Davis-Bacon wage rates · Texas

Sterling County highway construction wage rates

Federal prevailing wage rates for highway construction in Sterling County, Texas, from the wage determination SAM.gov lists for this county. Rates are shown exactly as published.

Data from SAM.gov, fetched October 7, 20261 wage determination
Wage determination
TX20260298
Modification
1
Published
May 18, 2026
Classifications
38
Other types here
Building, Residential, Heavy

These are federal Davis-Bacon rates for federally funded or assisted work. State and local public works can have their own prevailing wage rates under state law. See Texas prevailing wage for how the two fit together.

WD TX20260298, Mod 1

Make a WH-347 with these rates
Published May 18, 2026 38 classifications Covers 82 counties Types: Highway Source: SAM.gov

Some rows apply only to an area or zone named in the classification. The area text is printed exactly as published; check it against your project's location before you use a row.

Davis-Bacon rates in TX20260298 Mod 1, published 05/18/2026. Total is base plus the hourly fringe printed in the WD; footnote benefits (paid holidays, vacation) are extra and listed below the table.
ClassificationRate IDBaseFringeTotal / hour
AGRICULTURAL TRACTOR OPERATOR SATX2025-012
11/15/2023
$23.21 $0.00 $23.21
ASPHALT DISTRIBUTOR OPERATOR SATX2025-012
11/15/2023
$23.46 $0.00 $23.46
ASPHALT PAVING MACHINE OPERATOR SATX2025-012
11/15/2023
$21.32 $0.00 $21.32
ASPHALT RAKER SATX2025-012
11/15/2023
$19.58 $0.00 $19.58
BROOM OR SWEEPER OPERATOR SATX2025-012
11/15/2023
$18.10 $0.00 $18.10
CONCRETE FINISHER, PAVING AND STRUCTURES SATX2025-012
11/15/2023
$20.77 $0.00 $20.77
CRANE OPERATOR, HYDRAULIC 80 TONS OR LESS SATX2025-012
11/15/2023
$27.09 $0.00 $27.09
CRANE OPERATOR, LATTICE BOOM 80 TONS OR LESS SATX2025-012
11/15/2023
$24.40 $0.00 $24.40
CRAWLER TRACTOR OPERATOR SATX2025-012
11/15/2023
$22.51 $0.00 $22.51
EXCAVATOR OPERATOR, 50,000 POUNDS OR LESS SATX2025-012
11/15/2023
$24.67 $0.00 $24.67
FLAGGER SATX2025-012
11/15/2023
$14.82 $0.00 $14.82
FORM BUILDER/SETTER, STRUCTURES SATX2025-012
11/15/2023
$22.09 $0.00 $22.09
FORM SETTER, PAVING & CURB SATX2025-012
11/15/2023
$19.44 $0.00 $19.44
FOUNDATION DRILL OPERATOR, TRUCK MOUNTED SATX2025-012
11/15/2023
$32.17 $0.00 $32.17
FRONT END LOADER OPERATOR, 3 CY OR LESS SATX2025-012
11/15/2023
$19.06 $0.00 $19.06
FRONT END LOADER OPERATOR, OVER 3 CY SATX2025-012
11/15/2023
$20.11 $0.00 $20.11
LABORER, COMMON SATX2025-012
11/15/2023
$18.10 $0.00 $18.10
LABORER, UTILITY SATX2025-012
11/15/2023
$18.10 $0.00 $18.10
LOADER/BACKHOE OPERATOR SATX2025-012
11/15/2023
$21.03 $0.00 $21.03
MECHANIC SATX2025-012
11/15/2023
$25.47 $0.00 $25.47
MILLING MACHINE OPERATOR SATX2025-012
11/15/2023
$20.37 $0.00 $20.37
MOTOR GRADER OPERATOR, FINE GRADE SATX2025-012
11/15/2023
$26.74 $0.00 $26.74
MOTOR GRADER OPERATOR, ROUGH SATX2025-012
11/15/2023
$23.08 $0.00 $23.08
OFF ROAD HAULER SATX2025-012
11/15/2023
$18.10 $0.00 $18.10
PAVEMENT MARKING MACHINE OPERATOR SATX2025-012
11/15/2023
$23.48 $0.00 $23.48
PIPELAYER SATX2025-012
11/15/2023
$18.10 $0.00 $18.10
REINFORCING STEEL WORKER SATX2025-012
11/15/2023
$25.70 $0.00 $25.70
ROLLER OPERATOR, ASPHALT SATX2025-012
11/15/2023
$18.76 $0.00 $18.76
ROLLER OPERATOR, OTHER SATX2025-012
11/15/2023
$18.10 $0.00 $18.10
SCRAPER OPERATOR SATX2025-012
11/15/2023
$19.49 $0.00 $19.49
SERVICER SATX2025-012
11/15/2023
$21.31 $0.00 $21.31
SPREADER BOX OPERATOR SATX2025-012
11/15/2023
$18.31 $0.00 $18.31
TRUCK DRIVER LOWBOY FLOAT SATX2025-012
11/15/2023
$23.22 $0.00 $23.22
TRUCK DRIVER, SINGLE AXLE SATX2025-012
11/15/2023
$22.02 $0.00 $22.02
TRUCK DRIVER, SINGLE OR TANDEM AXLE DUMP TRUCK SATX2025-012
11/15/2023
$21.04 $0.00 $21.04
TRUCK DRIVER, TANDEM AXLE TRACTOR WITH SEMI TRAILER SATX2025-012
11/15/2023
$21.91 $0.00 $21.91
WELDER SATX2025-012
11/15/2023
$22.00 $0.00 $22.00
WORK ZONE BARRICADE SERVICER SATX2025-012
11/15/2023
$18.10 $0.00 $18.10

Questions about these rates

What is the Davis-Bacon rate for laborers on highway work in Sterling County?
On WD TX20260298 Mod 1, published May 18, 2026, the row "LABORER, COMMON" is $18.10 base plus $0.00 fringe, $18.10 an hour in total. Your contract's WD and modification govern, so check the WD number in your contract before you pay.
Which wage determination applies to my project?
The one in your contract. A WD is generally locked in when the contract is awarded (for sealed bids, a modification published at least 10 days before bid opening applies), and later modifications do not change it except in cases such as added out-of-scope work or option extensions. See 29 CFR 1.6(c).
What counts as highway construction?
Roads, streets, highways, runways, bridges, parking areas and related work. The contracting agency picks the construction type; it is written into your contract with the WD. Source: DOL All Agency Memorandum 130.
What if my worker's trade is not on the list?
Work that needs a classification the WD does not list is added after award through a conformance request, which goes through the contracting agency to the Department of Labor (29 CFR 5.5(a)(1)(iii)). Do not use a different classification because its rate looks close.

Using these rates on a WH-347

Each worker's line on the WH-347 needs the classification as it appears in the WD, a straight-time rate at least the base rate, and the fringe met in cash, through a bona fide plan, or both (see fringe benefits, with the math). Put the WD number and modification in the header.

Make this week's WH-347 with TX20260298

Other counties: all Texas counties · WD lookup

Your first certified payroll is free.

Upload last week's payroll, get a checked WH-347 back today.

No card. Same full report, no watermark.