) 80 HP & LESS) SUTX1992-003
04/10/1992
$7.35 $0.00 $7.35
POWER EQUIPMENT OPERATORS: (TRACTOR (PNEUMATIC) OVER 80 HP) SUTX1992-003
04/10/1992
$7.40 $0.00 $7.40
POWER EQUIPMENT OPERATORS: (TRAVELING MIXER) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
POWER EQUIPMENT OPERATORS: (TRENCHING MACHINE, HEAVY) SUTX1992-003
04/10/1992
$8.00 $0.00 $8.00
POWER EQUIPMENT OPERATORS: (TRENCHING MACHINE, LIGHT) SUTX1992-003
04/10/1992
$7.80 $0.00 $7.80
REINFORCING STEEL SETTER (PAVING) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
REINFORCING STEEL SETTER (STRUCT.) SUTX1992-003
04/10/1992
$9.60 $0.00 $9.60
SERVICER SUTX1992-003
04/10/1992
$7.55 $0.00 $7.55
SIGN ERECTOR SUTX1992-003
04/10/1992
$8.30 $0.00 $8.30
SPREADER BOX OPERATOR SUTX1992-003
04/10/1992
$7.30 $0.00 $7.30
TRUCK DRIVERS: (LOWBOY-FLOAT) SUTX1992-003
04/10/1992
$7.90 $0.00 $7.90
TRUCK DRIVERS: (TANDEM AXLE OR SEMI-TRAILER) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
TRUCK DRIVERS: (TRANSIT-MIX) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
TRUCK DRIVERS: (WINCH) SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
TRUCK DRIVERS: SINGLE AXLE, HEAVY SUTX1992-003
04/10/1992
$7.40 $0.00 $7.40
TRUCK DRIVERS: SINGLE AXLE, LIGHT SUTX1992-003
04/10/1992
$7.25 $0.00 $7.25
WELDER SUTX1992-003
04/10/1992
$9.85 $0.00 $9.85

3 of 3: WD TX20260033, Mod 1

Make a WH-347 with these rates
Published May 18, 2026 25 classifications Covers 254 counties Types: Heavy Source: SAM.gov

Scope as published: Dredging projects along the Texas Gulf Coast Area including all public channels, harbors, rivers, tributaries, and the Gulf Intracoastal Waterways

Davis-Bacon rates in TX20260033 Mod 1, published 05/18/2026. Total is base plus the hourly fringe printed in the WD; footnote benefits (paid holidays, vacation) are extra and listed below the table.
ClassificationRate IDBaseFringeTotal / hour
DECKHAND (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
DECKHAND (DREDGE UNDER 16") SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
DERRICK OPERATOR SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
DOZER OPERATOR SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
DREDGE TENDER OPERATOR (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
DREDGE TENDER OPERATOR (DREDGE UNDER 16") SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
FIREMAN (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
FIRST ASSISTANT ENGINEER (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
FIRST COOK (HYDRAULIC DREDGING) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
HANDYMAN (HYDRAULIC DREDGING) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
JANITOR - CABIN PERSON (HYDRAULIC DREDGING) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
LEVERMAN (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
LEVERMAN (DREDGE UNDER 16") SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
MESS PERSON (HYDRAULIC DREDGING) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
OILER (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
OILER (DREDGE UNDER 16") SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
OILER (MARSH BUGGY DRAGLINE) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
OPERATOR (MARSH BUGGY DRAGLINE) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
SECOND ASSISTANT ENGINEER (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
SECOND COOK (HYDRAULIC DREDGING) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
SHOREMAN (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
THIRD ASSISTANT ENGINEER (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
TRUCK DRIVER (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
WELDER (DREDGE 16" AND OVER) SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85
WELDER (DREDGE UNDER 16") SUTX1994-001
01/18/1994
$16.85 $0.00 $16.85

Questions about these rates

What is the Davis-Bacon rate for electricians on heavy work in Grayson County?
On WD TX20260058 Mod 1, published May 18, 2026, the row "ELECTRICIAN" is $11.43 base plus $0.00 fringe, $11.43 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for plumbers on heavy work in Grayson County?
On WD TX20260058 Mod 1, published May 18, 2026, the row "PLUMBERS AND PIPEFITTERS" is $10.96 base plus $0.00 fringe, $10.96 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
What is the Davis-Bacon rate for carpenters on heavy work in Grayson County?
On WD TX20260058 Mod 1, published May 18, 2026, the row "CARPENTER" is $7.79 base plus $0.00 fringe, $7.79 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
Which wage determination applies to my project?
The one in your contract. A WD is generally locked in when the contract is awarded (for sealed bids, a modification published at least 10 days before bid opening applies), and later modifications do not change it except in cases such as added out-of-scope work or option extensions. See 29 CFR 1.6(c).
What counts as heavy construction?
Projects that are not building, residential or highway: for example dams, sewer and water lines, utilities and other civil work. The contracting agency picks the construction type; it is written into your contract with the WD. Source: DOL All Agency Memorandum 130.
What if my worker's trade is not on the list?
Work that needs a classification the WD does not list is added after award through a conformance request, which goes through the contracting agency to the Department of Labor (29 CFR 5.5(a)(1)(iii)). Do not use a different classification because its rate looks close.

Using these rates on a WH-347

Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.

Make this week's WH-347 with TX20260058

Other counties: all Texas counties · WD lookup

Your first certified payroll is free.

Upload last week's payroll, get a checked WH-347 back today.